Building Code Review Board
Regular MeetingArlington Heights, IL · July 24, 2023
Minutes
BUILDING CODE REVIEW BOARD
MINUTES OF A MEETING BEFORE THE
VILLAGE OF ARLINGTON HEIGHTS
BUILDING CODE REVIEW BOARD
July 24, 2023
MEMBERS PRESENT: ADMINISTRATION PRESENT:
Richard Bondarowicz, Chairman Pro Tem Jorge Torres, Director of Building & Life Safety
Carl Baldassarra Dave Roberts, Division Chief
Pat O’Gorman Fred Alaimo, Plumbing Inspector
Scott Smith Patty LeVee, Recording Secretary
Trustee Jim Tinaglia
SUBJECT: Removal of amendments and adopting the appendices to the basic Building and Fire
Codes.
There being a quorum present, the meeting was called to order at 6:30pm.
APPROVAL OF MINUTES
TRUSTEE TINAGLIA MOTIONED TO APPROVE THE MINUTES OF THE MAY 17, 2023 MEETING OF
THE BCRB. SECONDED BY PAT O’GORMAN, THE MOTION PASSED.
AYES: Mr. Bondarowicz, Mr. O’Gorman, Trustee Tinaglia,
ABSTAIN: Mr. Baldassarra and Mr. Smith (absent from the May 17th meeting).
OLD BUSINESS
Mr. Torres provided an update as to the status of the last meeting regarding Chez Hotel. Mr.
Torres reported progress as the Petitioner has changed their plan. As requested, 50% of the
drywall of the first floor was removed. The property owners are now leading the project, the
prior project manager has been removed. Upon mutual agreement, the inspection responsibility
has been outsourced to FSCI, who will be responsible for all the inspections. Depending on the
result of their inspection of the first floor, they will request more drywall removal on the 2nd, 3rd,
4th and 5th floor. The 6th floor was framed and they will inspect that as well. Plan reviews have
been submitted as requested. This included the fire protection system, the elevator, the full
building permit, and the backup generator. Mr. Torres stated it appears they are going to get
this project moving forward quicker than anticipated.
Mr. Baldassarra asked Mr. Torres why he agreed to allow a 3rd party inspection agency? Mr.
Torres replied that because it was determined that it was to their best benefit as they need more
attention to this project. We are in our peak season and are unable to have our inspectors stay
1
on site 2 to 3 hours for the type of inspections needed, as the owners want to proceed quickly
on this and obtain occupancy. After discussing this option separately with our staffing and then
the owners, all agreed this is a better option and will provide the attention needed.
Mr. Baldassarra asked if we are spot checking the 3rd party? Mr. Torres replied, yes, and noted
we have worked with the 3rd party before. The contract is with the Village, the expense will be
covered by them, as they agreed. This is strictly for the inside of the building, the architectural,
they will not be involved with engineering, or planning etc.
There was further discussion regarding the need to return to this Board and the many counts
brought up at the May 17th meeting. Mr. Torres explained that the relief they were asking for
has nothing to do with Building Code, it was more a relief of errors from working on the project
without approved drawings. The option for a BCRB meeting is always there if they feel the need.
NEW BUSINESS
CH 27 2018 IFC Adopting
Mr. Torres stated that when the 2018 codes were adopted, part of the base code, the appendixes
were not adopted, making it unenforceable. The two appendixes are Appendix B, which is the
fire code requirement and Appendix C, the fire hydrant locations and distribution. This was
referenced and brought to our attention at a meeting as not adopted, therefor we are
recommending adopting these two appendixes.
Mr. Baldassarra asked if recently, have there been any major issues about complying with fire
flow permits in the Village? Mr. Torres stated there has not, however, we do not have anything
to hang our hat on if it comes up down the road. Mr. Baldassarra noted with the Village having
a pretty good water supply, we shouldn’t have trouble unless it is on a dead end.
Mr. Tinaglia asked, if that were to happen, is there language where the Building Code Official
can make adjustments and rule appropriately? Mr. Torres responded, yes, the Village can do
that.
Mr. Roberts stated there are a couple requirements to have them have more fire flow if the
need arises or allow them to have less.
Chapter 23
Removal of Amendments Related to Plumbing Code
Mr. Torres stated next are two amendments to the Plumbing Code. After research by our
plumbing inspector, Mr. Alaimo, it was found we are the only municipality that has these two
amendments. The first is the grease traps. We require the grease traps to always be installed
outside. Through conversation and discussions with other departments as to why this was
adopted, (which was roughly 20 years ago), the intent of this adoption was more for maintenance
issues. Due to having a new maintenance division, Mr. Alaimo and I feel comfortable that with
2
the team we have for maintenance, this can be addressed separately. Why would we overburden
the restaurant owner or the property owner on installing the grease trap outside if it can easily
be installed inside.
Mr. Torres continued stating, the other amendment is in regards to plumbing fixtures. For some
reason, beginning of Covid, we adopted the amendment to require all medical buildings to have
a hand sink in all rooms. Again, we are the only municipality that has this. In discussion with our
previous plumbing inspector, he thought this was primarily because of Covid. Mr. Alaimo, our
current plumbing inspector, had researched this with the CDC and IDPH regarding the need and
intent. They did not know what the intent was but no, this is more of a burden and overkill. Mr.
Torres stated we are comfortable that this is not needed or required, especially since the State
Plumbing Code does not have it there.
Building Regulations – Article II
Mr. Torres stated that lastly, for some reason for mechanical for new systems, we require to
always install a high and low return. Once again, old houses with a mechanical systems that work
perfectly well with the central return, not having a high and low return in each room, we are the
only municipality that has this amendment. We feel that it is not needed. This is getting into the
design of the furnace. Usually, the furnace will manifest its specification, will instruct how many
returns are needed or the design of it will figure that out. Why would we require something that
is overburden or overkill on this particular amendment? Obviously, it is better, it is more
efficient, no question there, but everything can be better. We need to keep in mind that Building
Codes are the minimum standards. We do not need to force the contractor or home remodeling
to do this, it is sometimes not practical. Having concluded, Mr. Torres opened to discussion on
any of these items.
Mr. Baldassarra commented on the first two items, asking are they consistent with the Il State
Plumbing Code? Mr. Alaimo replied that the first two items are amendments to the Code that
we are taking out. Mr. Baldassarra stated, then what we are proposing now will be consistent.
Mr. Alaimo replied, yes, consistent with the Code.
Mr. Baldassarra next commented on the high and low returns and his personal preference is that
he has it and likes it. Discussion on preference for this ensued. Mr. Torres agreed, stating more
quality is better and it is a better design but we are keeping in mind that this is really the minimum
code. Chairman Bondarowicz agrees that it is more efficient but in all of his experience, Arlington
Heights is the one that enforces this. In two of his current homes this is problematic during the
construction.
Chairman Bondarowicz called for any further comments or questions regarding the
amendments.
Mr. Tinaglia commented that it is great and appreciates the research and consideration and
cleaning up of some of these code related matters. There was short discussion on past code
amendments and where we are now.
3
Chairman Bondawowicz called for a motion as to the removal of these amendments.
MR. BALDASSARRA MOVED TO APPROVE, SECONDED BY MR. O’GORMAN, ALL WERE IN
FAVOR.
OTHER BUSINESS
Mr. Baldassarra inquired about the cycle for the next code upgrade. Mr. Torres commented
that this will be discussed next year.
Chairman Bondarowicz commented on the guidelines for the sprinkler requirement for the
systems for domestic tied in for un-engineered floor joists. There was discussion on this
requirement and the threshold of the square footage of the area, using a 10 x 10 furnace room,
for example.
Mr. Torres stated that for the residential and not for fully sprinklered homes, but just a particular
area, it would not be required by a licensed architect to do that drawing, as long as there are
specs of the coverage of the head. Chairman Bondarowicz was seeking clarification to this in
regards to the Village asking for a document that identifies all of the parts and pieces and
obstructions.
Chairman Bondarowicz next commented in regards to height restrictions on single family homes.
This continues to fester and feels we are pretty much the only community with this requirement.
It seems to be in zoning, not building code. Mr. Torres recalled this coming up during a
stakeholder meeting and thought there should be another meeting and follow up on this,
possibly as soon as September.
With no further comment, Chairman Bondarowicz called to adjourn the meeting.
The meeting adjourned at 7:05pm.
4
Agenda
Agenda
Village of Arlington Heights
Building Code Review Board
Commissions Room
33 S. Arlington Heights Rd., AH 60005
July 24, 2023
6:30 PM
I. CALL TO ORDER
II. ROLL CALL
III. APPROVAL OF MINUTES
A. May 17, 2023 Draft Minutes/Chez Hotel
IV. REPORTS
V. OLD BUSINESS
VI. NEW BUSINESS
A. Memo - Removal of amendments and adapting the appendices to
the basic Building and Fire Code.
VII. OTHER BUSINESS
VIII.PUBLIC COMMENT
IX. ADJOURNMENT
Persons with disabilities requiring auxiliary aids or services, such as an
American Sign Language interpreter or written materials in accessible
formats, should contact Erin Mercado, at 33 S. Arlington Heights Road,
Arlington Heights, Illinois 60005, emercado@vah.com or (847)368-5793.
Building Code Review Board
7/24/2023
Item: May 17, 2023 Meeting Minutes/Chez Hotel
Department: Building & Life Safety
ATTACHMENTS:
Description Type
May 17, 2023 Draft Minutes Minutes
DRAFT
BUILDING CODE REVIEW BOARD
MINUTES OF A MEETING BEFORE THE
VILLAGE OF ARLINGTON HEIGHTS
BUILDING CODE REVIEW BOARD
May 17, 2023
MEMBERS PRESENT: ADMINISTRATION PRESENT:
Tom Hutchinson, Chairman Jorge Torres, Director of Building & Life Safety
Richard Bondarowicz Hart Passman, Village Attorney
Pat O’Gorman Elliot Eldridge, Assist. Building Official
Trustee Jim Tinaglia Dave Roberts, Division Chief
Patty LeVee, Recording Secretary
Other: James Cazares, Barry Berk, Danielle Bilotto, Krystyna Cazares, Tony Cazares, Ewa Cazares, Tom
McCormack, Enrique Casper, Barbara Dettmer , Michelle Houmpavlis
SUBJECT: 519 W Algonquin Rd – Petition for Appeal and Modification
There being a quorum present, the meeting was called to order at 6:32pm.
APPROVAL OF MINUTES
CHAIRMAN HUTCHINSON MOVED TO APPROVE THE MAY 11, 2022 MINUTES OF THE BCRB.
ALL PRESENT WERE IN FAVOR
AYES: Mr. Hutchinson, Mr. Bondarowicz, Mr. O’Gorman, Trustee Tinaglia,
ABSENT: Mr. Baldassarra and Mr. Smith
NEW BUSINESS
Chez Hotel, 519 W Algonquin Rd, Petition for Appeal and Modification
Mr. Passman (Attorney for the Village of Arlington Heights) introduced himself and shared with
the Board a copy of the Village Code provisions that govern the BCRB. Specific mention to
powers, regulations and responsibilities of the BCRB was noted and the procedure of the meeting
was explained. Mr. Passman noted that the application was received in April, with VIII Counts, a
second revised application was received Thursday introducing a IX Count. Being there was not
enough time to respond, the meeting tonight is for the VIII Counts from the initial application.
Mr. Berk (Attorney for Petitioner) introduced himself, representing the applicant and owners at
519 W Algonquin Rd, Chez Hotel. Introductions of attendees were made which included the
owners, family members, their engineer, architect and inspectors, as well as co-counsel.
Mr. Berk presented that Arlington Heights previously treated the Cazares’ very collegially with a
great deal of cooperation and support for this development. They would like to find a way to
return to this kind of relationship as there is a mutual benefit; however, over the last couple of
years, this has changed.
Mr. Berk next described the project. The project is a six story hotel, added to the existing single
story banquet hall building that has two partial basements. The restaurant and the roof top are
planned for the 6th floor of the hotel, which was previously, maybe not the case anymore, but
strongly supported by Arlington Heights. The hotel addition, 1-hr fire rated construction, Type
2A, the existing banquet hall is non-combustible, non-fire rated Type 2B. The building is fully
sprinklered. Construction has been frozen. On January 20, 2023 there was a stop work order
issued. Prior, for whatever reason, commencing in February of 2022, the Village refused to
conduct any further inspections. Prior to that time, they conducted a number of inspections,
including seven rough inspections, which passed.
Mr. Berk explained the Village refused to conduct further inspections (which is an IBC violation).
Under a very difficult situation, they hired ICCI, Ms. Dettmer ’s firm (the Inspector for Chez Hotel)
firm, who conducted over 96 inspections. Barb completed the roughs that were not yet
completed by Arlington Heights. Some months thereafter they proceeded to dry wall. The last
inspection from the Village noted is January 28, 2022. At that time matters went south, he is not
sure why, but a stop work order was entered. The stop work order does not identify any issues
with any of the constructions nor does it say what has to be done in order to remove the stop
work order. Mr. Berk noted this was wrongful and violates the IBC.
Mr. Berk stated the first five floors are fully drywalled. Everything underneath, if not examined
in the set of approved roughs by the Village, were examined and signed off on by ICCI. The 6th
floor is not drywalled. That can be examined if there is a safety concern. There are 200 fire rated
access panels that could be reviewed. For whatever reason, the Village does not want to do that.
Mr. Berk stated his understanding is that the BCRB is an advisory body. He is hopeful that
whatever is advised or recommended to the Trustees would be taken very seriously.
Mr. Berk presented a one page chart to the Board and staff. It is a chart set forth in the Jensen
Hugh report; Jensen Hugh was hired by the Developer to look at the Building. Mr. Berk
proceeded to explain the chart.
Mr. Berk stated they proposed to Mr. Torres that Ms. Dettmer ’s inspections be allowed. It is
understood that under the IBC he has the discretion to do that. Mr. Berk stated that today his
co-counsel and he spoke with Mr. Passman and they started to talk about that perhaps down the
2
line the Village would no longer object to using Ms. Dettmer in some capacity. An agreement
was not reached, there was just a discussion.
Mr. Berk next discussed the VIII Counts as follows:
Count I – Request to utilize Ms. Dettmer ’s firm, ICCI, as a 3rd party inspection firm for the
remainder of the inspections and requests that her prior inspections be ratified.
Count II – Drywall issue, requesting a waiver to remove the fire rated walls and barriers. Asking
that any if any further inspections are deemed necessary, that they be deemed non-destructive.
Requests to reasonably rely upon 96 to 100 inspections by ICCI, to look at the 200 access panels,
to look on the 6th floor and to see where it is at.
Count III – Recission of Stop Work Order. The Stop Work Order, dated January 20, 2023, states
No Inspections. It states nothing else. It does not comply with IBC Section 115.2.
Count IV – Seeks approval of design alternative with regard to the 6th floor patio and bar. It could
also be termed the labor of the Village 3rd Floor rooftop regulation, which he understands is IBC
Table 503. This concept received unqualified support from the prior administration. It would be
a jewel in Arlington Heights and make the Village better, as long as it’s safe. Mr. McCormick’s
(representing Jensen Hugh) report says that it is safe and indicates what needs to be done to
assure that.
Count V – Approval of existing Fire Command Room. Alleged in the verified petition, sworn under
oath by Mr. Cazares, is that the current position of the Command Room was previously approved
by Fire Chief Larson. It is understood that Mr. Torres wants to relocate it to the lobby. The prior
approval was authorized pursuant to IBC Section 104.11. To move it now, creates substantial
hardship and practical difficulty.
Count VI – Request of the approval of the water feeding supply – Section 6.3.1 of the Jensen
Report addresses this very clearly. There is a proposed impairment plan, they believe that the
impairment plan exceeds the standard set forth in the National Fire Protection Association, 25
Chapter 15.
Count VII – Request the deferral of the generator installation for 36 months. There is an issue as
to whether or not the generator is even required.
Count VIII – That Thompson Elevator to serve as third party inspection for the elevator
inspections. It is proper pursuant to IBC 110.4.
Count IX – will not be addressed, but respectfully stand on the pleading it was filed and asks for
the record that the choice not to address that is that is just came across six days ago, not be
deemed to waive the relief they are requesting. Mr. Berk wants to make sure it is known there
3
is an amended petition that was filed. Mr. Passman clarified that it was submitted to the Village
but it was not submitted to the Board.
Mr. Berk discussed the violation of the IBC by the Village. Section 110.6 provides “the Building
Official, upon notification, shall, noting, shall is a mandatory not a discretionary term, make the
requested inspections. The Village has refused to inspect since February of 2022. Last record is
January 28, 2022, an electrical rough for the 2nd and 3rd floor. That is a violation of the IBC.
Second violation related to the stop work order, and the drywall. The problem is when the Village
violates the IBC and they won’t do any more inspections, it becomes a very difficult decision and
the Developer is faced with a decision and that is that they hired ICCI. ICCI did 96-98 inspections,
all roughs finished and they did that to make sure it was safe, that is when drywall started, after
the inspections were complete.
Mr. Berk concluded stating we are at a point where the question must be asked; has safety been
prioritized? The answer is yes. Bottom line is that making money by opening an enterprise
beneficial to Arlington Heights and safety are not mutually exclusive. They can and they do co-
exist at Chez Hotel.
Mr. Torres next responded stating that whenever we do a site inspection and the drawings do
not match what is at the site, we do require revised drawings. In December of 2021, it was
noticed that the load bearing walls were not done per the plans. We requested revised drawings.
We allowed them to continue working and we continued scheduling inspections not pertaining
to that area. We did not get a response on the revised drawings until January, 2022, when the
architect decided to change construction type because the section of the code for load bearing
wall would not allow reduction of the 2 hr. to 1 hr. He decided to change construction type. We
went down that path, we submitted the revised drawings for the construction type for 3rd party
review. A few months afterwards, the applicant decided to pull the petition, that they are not
going change the revised drawings, construction type. They are going to keep it the way it is.
After so many months, Mr. Torres informed them that the Village cannot do any inspections
without any approved drawings; however, you can continue working with the exception that you
cannot cover any walls. They were given written notice in March, 2022. The applicant requested
if they can cover the walls and Mr. Torres responded. absolutely not. Legal to legal also made
the comment that they cannot cover the walls, and also made the statement that a 3rd party
inspection will not replace the Village inspections. This is documented in email and included in
the summary presented to the BCRB.
Mr. Torres continued that in November, he attended a training session and met with Ms. Dettmer
who approached him and mentioned she is doing inspections at his Village, for Chez Hotel. Mr.
Torres was not aware of this and explained to her that she is not representing the Village. He
told her we encourage them to hire inspectors for their own construction as an organization but
not to represent the Village. Mr. Torres noted that his and Ms. Dettmer ’s impression was a bit
startled not realizing this was happening; however, through conversation they decided, yes, the
fire rating wall was reduced. Mentioned was using this exception on a high-rise section that
4
would allow the reduction of the load bearing wall. Mr. Torres had said we could do that,
however, you would have to comply with the entire Section now, as it is no longer a midrise, it
would be a high-rise if you want to use that exception.
Mr. Torres explained, this is where we are at. He received a letter from the architect, it was
agreed they will comply to the entire high-rise section to use that exception. One of the
conditions Mr. Torres had was to do a site inspection. Upon site inspection, the first thing noticed
was all walls and ceilings were covered on the 1st floor. At that, he was done and would not
continue to do any more inspection or walk the entire building because, what is he looking at,
everything was covered. It was then Mr. Torres posted a Stop Work Order as no inspection was
scheduled or passed in order to cover the walls and the ceilings.
Mr. Torres responded to the Counts as follows:
Count I – to utilize 3rd party inspection. Per the IBC, Section 110.6, “work shall not be done
beyond point indicated in each successive inspection without first obtaining the approval of the
Building Official.” The definition of approval as stated in the 2009 IBC is: “Acceptable to the Code
Official or authority having jurisdiction.” The Village does not permit 3rd-party inspectors hired
by building permittees to issue the approvals in the place of the Village inspections”. We have
never allowed it, especially without even notifying us. Therefore, Count I, denial for request
modification for the 3rd party inspection firm.
Count II – request for waiver to remove fire rated walls and barriers. Again, Petitioner did not
request modification per IBC Section 110.6 – the Village is unable to perform the required rough
inspection while drywall remains mounted. Installation of drywall prior to successful completion
of a rough inspection is not permitted by the Code. Moreover, the Village did not approve or
retain ICCI as an inspector. Ms. Dettmer ’s inspections are not valid for the Village, there was no
authorization.
Count III – request to rescind wrongful Stop Work Order. The Village position, denial request for
modification. Section 104.3 of the IBC states: “The Building Official shall issue all necessary
notices or orders to ensure compliance within the Code.” Because work continued without
inspection, a Stop Work Order was posted. The Village stopped performing inspections because
it did not have approved drawings that reflect the construction actually performed. The
construction still does not comply with any approved drawings, after 1 ½ years, no approved
drawings.
Count IV –Request for approval of proposed design alternatives under IBC Section 104.11. Denial,
request for modification. Per Section 709.3 of the 2009 IBC, concerning fire rating, “Fire
partitions shall have a minimum fire-resistance rating of 1hr.” However, based on the approved
set of drawings from the Architect dated December 13, 2018, and approved February 8, 2019,
Page T1 – load bearing interior walls needs to be 2hr rating. The permitee did not comply with
this requirement that the approved drawing states.
5
Count V – Request approval of Fire Command Room. Mr. Torres stated that as of now, as of this
day, through FOIA’s and everything else, we have no records of Chief Andrew allowing the Fire
Command Center to be located in the basement. There is no record of that. Per the Code, the
Fire Command Center must be by the main door on the 1st floor. On discussion with the Fire
Chief, that is our request. Since we are using high-rise section, this is mandatory. The approved
drawings did not call that room in the basement a Fire Command Center, it called it a Pump
Room.
Count VI – Request modification of water supply feeding with impairment plan pursuant to IBC
Section 403.3.2. Once again, denial modification. Per Section 403.3.2, the IBC Fire Pump shall be
supplied with connections with at least two watermains. It is the Code; it is the minimum Code.
Count VII – Request for deferred installation of generator for 36 months. We request denial of
the modification. We do require permit plans to be approved and we can discuss the installation
not more than a year. We are willing to work with the applicant but not more than one year,
once the building permit has been approved for the generator.
Count VIII – Request to utilize Thompson Elevator Inspection Service. Mr. Torres explained there
is no problem with that, with the exception they provide approved drawings for a high-rise
elevator. if they want to use that exception of the fire rated wall or load bearing wall. We have
no problem using Thompson, but what are they going to do without approved drawings?
Discussion with Thompson, of which the applicant was emailed, they want to review it as a high
rise because that is the condition that we allowed them to use that fire rating.
Mr. Berk stated, it was not discussed why Ms. Dettmer ’s inspections or reports should not be
considered and so forth. What we heard was a technical recitation of what brings us here tonight.
No willingness to work with the Developer to have a safe facility and to get it open. He was
hopeful to talk through this and find ways things can be done.
Mr. Berk continued noting nothing was said about why it does not make sense to look at 6th floor,
nothing about not examining access panels, nothing about the Stop Work Order showing why it
doesn’t violate the IBC and so forth.
Trustee Tinaglia informed Mr. Berk the BCRB is made up of all professionals, some things
explained, they already understand. He pointed out that nothing said tonight is any derogatory
way towards their credentials or professions. There is usually a reason why something goes
sideways. How did we get here so far down this road without answers as to why this is
happening?
Mr. Bondarowicz asked, who is the general contractor leading this project, who is running this
project as a contractor? Mr. Cazares stated, he is a licensed contractor. He has 20 years of
experience and has built these types of buildings before, he’s built skyscrapers. He has dealt with
these types of projects in the City of Chicago and other municipalities.
6
Trustee Tinaglia explained that when there is a multi-million dollar project like this, there are
things call RFI’s (request for information), there are change orders, there are a number of things
that can happen on every project, and somebody has to answer those before the work goes on.
Example: we want to change the 6th floor to something different than it is. The architect might
do a design drawing for the owner. Then the drawing has to go through proper chain and
eventually get approved by the municipality. It could be as simple as a rating on a wall. When
these things happen, there is always a document called an RFI that somebody has to prepare and
get approved before the work goes on. If there is a question as to whether there is a legitimate
alternative, not a clear-cut answer, often times the Village or Municipality or whoever is
governing the project opinion is sought to make sure it is acceptable when the inspector comes
out. Do we have that, RFI’s and so forth, that states why we changed to a high-rise code because
the fire rating of the bearing wall was changed, and here’s how the plans are changing to
accommodate that unilaterally throughout the whole project, including the generator for the
elevator?
Trustee Tinaglia continued that once you go to high rise, you are adding a generator. No way
around that, it is part of the high-rise code. He asked if they can present RFI’s and change orders.
Ms. Bilotto (co-counsel) stated that Mr. Cazares has stamped and approved plans. It went
through over 20 reviews by Deb Pierce, Master Plan Examiner for the Village, over the course of
over a year. All were stamped and approved. At every line item it listed exactly what was as built
now. At no time did the Village say this is not allowed, there is a problem here, this does not
meet the Code. A person building in the Village relies on the municipality and their expert plan
reviewer, their inspectors, their Building Department to be able to guide through the process and
prevent them from getting to a fully erect building, and now all of the sudden they are finding
out that there are problems.
Ms. Bilotto continued that the fact this is stamped and approved is critical. On top of this, prior
administration, Mr. Lay and Mr. Touloumis, had conversations with Mr. Cazares as to the
differences between a high-rise and a midrise. They have emails between them that state, bring
it down a couple of inches and you won’t have to comply with this, that or the other. Or you
need, this, this and/or generator but you do not need all. We have those emails and there was
communication. It may not be memorialized beyond those emails and beyond the stamped and
approved plans, she is unsure about RFI as it is outside her knowledge base, but they have that.
The new administration came in and started to undo what the old administration had already
approved. It is said that you have the right to rely on someone you believe has the authority to
grant these things, whether right or wrong, granting these exceptions is neither here nor there,
because as a consumer, as a construction person, as a resident, you are relaying on the authority
that they have to grant permission to do xyz. This is what was granted. There were little
variances given to them on the project, which is why we are having the problem where this falls
in between a midrise and a high rise. There is argument over which classification it should be.
Mr. Torres stated the architect designed the building as a midrise not a high rise. The only thing
is that the high-rise came into position of the role is because the fire rating wall that they built;
7
they want to use the exception of a high-rise section. You can use that if it is a high-rise building
only, they did not design it nor was it approved as a high-rise. Mr. Torres acknowledge that Ms.
Bilotto is right, we recommended lowering the height of the building so you would not be
classified as a high-rise and avoid that section. The problem is the architect and the code requires
that if it is a load bearing wall, it has to be 2hr rating. They did not install it as 2hr rating, we
noticed that in December, 2021. That is when they wanted to change construction type, that is
when the architect sent a letter that they want to keep the 1hr rating; however, they will comply
with the entire high-rise section. That is the only time high-rise came into play, it was this year.
Last year, in November, when Mr. Torres spoke with Ms. Dettmer, in December or January, the
architect sent a letter stating, yes, they are going to meet all of the high-rise section or order to
use the exception of the fire rating wall to be reduced from 2hr to 1hr.
Mr. Bondarowicz stated an important turn is that the Village went out for inspection and noticed
that this was not per the plans and requested updated drawings. The date was December, 2021.
What happened with those drawings?
Mr. Torres replied they did not receive any response from the Architect until January, stating yes,
the 1hr rating will work if we change construction type. Mr. Torres said they cannot change
construction type in the middle of construction. They said they would like to do that. They were
told if they want to change construction type, we are going to have to review the entire drawings,
not for the mechanical because that has been inspected and approved, but the entire drawings
for changing construction type.
Mr. Bondarowicz asked if drawing were ever resubmitted. Mr. Torres answered, resubmitted
for change of construction type, yes.
Mr. Cazares stated that was with Mr. Touloumis, the building was originally a high rise. The
Village Board approved the building as a high-rise. It was submitted as a high-rise. They came
back to the Board and modified, made a reduction in rooms at a smaller size. Furthermore, after
meeting with Mr. Touloumis and Mr. Lay, they continued through the process of working through
the entire building and they made modifications in heights. They worked with the past Fire Chief
on the location of where the Fire Command Room and where the panel was going to be. There
were many, many meetings with them, of which Mr. Torres was not part of that. Mr. Torres in
just recently and Mr. Cazares understands that what happened before, Mr. Torres has no record
of that and no understanding. What Mr. Cazares and Mr. Castel (the architect) did and this
building was developed as a high rise, the fire alarm is high-rise compliant. They have so many
high-rise compliant items, and when they made the reduction of 6 inches in the building, some
items were granted, like the generator xyz. And the determination of how it was a high rise, was
from the old Fire Chief of where historically the fire car stops. The fire car stops right by the front
entrance, not in the rear or in the back, or where the soffit is and so forth, this was all done over
4 years ago, hashed through multiple meetings. Everything was memorialized and stamped.
Trustee Tinaglia explained to James that many times, especially on a big project like this, you run
into these bumps and you want to ask for some relief on something. Before you go too far, you
8
come in and get approval on that particular deviation from whatever code issue is in your way.
What it feels like here is that there were a lot of missed opportunities for that over so many
months.
Mr. Cazares said he received those deviations over 5 years ago with the previous administration
and they had multiple meetings over 13 months talking with us and getting variances and
modifications. His understanding is that he already received them. He kindly disagrees, he
received those, it is just that it is not being honored by the current administration.
Trustee Tinaglia corrected the statement noting Mr. Cazares came to the Village Board and got
approve for a high rise. He explained as a Village Board, we have no authority, no inference, no
position to approve something “called a high rise”. You present a drawing, a design that your
architect draws, and it is either this tall or this tall, this many stories or this many units, if it gets
approved it does. There is another level of approval that happens later from Building Code
requirements which is what happens when the drawings get completed. That is Mr. Torres’
Department, the Village Board would have no authority to tell him what it has to be.
Mr. Passman noted that predated him as well. That meeting was in January 2019, that was the
most recent meeting and was purely for zoning approval. He also wanted to make sure it is clear,
as mentioned in the beginning of the meeting, the provision in the Village Code that governs this
process, this is not an adversarial proceeding, this is not Chez Hotel v the Building Department.
What we have from staff is their opinion, position, recommendation on the requested relief. This
is not a situation where you are or the Village Board is to weigh this side is more correct than the
other. The BCRB’s job is to view whether they have met the standards set forth in the Code for
one or more of the Counts of relief they are seeking.
Trustee Tinaglia added, the last thing they want is have an advisory situation. We want you to
be open, we want you to get this done. But what needs to be understood is that none of us here
are going to take sides, we want to make sure that the rules are followed, the project is safe and
where mistakes are made, that maybe there are some ways to correct those, or maybe there are
some ways to adjust, but we cannot set a precedent of allowing things to happen that never
should have happened in the first place.
Ms. Bilotto asked to clarify a point brought up, that is that the prior administration had approved
it and there would be no need to necessarily think otherwise. They had been engaging with Mr.
Torres and Mr. Passman for over a year now, trying to work this out. They were hopeful in
negotiating things. Back in December of 2022, Mr. Cazares did in fact, negotiate the whole 1hr
versus 2hr dry wall and Mr. Torres allowed for 1hr to be compliant. Now we are at this stage,
where the drywall has been installed on 90% of the building and the Village is asking its removal.
Trustee Tinaglia asked if they had an explanation as to why drywall was put up on all of the walls
when, according to Mr. Torres, he was very specific that none should be put up without
inspections from the Village. How did that happen?
9
Ms. Bilotto acknowledged that was one of the things Mr. Torres stated, that they do not allow
3rd party inspections as a Village. They notified Mr. Torres and Mr. Passman multiple times, in
emails and at meetings, via phone call, that their client was going to proceed by hiring Ms.
Dettmer to continue inspections because they would not let us proceed.
Trustee Tinaglia summarized their position being that because our Building Department told you
not to do any more work, and that they were not going to send out any inspectors until some
things were corrected, you went and commissioned another outside source.
Ms. Bilotto said they did not say not to do any work at the time they commissioned her. Trustee
Tinaglia asked, then why did you commission her? Ms. Bilotto said because they were not
inspecting anymore. Mr. Torres refused inspections back in February or January of 2022. It was
around March or April when they retained Ms. Dettmer to continue inspections. At all times they
let them know that inspections were moving forward, that they could not hold up the project, it
is already delayed due to Covid, they were trying to play catch up and move forward with this
project.
Mr. Torres said that on March 29th, 2022, Mr. Cazares asked via email, can we start drywalling,
Mr. Torres response to the email on March 30, 2022, was “definitely not, all rough inspections
have not passed”. On June 21, 2022 there was an email, attorney to attorney, saying, please be
advised the Village will not be performing further inspections until your client provides revised
plans to the Village to determine it will be consistent with Type A construction. Neither a 3 rd
party inspector hired by your client nor ICCI has the authority under the Village Code State law
to administer Village Building Codes. Email on June 21st, from attorney to attorney.
Ms. Bilotto acknowledge this but at the same token stated her client had to make a business
decision to move forward.
Mr. Bondarowicz asked, what inspections were done? You should have thousands of pictures.
Ms. Dettmer, stated that she does not do pictures while doing inspections. Mr. McCormack,
their Engineer, stated he has pictures.
Mr. Bondarowicz suggested, as a group, as in the past, where there are reasonable items to look
at, such as inspection reports and images, we can refine them, spend time on them, come to a
resolution so that we are not ripping apart the building. It may be possible to conclude a
reasonable alternative.
Trustee Tinaglia asked which Code are we going by. When the plans were submitted for the
original permit to the Building Department, were they high-rise or not high-rise? Mr. Cazares
answered, they were originally high rise, yes. Mr. Castel explained, it was a high-rise at first and
explained his processes of changes.
Mr. Torres added, the approval was not a high-rise, it was a mid-rise. There was an agreement
to use the exception if they comply with the entire section, however, the items now in hand is
10
that, since it was approved as mid-rise, the fire protection systems are approved as a mid-rise,
the elevators were approved as a mid-rise, they would have to be reviewed now as a high rise.
Trustee Tinaglia asked if those plans have been redone. Is there a new set of high-rise plans
resubmitted?
Mr. Cazares stated he submitted to the Board and to Jorge with the alternate method of
compliance of what they need to do to bring it up to high rise. The building was designed as a
high rise, it has a high-rise fire alarm, smoke system, ventilation, it has everything there. Some
things were reduced under Mr. Lay and Mr. Touloumis, and they allowed the roof top on the 6th
floor.
Mr. Passman stated, to his understanding, the approved plans under the Building Code was as a
mid-rise in 2018, under the 2009 IBC. When someone comes with building plans, they go through
plan review and they get revised, and there can also be zoning changes. When the plans are
stamped, the project can begin. It was as a mid-rise under the 2009 IBC. Those plans required
construction under Type 1B, which requires a 2hr fire rating for load bearing walls. The Village
identified in late 2021, as Mr. Torres has stated, that all of the load bearing walls were built at a
1hr fire rating. Mr. Passman became involved shortly after in early 2022 and attended several
meetings.
Mr. Passman stated the first phase was the shift to Type 2A which allows a 1hr fire rating. There
was a back and forth over whether the building could be converted to 2A. The option to go to a
high-rise as an issue was identified. There were conversations with Mr. Torres and Mr. Castel
and that became the push, to shift it to a high-rise building. Where we are now, is that the next
step from the Village’s perspective is to submit those drawings.
Mr. Cazares stated, he did submit that and Jorge sent them to B&F for review. B&F never
received the Jensen & Hugh report. Mr. Cazares called them personally, what they received is
not what was submitted. They were sent partial information, and Jorge was picking doing what
he wants and they have been getting nowhere for two years. This is not normal; he has done this
with Chicago and many other places.
Mr. Berk went back to the question – how did we get here, you see the nature of the relationship.
He asked the Board if there is a way with their help and guidance and experience to talk about
what to do, to get back on track and move forward in a way that is safe.
Trustee Tinaglia summarized a scenario would be a new set of drawings, submitted to Jorge
under the high-rise code and everything by Mr. Castel is exactly as it should be, next B&F reviews
it. They make some comments, like, for example, the Fire Command Room, it cannot be in a
basement. It has to be at the front door. How do we get around some of those things?
11
Mr. Cazares stated they would have to come up with some alternate solutions, but you do have
to work with us. Mr. Cazares mentioned his discussions and agreements with Mr. Lay. He stated
it is not a new construction, it is an addition.
Mr. Torres asked to clarify a few items. He stated there several permits involved now. The
building permit was reviewed in house. However, the generator permit and back up permit were
outsourced to B&F, only that permit, only that application, not the regular building drawings.
The regular building drawings are reviewed in house. He believes we are at about 99% of the
“building” permit completed. The generator was outsourced because it is out of our specialty.
We are still talking about the sprinklers and the fire alarm and the elevator. That has not been
reviewed as a high-rise yet. They have an approval as a mid-rise. The drawings have only been
approved as a mid-rise.
Mr. Passman asked what drawings were received since the conversion to a high rise. Mr. Torres
responded, the only drawings he received is for the regular building, architectural drawings, that
we required to come as each section. We received that and are 99% completed. They submitted
a permit application for the generator for the high rise, that was outsourced to B & F. They have
not submitted drawings for the Fire Protection. Mr. Torres stated he has an email by both the
elevator and fire protection system consultants they reviewed as a mid-rise, because it is
designed as a mid-rise. It is not reviewed as a high rise. Trustee Tinaglia stated, it is agreed that
this needs to be done. This has to be reviewed as a high rise.
Mr. Bondarowicz said this sounds like the logical pathway forward is that the Building, the Fire
Suppression System, all of this gets submitted as a high-rise and approved as a high rise. If there
is some minutia within that that is not allowed under the code, such as location in the basement
versus the first floor, that comes to the BCRB to make a recommendation to the Village Board.
Trustee Tinaglia inquired, can Mr. Castel and anyone else involved in the drawings, to get the
high-rise application100% complete. Can that get done? Mr. Cazares again said it is here. The
alternate method of compliance shows what needs to be done.
Trustee Tinaglia stated the general rule is that there are never any inspections, there should
never be any construction, never any demolition, or anything on the job site, without an
approved set of plans. That is the first step.
Ms. Bilotto wanted to clarify and make sure, as we move forward, the request is that additional
high-rise plans be resubmitted. What their concern is that where does this stop. Is there an
ending. If they submit the plans again, the Village has indicated that they are willing to accept
Ms. Dettmer’s past inspections because they were done under a different classification.
Trustee Tinaglia responded, that is when you come back here. He does not believe Mr. Torres
can unilaterally disregard the Code and say what Barb or anybody else has done in the field is
alright, if he believes it is against the Code. This is where the BCRB comes in.
12
Mr. Torres stated that is correct to a degree. Going back to Ms. Dettmer ’s inspections, the way
to do that is to ask for permission first, that the 3rd party is allowed.
Ms. Bilotto wanted to make sure that whether is it a high-rise or a mid-rise or a low rise, the
rough inspections for the electrical, the plumbing, the HVAC, the insulation, they do not change,
whether it is a 1A, 2B or whatever the code classification is. That does not change.
Trustee Tinaglia answered, that is not correct. There are many, many penetrations in party walls,
roof assemblies, floor assemblies, fire rated walls, where they have to do different kinds of
treatments when they penetrate with electric, plumbing or HVAC. There are fusible links and
there are all kinds of things that happen on one type of code versus the other. He suggested
retracting her statement on that.
Mr. Torres added, he cannot do an inspection without approved drawings. To which, Mr.
Bondarowicz stated, bottom line, is that we need a set of plans that is a high rise, complete and
reviewed. If there are issues, come back to the BCRB and they will help try to resolve. At this
point we have a high-rise building and no high-rise plans.
Mr. Torres added, Mr. Cazares did the high-rise section, we did not receive the full drawing, he
has not answered any of the review comments from the generator permit, nor has he submitted
the fire protection and the elevator drawing as a high rise. Mr. O’Gorman said it sounds like that
shouldn’t be a problem because Mr. Cazares stated he has it. Mr. Cazares acknowledged; it is
completed.
Trustee Tinaglia commented that this is encouraging and should be very easy to do. Mr. Cazares
stated that with what they put together, it is almost comical what needs to be done. They have
a high level of safety; it is so minute.
Trustee Tinaglia commented to Mr. Cazares, that is your opinion. The three smoke detectors,
some reflective tape, that is so elementary. Please do not go down that road, because that is
going to produce adversarial conversations. Mr. Torres is professional, and is respective. Let’s
get the drawings so that Mr. Torres can do his job the right way, and let’s not belittle what minutia
is.
Ms. Bilotto asked where the Board would stand as far as, say they resubmit the plans, but then
they are looking at what the next step is and they want to get before this Board right away. They
are concerned about that requirement that Mr. Torres set forth for removal 50% of the 1st floor.
Depending on what that shows, they may have to remove more going up.
Trustee Tinaglia responded; you are going to come back here. Once those plans are reviewed
and approved, Mr. Torres’ department will identify whatever items do not meet code or
whatever items you are looking for relief on, this Board will evaluate those and give our opinions.
If you like our opinions, and it works out fine for you, then you will be on your way after the
Village Board ratifies whatever we say. There is a process that has to be followed. Unlike what
13
happened before, with Ms. Dettmer , no disrespect to her, but you did not ask the Village Building
Official for permission to use her professionalism, in lieu of the Building Department’s
professionalism. That was a huge mistake.
Ms. Bilotto stated that they notified. To which Trustee Tinaglia responded, no one asked you to
notify, you were supposed to get approved before you did that. These are the types of things
you need to avoid.
Mr. Berk agreed, lets submit what is being suggested, see where we are at, and then with the
help and professional assistance of the BCRB, find a way to collegiately move forward. It should
not be adversarial, lets get rid of the adversarial nature, and find a way to safely open the hotel.
Trustee Tinaglia added to Mr. Berk, avoid those mistakes and they will not be in your way.
Referring to Mr. Cazares he said, you cannot go and just do and then ask for forgiveness later.
You have to do this in a way that makes proper sense, through proper code, proper inspections
and proper approvals. You may have done it differently in Chicago, it does not work that way
here.
Mr. Cazares stated he will submit the plans in less than 48 hours for high rise. Mr. Torres stated
again, the drawings that are missing are a full set of drawings showing high rise, generator permit
drawings that show high-rise that have to be approved, the elevator drawings have to be
reviewed again for a high rise, the fire protection system, which is sprinklers and alarm, has to be
submitted and reviewed as a high-rise by a 3rd party.
Chairman Hutchinson added, that he is assuming as a part of this, we are considering allowing
this to move forward without him doing demolition on all of the drywall that is installed. We are
probably going to want to see all of the photographs that construction has.
Mr. Bondarowicz stated that if it looks like it is going down the path of opening 50% of the walls
on the 1st floor to do inspection, he is making a suggestion being, he would get going. Let’s get
this done. Mr. Bondarowicz asked Mr. McCormick (the engineer) if he saw the building before
drywall? Mr. McCormick responded no, he came in two months ago, and he has only seen the
6th floor open and everything that has been after drywall.
Mr. Bondarowicz mentioned it may help us as a group if you have a report in which you are
referencing images. Mr. Berk referenced looking at the 6th floor, comparing to not needing to
see the 1st floor and Mr. Bondarowicz asked that we not go through this again, lets get the
approved set of plans. He noted that there is a lot of liability here. Let’s get the approved plans
and go from there.
Mr. Cazares said he has the plans complete; he will submit it to Mr. Torres. He mentioned that
the Village is looking for all mechanical, electrical, plumbing drawings that have already been
installed. Mr. Torres noted, we need full building, not just Section 403 of the high rise.
14
Trustee Tinaglia stated to Mr. Cazares that we need a set of drawings that are signed, sealed by
your Architect, stamped by the Village. That is what we need to make Mr. Torres’ job comfortable
in moving forward.
Mr. Bondarowicz, touching back on one of the Counts, asked what the logic was in deferring 36
months on the generator? Mr. Cazares answered that the problem is, is that the transfer switch
for the fire pump is over 20 something months backordered. We agreed to get the plans, but the
transfer switch itself is not available.
Chairman Hutchinson asked for any other business. Mr. Passman responded that with the
direction he is hearing, they do have a pending application, which is supposed to give
recommendation on.
MR. BONDAROWICZ MADE A MOTION THAT THE CURRENT APPLICATION BE DENIED BASED ON
DISCUSSIONS THIS EVENING. TRUSTEE TINAGLIA SECONDED THE MOTION AND ADDED
COMMENT STATING, WITH THE DIRECTION THAT THE PETITIONER COMPLETE THE TASK
DISCUSSED ALL NIGHT OF COMPLETING A HIGH-RISE APPLICATION.
ALL WERE IN FAVOR.
There was brief discussion where Mr. Torres clarified that this is for denial of the application.
This is the recommendation that will go to the Board.
Trustee Tinaglia concluded that the good news was that the faster you get this in the Building
Departments hands, in a satisfactory way, Mr. Torres will review and we will reconvene here if
necessary for whatever items. Mr. Berk added, to the extent that after that is done, some of the
issues surface again and both sides need your assistance, tonight’s denial is not going to stop you
from doing that. Is that correct? Mr. Bondarowicz stated, what we are doing is we are denying
this particular application.
TrusteeTinaglia suggested to Mr. Cazares that if it were his building and he knew one of the road
blocks was the fact that all of this drywall is up, if I don’t have 1000 pictures of all of the
mechanicals and so forth in there, then I am removing some drywall to invite the inspectors out
to see things. Don’t delay on that. Brief discussion took place regarding inspections.
With no other business, Chairman Hutchinson moved to adjourned.
The meeting adjourned at 8:38pm
15
Building Code Review Board
7/24/2023
Memo - Removal of amendments and adapting the appendices to the basic
Item:
Building and Fire Code
Department: Building & Life Safety
ATTACHMENTS:
Description Type
Removal of amendments and adapting the
appendices to the basic Building and Fire Memorandum
Code
MEMORANDUM
DATE: July 17, 2023
TO: Building Code Review Board
FROM: Jorge Torres, Director of Building & Life Safety
SUBJECT: Removal of amendments and adapting the appendices to the basic Building, Plumbing
and Fire Code
The International Code Council develops construction and public safety codes through a governmental
consensus process. This system of code development has provided the highest level of safety in the world
for more than 90 years. The International Code Council is the largest international association of building
safety professionals. The Code Council is the trusted source of model codes and standards that establish
the baseline for building safety globally and create a level playing field for builders and manufacturers.
International Code Council building safety solutions draw directly from the expertise developed in
authoring the international codes and standards and apply that to product evaluation, accreditation,
certification, codification, training, and technology. Staff believes that basic model code has been tested
for the minimum building codes and is proven to work well.
Section 27-101 Adoption of the 2018 International Fire Code. There is hereby adopted by reference the
2018 Edition of the International Fire Code (IFC), except as modified by Section 27-102 of this Article.
Appendix D is specifically adopted.
Ch 27 2018IFC Adapting:
• Appendix B Fire-flow Requirements
• Appendix C Fire Hydrant Locations & Distribution
By adapting the above, we will be able to enforced as the minimum requirements.
Chapter 23 Removal of Village Amendments:
Section 23-903 Modification by Amendment of Certain Sections of the Illinois Plumbing Code. The Illinois
Plumbing Code adopted by this Article is modified for use in the Village by the following amendments,
which amendments are given section numbers identical to the Illinois Plumbing Code. Subpart E:
Interceptors- Separators and Backwater Valves.
CURRENT
Section 890.510: Grease Interceptor Requirements.
Add the following paragraph after the first paragraph in the section: When a Type 1 Grease Hood is utilized
in a commercial kitchen, as specified in the International Mechanical Code, and external grease trap shall
Page 1 of 3
be required. Minimum external grease trap size as specified in the State of Illinois Plumbing Code of 2014,
Section 890, Appendix E, Subpart E, Illustration B, Typical Grease Trap. Section 890.510(a)(2) Add the
following sentence: Minimum interior grease trap size shall be 50 GPM (gallons per minute) and shall be
installed with removable cover set flush with the finished floor in a readily accessible area for regular
maintenance and inspection. The installation of a (“50 GPM” or “properly sized”) grease trap is required
in any location which contains a Type II grease hood as required in the International Mechanical Code.
PROPOSED
Section 890.510: Grease Interceptor Requirements.
Add the following paragraph after the first paragraph in the section: When a Type 1 Grease Hood is utilized
in a commercial kitchen, as specified in the International Mechanical Code, and external grease trap shall
be required. Minimum external grease trap size as specified in the State of Illinois Plumbing Code of 2014,
Section 890, Appendix E, Subpart E, Illustration B, Typical Grease Trap. Section 890.510(a)(2) Add the
following sentence: Minimum interior grease trap size shall be 50 GPM (gallons per minute) and shall be
installed with removable cover set flush with the finished floor in a readily accessible area for regular
maintenance and inspection. The installation of a (“50 GPM” or “properly sized”) grease trap is required
in any location which contains a Type II grease hood as required in the International Mechanical Code.
This amendment should be removed from the Village Code due to this is more of a maintenance issue not
a plumbing code.
CURRENT
Subpart F: Plumbing Fixtures
Section 890.680 Lavatories. Add the following sentence as the first sentence of the section:
Lavatories/hand sinks are required in all commercial kitchens and examining rooms used by physicians,
dentists, chiropractors and other medical practitioners, as well as massage therapists, aestheticians and
any other business that require direct contact with the skin.
PROPOSED
Subpart F: Plumbing Fixtures
Section 890.680 Lavatories. Add the following sentence as the first sentence of the section:
Lavatories/hand sinks are required in all commercial kitchens and examining rooms used by physicians,
dentists, chiropractors and other medical practitioners, as well as massage therapists, aestheticians and
any other business that require direct contact with the skin.
This amendment should be removed from the Village code the state plumbing code is sufficient.
BUILDING REGULATIONS Article II
Regulations and Standards for One- and Two-Family Dwellings
Section 23-201 Adoption of the 2018 International Residential Code and Appendices for One-and Two-
Family Dwellings. There is hereby adopted by reference the 2018 Edition of the International Residential
Code for One- and Two-Family Dwellings (IRC), including Appendices J, K, M, and O, except as modified by
Section 23-202 of this Article. In the event that a detail of the construction or regulation is not covered by
the 2018 Edition of the International Residential Code, the provisions of Article III of this Chapter shall
apply.
Page 2 of 3
CURRENT
Add: M1602.3 Return air inlets. Unless approved by the Building Official in writing, non-central return air
inlets shall be installed both high and low in each room where return inlets are installed.
PROPOSED
Add:M1602.3 Return air inlets. Unless approved by the Building Official in writing, non-central return air
inlets shall be installed both high and low in each room where return inlets are installed.
This should be removed as it is more of a design factor than code enforcement.
Recommendation:
Staff recommends that that Building Code Review Board recommend to the Village Board the approval
of an amendment to the Arlington Heights Building Code to make the deletions described.
Page 3 of 3