Airport Commission
Regular MeetingBurlington, VT · November 5, 2025
Minutes
PATRICK LEAHY BURLINGTON INTERNATIONAL AIRPORT
AIRPORT COMMISSION
MINUTES OF MEETING
November 5, 2025
Location: The Wright Room
1200 Airport Drive,
South Burlington, VT 05403
[Hybrid meeting] Approved 12/3/25
MEMBERS PRESENT: Tim George
Andrew Savage
Robin Guillian
Chip Mason
Helen Riehle
Jeff Schulman
Connor Daley
MEMBERS ABSENT: None
BTV STAFF PRESENT: Nicolas Longo, Director of Aviation
Larry Lackey, Director of Engineering & Environmental Compliance
Marie Friedman, Director of Finance
Jeff Bartley, Director of Innovation & Marketing
Jesse Sprague, Executive Assistant
David Carman, Deputy Director of Aviation Operations
Madison Reagan, Environmental Compliance and Project Manager
Romeo von Hermann, Customer Experience Manager
OTHERS PRESENT: CCTV
1.0 Call to Order
Airport Commission Chair, Tim George, called the meeting to order at 4:03 PM. Individuals
attending the meeting remotely identified themselves (Andrew Savage, Chip Mason, Jeff Schulman,
Connor Daley, Robin Guillian)
2.0 Agenda
Approve/Adopt Agenda
MOTION by Helen Riehle, SECOND by Robin Guillian, to approve the agenda as presented.
VOTING: unanimous (7-0) motion carried.
3.0 Public Forum
3.1 The following members of the public made public comment, in the below order, regarding
the respective topics:
3.1.1 Leif Taranta – ICE operations at the airport
3.1.2 Gene Bergman – ICE operations at the airport
3.1.3 Sherry Wormser – ICE operations at the airport
3.1.4 Rachel Siegel – ICE operations at the airport, City Council resolution
4.0 Consent agenda:
4.1 Approval of Minutes from the Airport Commission Meeting on October 1, 2025 and October
15, 2025
MOTION by Helen Riehle SECOND by Robin Guillian to approve the items in the consent agenda as
presented in the agenda packet.
VOTING: unanimous (7-0) motion carried.
5.0 Construction Update, L. Lackey
In addition to the written construction update provided to the Airport Commission, Director Lackey
highlighted the following updates:
5.1 Item 4 is moving from design to permitting and construction with a grant application in next
year
5.2 The SRE building will be going out to bid in the next 1-2 weeks
5.3 The new Burlington Tech Center opened to students last week
5.4 Beta Technologies is working to permit a childcare center and new hangar
5.5 Leahy BTV has submitted its first FAA forms regarding the glycol system upgrade
5.6 Leahy BTV is working with the FAA on how to fund the CIP over the next few years
5.7 The proposed project worksheet that the FAA requires was submitted at the end of October
for the grant to complete the 2nd floor renovation and HVAC system.
5.8 The grant for runway 15/33 will have a close out document soon
5.9 Contracts with Pike Industries are being finalized for the Taxiway C-G rehabilitation
6.0 Noise Data
6.1 Noise Data, L. Lackey
In addition to the written construction update provided to the Airport Commission, Director
Lackey highlighted the following:
6.1.1 Phase 1 was submitted to the FAA for closeout
6.1.2 Phase 2 is the next phase to close out
6.1.3 Phase 3 homes have been finished and the acoustical completed
6.1.4 Phase 4 homes are under construction
6.1.5 Phase 5
6.1.6 With the lapse in government funding, the OLDCC is not able to communicate
on programs until their staff returns to office
7.0 Financial Update, M. Friedman
In addition to the written presentation, Director Friedman reported:
7.1 Revenues are similar to last year’s revenues
7.2 Breeze Airways will start paying landing fees and terminal fees, which are waived in their
first two years at Leahy BTV.
7.3 The Airport had its annual audit this week
7.4 Garage rates rose in July ’25 from $12-14, and it the hardware and software system for Flash
Parking will be installed next week.
7.5 The Airport has paid off the T2 equipment; the Flash equipment payment model is similar to
a subscription. The new system comes with new features, including digital pay.
8.0 Director’s Update
In addition to the written presentation, Director Longo reported:
8.1 The first of four new jet bridges has been delivered. These jet bridges will accommodate
large and small aircraft.
8.2 Director Longo presented on the aircraft at the invitation of Education and Enrichment for
Everyone (EEE). The group invites a speaker to present every Friday in South Burlington
8.3 Airport staff attended the Airport Councils international North America and World groups
met in Toronto for their Annual Conference and Exhibition
8.4 The Burlington Technical Center reopened to students with the new renovations.
8.5 The Blue Lightning Initiative trainings will be required for any employee at the airport with a
badge
8.6 TSA employees at Leahy BTV have been coming to work amidst the government shutdown
8.7 Leahy BTV is partnering with Aunt Flow to provide free menstrual products in the female
and family restrooms.
8.8 Fewer aircraft are landing at Leahy BTV, but the planes that do land are carrying more
passengers because they are larger planes.
8.9 October 5-22, there were over 3,000 people through the TSA checkpoint, marking a new
record since 2008.
8.10 There will be a ribbon cutting for the pedestrian/bike path on November 19 at 9:30am.
8.11 Projected passengers are calculated from the scheduled seats that are reported to the
Department of Transportation. The slide reporting ‘Projected Passengers’ presents 80% of the
scheduled seats as a projection of how many seats that come to Burlington will be filled.
8.12 In response to a resolution draft presented to the Airport Commission by Rachel Siegel,
Commissioner Chair Tim George stated that he does not have a response to the resolution at
this time.
9.0 Commissioner Items
9.1 No Commissioner items
10.0 Follow Up Items
10.1 Patrolling of cell phone lot
10.1.1 Director Longo reported that the airport is offering free parking, meaning that
individuals who would normally access the cell phone lot can now pull into the
garage while they wait.
11.0 Adjournment
MOTION by Helen Riehle, SECOND by Chip Mason to adjourn the meeting.
VOTING: unanimous (7-0) motion carried. The meeting was adjourned at 5:11 PM.
Agenda
Airport Commission
Wednesday, November 5, 2025, 4:00 PM, Zoom/Wright Room at the Airport
PLEASE NOTE:
This meeting is will be held on zoom and in-person in the Wright Room at the Airport. Zoom Info:
Join from a PC, Mac, iPad, iPhone or Android device:
Please click this URL to join. https://zoom.us/j/95941583622?pwd=jspMUXkiTTeF3LGU9JkR8vhdYXocQq.1
1. Call to Order
Subject 1.1. Call to Order
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 1. Call to Order
Department
Type
Subject 1.2. Acknowledgement of Remote Commissioners
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 1. Call to Order
Department
Type
2. Agenda
2.1. Motion to amend/adopt agenda
3. Public Forum
Subject 3.1. PUBLIC FORUM - Verbal Comments
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 3. Public Forum
Department
Type
4. Consent Agenda
Subject 4.1. Approval of Minutes
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 4. Consent Agenda
Department
Type
Recommended Action
5. Construction Update
Subject 5.1. Construction Update, L. Lackey
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 5. Construction Update
Department Burlington International Airport
Type
6. Noise Data
Subject 6.1. Noise Data, L. Lackey
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 6. Noise Data
Department Burlington International Airport
Type
7. Financial Update
Subject 7.1. Financial Update, M. Friedman
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 7. Financial Update
Department Burlington International Airport
Type
8. Director's Report
Subject 8.1. Director's Report
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 8. Director's Report
Department
Type
9. Commissioner Items
Subject 9.1. Commissioner Items
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 9. Commissioner Items
Department
Type
10. Follow-up Items
Subject 10.1. Patrolling of the Cell Phone Lot
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 10. Follow-up Items
Department Burlington International Airport
Type
11. Adjournment
Subject 11.1. Motion to adjourn
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 11. Adjournment
Department Council and Board
Type
Recommended Action
12. Informational and Non-Discrimination Statements
Subject 12.1. This agenda is available in alternative formats upon request. For more
information on access, call Lori Olberg, Licensing, Voting and Records
Coordinator (802-865-7136)(TTY 802-865-7142). Persons with disabilities
who require assistance or special arrangements to participate are encouraged
to contact 802-865-7000 (voice) or 802-865-7142 (TTY) at least 72 hours in
advance so that proper arrangements can be made. This meeting will also air
on Town Meeting TV the Wednesday after the meeting, starting at 8:00 pm and
repeating at 1:00 am and 7:00 am the following day. The City of Burlington will
not tolerate unlawful harassment or discrimination on the basis of political or
religious affiliation, race, color, national origin, place of birth, ancestry, age,
sex, sexual orientation, gender identity, marital status, veteran status,
disability, HIV positive status, crime victim status or genetic information.
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 12. Informational and Non-Discrimination Statements
Department Council and Board
Type
Packet
Airport Commission
Wednesday, November 5, 2025, 4:00 PM, Zoom/Wright Room at the Airport
PLEASE NOTE:
This meeting is will be held on zoom and in-person in the Wright Room at the Airport. Zoom Info:
Join from a PC, Mac, iPad, iPhone or Android device:
Please click this URL to join. https://zoom.us/j/95941583622?pwd=jspMUXkiTTeF3LGU9JkR8vhdYXocQq.1
1. Call to Order
Subject 1.1. Call to Order
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 1. Call to Order
Department
Type
Subject 1.2. Acknowledgement of Remote Commissioners
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 1. Call to Order
Department
Type
2. Agenda
2.1. Motion to amend/adopt agenda
3. Public Forum
Subject 3.1. PUBLIC FORUM - Verbal Comments
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 3. Public Forum
Department
Type
Page 1 of 36
4. Consent Agenda
Subject 4.1. Approval of Minutes
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 4. Consent Agenda
Department
Type
Recommended Action
5. Construction Update
Subject 5.1. Construction Update, L. Lackey
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 5. Construction Update
Department Burlington International Airport
Type
6. Noise Data
Subject 6.1. Noise Data, L. Lackey
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 6. Noise Data
Department Burlington International Airport
Type
7. Financial Update
Subject 7.1. Financial Update, M. Friedman
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 7. Financial Update
Department Burlington International Airport
Type
8. Director's Report
Subject 8.1. Director's Report
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 8. Director's Report
Department
Page 2 of 36
Type
9. Commissioner Items
Subject 9.1. Commissioner Items
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 9. Commissioner Items
Department
Type
10. Follow-up Items
Subject 10.1. Patrolling of the Cell Phone Lot
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 10. Follow-up Items
Department Burlington International Airport
Type
11. Adjournment
Subject 11.1. Motion to adjourn
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 11. Adjournment
Department Council and Board
Type
Recommended Action
12. Informational and Non-Discrimination Statements
Subject 12.1. This agenda is available in alternative formats upon request. For more
information on access, call Lori Olberg, Licensing, Voting and Records
Coordinator (802-865-7136)(TTY 802-865-7142). Persons with disabilities
who require assistance or special arrangements to participate are encouraged
to contact 802-865-7000 (voice) or 802-865-7142 (TTY) at least 72 hours in
advance so that proper arrangements can be made. This meeting will also air
on Town Meeting TV the Wednesday after the meeting, starting at 8:00 pm and
repeating at 1:00 am and 7:00 am the following day. The City of Burlington will
not tolerate unlawful harassment or discrimination on the basis of political or
religious affiliation, race, color, national origin, place of birth, ancestry, age,
sex, sexual orientation, gender identity, marital status, veteran status,
disability, HIV positive status, crime victim status or genetic information.
Meeting November 5, 2025 - Airport Commission Meeting - Wednesday, November 5, 2025,
4:00 PM, Zoom/Wright Room at the Airport
Category 12. Informational and Non-Discrimination Statements
Department Council and Board
Page 3 of 36
Type
Page 4 of 36
PATRICK LEAHY BURLINGTON INTERNATIONAL AIRPORT
AIRPORT COMMISSION
MINUTES OF MEETING
October 1, 2025
Location: The Wright Room
1200 Airport Drive,
South Burlington, VT 05403
[Hybrid meeting]
MEMBERS PRESENT: Tim George
Andrew Savage
Robin Guillian
Chip Mason
Helen Riehle
Connor Daley
MEMBERS ABSENT: Jeff Schulman
BTV STAFF PRESENT: Nicolas Longo, Director of Aviation
Larry Lackey, Director of Engineering & Environmental Compliance
Jeff Bartley, Director of Innovation & Marketing
Jesse Sprague, Executive Assistant
David Carman, Deputy Director of Aviation Operations
Madison Reagan, Environmental Compliance and Project Manager
Jillian Waite, Office Assistant
Romeo von Hermann, Customer Experience Manager
Michael Waite, Properties Manager
OTHERS PRESENT: CCTV
VTDigger
1.0 Call to Order
Airport Commission Chair, Tim George, called the meeting to order at 4:05PM. Individuals attending
the meeting remotely identified themselves (Connor Daley, Robin Guillian, Helen Riehle, Chip
Mason)
Page 5 of 36
2.0 Agenda
Approve/Adopt Agenda
MOTION by Chip Mason, SECOND by Andrew Savage, to approve the agenda as presented.
VOTING: unanimous (6-0) motion carried.
3.0 Public Forum
3.1 The following members of the public made public comment, in the below order, regarding
the respective topics:
3.1.1 Michael Holmes—comments regarding parking and safety on streets near the
airport
3.1.2 Rachel Siegel—comments regarding ICE operations at the Airport.
3.1.3 Julie Macuga—comments regarding ICE operations at the Airport.
4.0 Consent agenda:
4.1 Draft Minutes from the Airport Commission Meeting on September 3, 2025
4.2 Communication: Rachel Siegel, re: ‘Burlington Airport Commission Public Forum
Highlights from August 9, 2025’
MOTION by Helen Riehle, SECOND by Andrew Savage to approve the items in the consent agenda
as presented in the agenda packet. This includes items 4.1 and 4.2
VOTING: unanimous (6-0) motion carried.
5.0 Construction Update, L. Lackey
In addition to the written construction update provided to the Airport Commission, Director Lackey
highlighted the following updates:
5.1 Annual meeting with the FAA on the CIP coming up. At the meeting, the agenda includes
reviewing the grants for the next five years. Projects over the next five years and beyond
include: cargo apron construction, SRE building construction, obstruction removal
easements, and Phase 6 RSIP.
5.2 The airport is prioritizing a centralized deicing project in the near future.
5.3 The North Terminal Improvement project received a grant to fund more exit lanes in the
terminal. Majority of the funding would not be eligible for the project costs, so the remaining
amount of the grant will be returned.
6.0 Noise Data
6.1 Noise Data, L. Lackey
6.1.1 In addition to the written construction update provided to the Airport
Commission, Director Lackey highlighted the following:
o Phase 3 housing improvements are almost 100% complete.
o Phase 4 construction has moved forward
o OLDCC has accepted the application for the Airport to get funding for
more RSIP work.
6.2 Noise Comments, J. Sprague
6.2.1 In addition to the written noise comments report, Jesse Sprague highlighted the
following:
o Three new comments on noise in September, bringing the total noise
comments to 835 during the time period June 2021 through September
2025.
Page 6 of 36
7.0 Financial Update, N. Longo
In addition to the written presentation, Director Longo reported:
7.1 This report covers the first two months of FY26.
7.2 Revenues are up, specifically up 12% in the garage.
7.3 Cash balance is just under $4 Million.
7.4 Meeting with OLDCC for the grant funding for the recent grant award will be delayed due to
the government shutdown
7.5 The Airport plans to submit a final reimbursement on the ARPA grant.
8.0 Innovation and Marketing Quarterly Update, J. Bartley
In addition to the written presentation, Director Bartley reported:
8.1 Events, accomplishments, and upcoming initiatives from the Innovation and Marketing
Department, including the Fly By 5k and Blue Light Initiative.
8.2 Leahy BTV is partnering with Hello Burlington and UVM to contract with a national PR firm
for nationwide coverage on Burlington.
8.3 Data collected measuring passenger satisfaction at Leahy BTV, with categories including
TSA experience, cleanliness, parking garage, airline experience, and amenities.
8.4 The Innovation and Marketing team will present updates quarterly
9.0 Director’s Update
In addition to the written presentation, Director Longo reported:
9.1 Most of glass is installed on the concourse level at Project NexT, and the concrete has been
poured for the installation of the jet bridges.
9.2 VTANG hosted a very successful open house in September, with around 6,000 attendees
9.3 Heritage Aviation hosted the Girls in Aviation Day for a group of 5th-8th graders
9.4 Departure numbers are lower, but passenger numbers are higher, which means that larger
aircraft are flying into Leahy BTV.
9.5 Leahy BTV is projecting to have its highest passenger numbers since 2019.
9.6 Area 5 is the Valley West Apron with a grass field in the location.
9.7 Beta Technologies has filed to go public with the Securities and Exchange Commission.
10.0 Commissioner Items
10.1 ICE Airport Updates
10.1.1 The Airport is supporting the Blue Light Initiative and information regarding
how to report human trafficking. The Airport will be installing information
kiosks.
11.0 Follow Up Items
11.1 Chip Mason requested more information regarding TSA’s responsibility to collect
documentation from detainees through the checkpoint.
11.2 Patrolling of cell phone lot
12.0 Adjournment
Page 7 of 36
MOTION by Helen Riehle, SECOND by Connor Daley, to adjourn the meeting.
VOTING: unanimous (6-0) motion carried. The meeting was adjourned at 5:28 PM.
Page 8 of 36
PATRICK LEAHY BURLINGTON INTERNATIONAL AIRPORT
AIRPORT COMMISSION
MINUTES OF MEETING
October 15, 2025
Location: The Wright Room
1200 Airport Drive,
South Burlington, VT 05403
[Hybrid meeting]
MEMBERS PRESENT: Tim George
Andrew Savage
Jeff Schulman
Connor Daley
MEMBERS ABSENT: Helen Riehle
Chip Mason
Robin Guillian
BTV STAFF PRESENT: Nicolas Longo, Director of Aviation
Marie Friedman, Chief Financial Officer
Jesse Sprague, Executive Assistant
OTHERS PRESENT: CCTV
1.0 Call to Order
Airport Commission Chair, Tim George, called the meeting to order at 4:23PM. Commissioners
attending the meeting remotely identified themselves (Connor Daley, Jeff Schulman, Andrew Savage,
Tim George). Director Nic Longo, Marie Friedman, and Jesse Sprague were in person at the Wright
Room.
2.0 Agenda
Approve/Adopt Agenda
MOTION by Connor Daley, SECOND by Jeff Schulman, to approve the agenda as presented.
VOTING: unanimous (4-0) motion carried.
3.0 Public Forum
3.1 No members of the public present.
4.0 Action Items
4.1 Request to Sign a Ground Lease agreement with Beta Technologies
Page 9 of 36
4.1.1 MOTION by Connor Daley, SECOND by Jeff Schulman. to recommend that the
Board of Finance and City Council approve the execution of a ground lease with
Beta Technologies for Area 5 as outlined in the agenda packet.
DISCUSSION, led by Director Nic Longo, included the following:
• Area 5 is about 27,000 square feet on the existing apron. It is on the
Valley West Apron and has been vacant since the apron was
constructed. This space, as well as all available aeronautical spaces,
has been advertised on the Airport’s website.
• The lease term is 30 years with an execution date set to begin when
the lease is signed.
• The lease draft will be updated to show that the lease rate is $0.50
per year per square foot. The rate is consistent with other
leaseholders at the Airport.
• Area 5 is located near Pratt & Whitney’s building on Eagle Drive
• Beta Technologies will pay for construction of the building and after
30 years, the property will be owned by the Airport. The lease
includes capital reserves
• Area 5 is one of several spaces currently available at the Airport.
• The apron adjacent to the proposed hangar will remain available to
the public.
• Beta’s presence on this apron will not impede the ability for other
aircraft to use the apron.
VOTING: unanimous (4-0) motion carried.
5.0 Commissioner Items
5.1 No commissioner items
6.0 Follow Up Items
6.1 No follow up items
7.0 Adjournment
MOTION by Connor Daley, SECOND by Andrew Savage, to adjourn the meeting.
VOTING: unanimous (4-0) motion carried. The meeting was adjourned at 4:47 PM.
Page 10 of 36
To: Airport Commission
From: Larry Lackey, Director of Planning, Engineering and Environmental Compliance
Date: November 5, 2025
Subject: Airport Commission Construction Update
1. Annual Parking Garage Maintenance ($.35M). The replacement of the expansion joints and joint seal
repair in the vicinity of the north and south garage areas has started and is ongoing. This will be
completed by July. Completed.
2. Environmental Assessment (est. $.25M). The purpose of this project is to evaluate environmental
impacts related to the mitigation of obstructions with in the aircraft approach surfaces to the
runways. This is in follow up to the recently completed Master Plan, which includes obstruction
identification and environmental review. Completed, working on close out documents.
3. South Terminal Replacement Project ($35M). The purpose of this project is for overall terminal
efficiencies and a better passenger experience. Due to increased aircraft seating existing passenger
hold areas are overcrowded during peak times as identified in the recent Master Plan Update.
Recently the opportunity had risen through the Airport Terminal Improvement Program from the
Bipartisan Infrastructure Law. We have submitted our request for full build out of this project,
including: Demolition of the existing South Concourse; new Terminal improvements (approximately
45,000 SF of new gross floor area on 2 levels); five (5) new aircraft gates; up to four (4) new passenger
boarding bridges (PBB), new passenger circulation and hold rooms; future concessions space; and
apron construction within demolished South Concourse footprint. The South Terminal Replacement
Project will be approximately 160' farther from Taxiway A as the existing South Concourse. We were
not selected this past year and have reapplied for FFY23 design only. We did receive notice from the
program that we will be awarded the a design only grant for this project. We have finalized discussions
with the FAA to how best move this project forward in the future, as the timing to design this needs to
be pushed back due to FAA scheduling requirement and having the funding to complete the
construction of this project. We have moved forward with schematics and preliminary cost estimates
for existing potential funding source applications.
4. Cargo Apron Construction Project ($4.7M). The purpose of this project is to provide additional space
for other potential cargo carry operations. Have submitted 7460-1 (Air Space Review) to FAA for this
project. The scoping of the he project, design only has been completed with the FAA. The IFE process
for completion before a FAA Grant Application in April has been completed. Grant Application was
Page 11 of 36
November 5, 2025 Airport Commission Construction Update Page 2 of 6
submitted on April 3, 2023. Grant has been issued, moving to finalize contract. The contract has been
issued to Hoyle, Tanner and Associates with the design to start. It has been determined that this
project will require additional FAA technical operations review prior to proceeding. The FAA updated
review has been issued as favorable, and the project design is moving forward. We plan on bidding
this project later this year. Project design is near completion. Working on permit applications. We will
apply for a grant in April of 2026 for construction.
5. SRE Building Design ($1.2M). The purpose of this project is to replace the existing out dated facilities,
which does not meet the storage needs of the required equipment to maintain the airfield. A contract
for study is being completed with programing and scoping moving forward. The scoping session with
the FAA has been completed. The final scope is complete with the IFE process was completed. The
Grant Application was submitted to the FAA. Contract has been signed with Passero Associates to
design and bid this project. Site investigations were completed in November. The site plan is
developed with the building design at 30%. We have had page turn of the draft plans. Applications for
permits are being moved forward. A pre –Application meeting was held with South Burlington
Planning and Development Staff in preparation for an upcoming DRB hearing. Permit Applications are
being prepared. We presented to the South Burlington DRB on June 3rd. The hearing was not closed.
There were items that needed follow up. We have followed up on these items and are scheduled back
with the DRB on July 1, 2025. The SB DRB process has been completed. We have filed for all other
required permits. We plan on advertising for bids for construction of this project in the next 1-2
weeks.
6. Burlington Tech Center (BTC) ($12M). The purpose of this project is to support the design efforts for
an improved facility at the airport for the regional educational needs. The Burlington School district
has been given an award for $10M in which they are in the process of applying for. We continue to
work with the school on this project. Permit applications were submitted on March 25th to the
regulatory bodies for this project. The SB DRB issued there positive decision with follow submittal
needed as agreed during the hearing. DEW was the selected contractor. Construction started
December 4th. The planned completion was August 2025. This project is substantially completed with
students starting on October 28, 2025.
7. FAA CIP for FY26 and next 5 years. We met with the FAA Airports Division on September 17th. Items
discussed for FFY26, cargo apron construction, SRE building construction, obstruction removal
easements, final application to complete project NeXT, RSIP Phase 6 considering receipt of the $7.3M
grant from OLDCC, centralized deicing and the following 5 years. We are working on updated CIP to
reflect the meeting discussions and commitments.
8. BETA – Development
Communication and coordination with Beta on the first phase of the Electric Aircraft Assemble Facility
and Valley West Hangar for all aspects of permitting, environmental, engineering, utilities and
attendance at public hearing and construction meetings. The first Phase is complete. We are
coordinating with Beta on the child care center.
Page 12 of 36
November 5, 2025 Airport Commission Construction Update Page 3 of 6
9. South Apron and TW G Ext. Development ($6.6). The purpose of this project is to provide much
needed additional general aviation apron area on the airfield. Completed, working on closeout
documents.
10. Glycol System Upgrade (est. $3.5M). The purpose of this project is to improve the glycol system (De-
icing). We have had additional follow up discussions with the FAA and it appears this is eligible for
funding and is being added back into our FAA CIP. We have received and reviewed the site evaluation
and process review scope. We brought this for Airport Commission approval last month subsequently,
it was approved by City Council. Study is moving forward. We visited the Syracuse Airport to evaluate
and understand the technology they were using to compare to our Portland Jetport visit. The Draft
study has been issued and is under review by the airport team. A review session with Stantec was
completed. We had a joint meeting last week with our consultant and our FBO Heritage Flight to get
their input. The final report is completed. A 7460 – 1 (Siting review) has been submitted for the siting
of the first site location for review. We are working on our CIP with the FAA, to see how we fund this.
Then we can start scoping the project with the FAA.
11. North Terminal Improvement Project ($2.2M). The purpose of this project is for overall terminal
efficiencies and a better passenger experience due to the completion of the TIP the north terminal will
be upgraded to provide more capacity for passengers and concessions. This includes the removal of
the existing north TSA station along with the removal of the existing escalators. This project is under
design and funding is anticipated from the recent approval of the Infrastructure Law. Received Bids
with the selected bidder being Engelberth Construction, Inc. Preparing and submitting Grant
Application. This will become a FFY23 Project. We have received the Grant from the FAA. Construction
is nearing completion, and should be complete by September 15th. There was a delay related to the
glass for the new restaurant area. Construction is complete with final inspection with the FAA
completed on 10/30/23. Project closeout in process. We have applied for an additional grant to add
additional egress lanes in both the North and South Terminal locations. A grant application was
submitted April 26th to the FAA. Received BOF approval to accept the Grant on June 17, 2024, City
Council to vote on June 25, 2024. Grant has been issued for the two new egress lanes. A review of the
issued funding is being reviewed by the airport on how much money can actually be used from the
grant for this project. This determination is close to being resolved. Due to FAA rules this grant is being
sent back because it does not support the full extent of this project.
12. PROJECT NEXT: North Terminal Replacement Project and New PBB’s ($63M). The purpose of this
project is for overall terminal efficiencies and a better passenger experience. Due to increased aircraft
seating existing passenger hold areas are overcrowded during peak times as identified in the recent
Master Plan Update. Recently the opportunity had risen from Senator Leahy’s office through
Congressional Directed Spending. We have submitted our request for full build out of this project
Phase III Terminal Improvement Project, including: Demolition of the existing North Concourse; new
Terminal Improvement (approximately 25,000 SF of new gross floor area on 2 levels); five (5) new
aircraft gates; six (6) new passenger boarding bridges (PBB), new passenger circulation and hold
rooms; future concessions space; and apron construction within demolished North Concourse
Page 13 of 36
November 5, 2025 Airport Commission Construction Update Page 4 of 6
footprint. Contract for 30% design has been issues to Jacobs Engineering Group. Geo-technical site
work has been completed. Data collection and design currently on going. We submitted to the FAA for
a Construction Manager at Risk (CMAR) RFQ/P construction development process. We received
approval from the FAA on this procurement process. The RFQ/P for CMAR has been advertised with a
pre-bid meeting and site visit by prospective contractors completed. CMAR Proposals received
reviewed and scored. Also, held interviews with the top 3 contractors. This has been scored and we
can let you know the selected contractor at the AC meeting. As reported the CMAR selected is
Engelberth Construction Company. The contract with our design engineer, Jacobs Engineering Group,
is completing the 80% design to move to pricing. We received City Council approval to accept the
Grant on March 25 for this project, as brought for your approval during our last meeting. Our CMAR is
in the process of receiving bids for the final price for this project. The FAA asked us to submit a draft
grant application for administrative review prior to final construction pricing to help us expedite the
grant issuance, with them once final pricing is in. The Draft Application was completed and submitted
on March 27. The FAA grant application was submitted on May 23. Received BOF approval to accept
the Grant on June 17, 2024, City Council to vote on June 25, 2024. We received the Grants for this
project. The work has started and is ongoing the project. We submitted the NeXT Grant Application -
3 with Contractor Change Orders to support the new passenger boarding bridges and the second floor
renovations, on April 28, 2025. This grant was recently received. The jet bridges have been ordered
and the bases are being set. We are working on the final grant application for items that will wrap this
project up. This includes but is not limited to the balance of the second floor renovation, additional
apron and heating and cooling systems.
Conceptual Renderings – North and South Terminal (concourse) Improvements
Page 14 of 36
November 5, 2025 Airport Commission Construction Update Page 5 of 6
13. RW 15 – 33 Improvements – Mill and Overlay (15M). The project is complete, with a few minor punch
list items to be completed. Final inspection was completed with the FAA present. We are moving this
project to close out.
14. Airfield Pavement Plan Update ($.25M). The purpose of this project is to update the outdated
pavement condition report done in 2017. All surfaces will be evaluated so we can plan on future
improvement for the safety of the aircraft users. Scoping has been completed with the FAA. We have
completed the IFE. A Grant Application was submitted on April 3, 2023. Investigations have started,
and the grant has been issued. Moving to finalize contract. The Contract has been issued to HTA with
the investigations being completed. The report is in progress.
15. TW C/G Rehabilitation ($4.6M). The purpose of this project is to improve the pavement condition of
the airport’s taxiway C and intersection at taxiway G. Bids were received on April 24, 2025. We
Page 15 of 36
November 5, 2025 Airport Commission Construction Update Page 6 of 6
received 2 bids. Pike Industries was the lowest most responsive bidder. The FAA Grant Application was
submitted on April 28, 2025. Construction will begin in the spring of 2026. This grant was recently
received. A NOA has been given to the contractor with contract being completed. Contracts are being
reviewed for execution.
16. Obstruction Removal ($0.5M). The purpose of this project is to remove potential obstructions with in
the aircraft approach surfaces to runways 15 and 33. Environmental Assessment is almost complete
with the scoping session with the FAA to be scheduled. FAA Grant Application is pushed back to May
1, 2026. This is due to a review of our existing easement and a determination if others may be
required Construction will begin as soon after grant is issued as possible taking into environmental
conditions. We are moving forward with scoping to review existing and proposed easement.
17. Runway 33 Threshold Bar Improvement Project ($.25M). The purpose of this project is to remove the
damaged navigational aid, replace the lights and rings, and place a quick dry durable concrete for a
longer term fix. This project has been completed and the FAA flight check completed.
18. VTANG Arrester Cable Drainage (Stormwater) Project ($1.5M). This project involves repairing and
modifying the existing Aircraft Arresting Systems (AAS), which are safety mechanisms designed to
rapidly decelerate aircraft during landings or takeoffs by catching the aircraft with cables or barriers.
The improvements will include upgrading the drainage system by adding infiltration galleries and
connecting it to the existing stormwater system, ensuring continued compliance with state and
federal stormwater regulations. Enhancements include upgrading the sump pump capabilities to
establish redundant drainage functions in each barrier pit, updating the control system for flood-level
monitoring, and relocating the Arresting Gear Markers. The AAS at Leahy BTV are the only functioning
systems for this installation and are critical to operations. This project is being completed concurrently
with the Runway 15 – 33 Rehabilitation Project. The project was bid. Engineers Construction, Inc. (ECI)
was selected to complete this work. We have a signed contract from ECI and have received final
documents from VTANG. The contract has been executed by the Airport. The project is complete,
with a few minor punch list items to be completed. Final inspection was completed with VTANG
present. We are moving this project to close out.
Page 16 of 36
Patrick Leahy Burlington International Airport
Board of Commissioners
Sound/Noise Update Report
November 5, 2025
ADDITIONAL INFORMATION IS UPLOADED TO WWW.BTVSOUND.COM
BACKGROUND:
Residential Sound Insulation Programs:
The purpose of the project is to convert a sample of incompatible residential units to a compatible land
use by installing an acoustical treatment package which will provide relief from aircraft noise by
upgrading interior living areas. Upgrades may include replacement of windows and doors with
acoustically rated products and installation or upgrade of ventilation systems. The sound insulation
treatments are designed to reduce the interior noise levels to below 45 DNL and provide a minimum
noise level reduction of 5dB.
PHASES OF THE RESIDENTIAL SOUND INSULATION PROGRAM (RSIP)
1. Sound Insulation Pilot Project (Phase 1) ($1.5M). This Program includes: Program formulation,
Home eligibility determination, project schedule for this Phase 1 portion included 9 properties,
and construction improvements are substantially complete. The close out is ongoing with the
contractor.
2. Residential Sound Insulation Project - Phase 2 ($2.20M) The purpose of the project was to
convert incompatible residential units to a compatible land use by installing an acoustical
treatment package which will provide relief from aircraft noise by upgrading interior living areas
as defined in the Phase 1 project and the Noise Compatibility Program. The Airport continued
implementation of its Residential Sound Insulation Program (RSIP). This grant included:
community outreach, historic review, design and bidding of 52 homes, noise reduction of 6
homes which construction improvements were substantially completed and close out is
ongoing with the contractor. Properties were located within the 70+ DNL FAA accepted 2023
noise contours. The installation of noise reduction materials for the 5 properties was
Page 17 of 36
Page 2 of 6
completed. Materials were purchased for the 6th property however the homeowner left the
area. It will be completed with the next phase of homes. The close out is ongoing with the
contractor.
3. Residential Sound Insulation Project - Phase 3 ($6.2M). The Airport is continued
implementation of its Residential Sound Insulation Program (RSIP) as described in more detail
above. This grant was issued and includes: the construction improvements of the 52 Homes
designed and bid in Phase 2, in addition it provides for community outreach, historic review,
design and bidding of the next approximately 50 homes for improvements. The schedule for
installing the noise insulating improvements for the 52 homes started in 2024. The Construction
Improvements has started on this phase of homes and will continue through September 2025.
See status below as of 20250924:
4. Residential Sound Insulation Project - Phase 4 ($3.9M EST.). The Airport is proposing to
continue implementation of its Residential Sound Insulation Program (RSIP) as described in
more detail above. We are currently reviewing the status of the programing and will be able
to detail this in our next month’s airport commission meeting. The initial grant for 16 of the 50
Page 18 of 36
Page 3 of 6
homes for construction improvements was submitted grant was received from the FAA. Also in
the grant was the funding for the next 50 homes. As discussed we are completing the required
new acoustical testing for the balance of the 50 homes so we can do a follow grant application
on those homes. (See update above) The Buy American process moving forward but awaiting
grant for the 16 homes. We received the grant for this phase however; the amount ($)’s was
slightly less than what the application was. Based on instructions from the FAA we will leave the
scope intact for this project and just amend the grant during closure. The Contact with Strong
Tower to start construction improvements has been signed. The Construction Improvements
has started on this phase of homes and will continue through September 2025. See status
below as of 20250924:
Page 19 of 36
Page 4 of 6
RSIP Phase Status Chart & Timeline
5. Residential Sound Insulation Project - Phase 5 ($2.4M EST.). The Airport is proposing to
continue implementation of its Residential Sound Insulation Program (RSIP) as described in the
first paragraph in this report. It includes the construction improvements of 6 units that remain
in the above 70 DNL contour. Also, due to the change in the FAA acoustical requirement
additional funding is being requested for homes in outreach from Phase 4. We submitted a grant
application to the FAA on April 28, 2025 for this phase. The grant was just recently issued.
Contract documents and submittals are in progress.
Page 20 of 36
Page 5 of 6
Page 21 of 36
Page 6 of 6
6. Noise Exposure Map Updates (NEM) (est. $.85M). The purpose of the Federal Aviation
Administration (FAA) grant is to prepare a 14 C.F.R Part 150 Noise Exposure Map (NEM) update
for Patrick Leahy Burlington International Airport (Leahy BTV). The NEM Update replaced the
maps which were accepted by the FAA in 2019. Under the Federal requirements, the previous
NEM Update indicated an update would be completed once the F-35A aircraft have been
operational for one year. This project is complete and we are moving it to closure.
7. Residential Sound Insulation Project “Construction” – OLDCC (DOD) ($7.4M EST.). We received
this grant funding and will provide further update during the October meeting. No
communication has been possible with the government shut down.
8. Residential Sound Insulation Project - Phase 6 (TBD). The Airport is proposing to continue
implementation of its Residential Sound Insulation Program (RSIP) as described in the first
paragraph in this report. With the OLDCC award we are currently planning our approach for
the FAA 2026 grant application season.
Page 22 of 36
Page 23 of 36
Page 24 of 36
Page 25 of 36
Page 26 of 36
Page 27 of 36
2025
Patrick Leahy
Burlington International Airport
November 5, 2025
Airport Commission
Director’s Report
1
Page 28 of 36
2025
Project NexT
Photos by Jacobs
2
Page 29 of 36
2025
Education and Enrichment for Everyone Presentation
Page 30 of 36
2025
ACI-NA & ACI World Annual Conference & Exhibition
Page 31 of 36
2025
Burlington Technical Center Ribbon Cutting
Page 32 of 36
2025
Events and Items
• Current Items:
• ICE Updates
• Federal Government Shutdown Impact
• Aunt Flow Products
• Upcoming Items:
• Vermont Flight Academy Lease
• Hangar Condo Association Lease
• Aerodyme Lease
• Conferences:
• AAAE Noise Conference 11/11-11/13
Page 33 of 36
2025
Scheduled Departures; Projections
2025 2024 2019
1200
JAN 730 542 910
FEB 656 541 851
1000
MAR 808 613 970
APR 815 654 991
800
MAY 846 717 944
JUN 887 854 1,071
600
JUL 930 901 1,127
AUG 909 946 1,122 400
SEP 852 970 1,067
OCT 996 1,015 1,038 200
NOV 719 741 942
DEC 711 758 962 0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
TOTAL 9,859 9,341 11,995 2025 2024 2019
Page 34 of 36
2025
Scheduled Seats; Past and Projections
Total Annual Seats and Load
Factor:
2025 2024 2019 2008 = 1,051,115 @ 74.6%
120,000
2019 = 858,589 @ 82.7%
JAN 69,073 50,245 63,905 2022 = 804,380 @ 79.94%
2023 = 774,095 @ 86.7%*
FEB 60,958 48,066 60,240 2024 = 850,699 @ 81.18%
*Highest in recorded history since 1990
100,000
MAR 74,030 52,577 68,428
APR 72,724 53,671 66,566
80,000
MAY 71,276 64,163 67,379
JUN 77,239 78,672 78,828
60,000
JUL 86,108 86,352 84,658
AUG 84,106 92,765 83,786
40,000
SEP 80,415 92,016 76,194
Average # Seats per Flight:
OCT 91,292 94,651 75,193 2008 = 69 per flight
20,000
2019 = 71 per flight
NOV 63,563 66,633 66,096 2022 = 84 per flight
2024 = 91 per flight
DEC 58,395 70,888 67,316 2025 = 92 per flight (projected)
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
TOTAL 889,179 850,699 858,589
2025 2024 2019 2008
Page 35 of 36
2025
Passenger Statistics
90,000
2025 2024 2019
JAN 50,093 42,691 46,356
FEB 49,619 44,133 49,867 80,000
MAR 56,029 45049 56,400
APR 54,601 46,158 54,340 70,000
MAY 55,533 50,972 55,209
JUNE 61,182 61136 62,180
60,000
JULY 72,243 68,026 71,381
AUG 74,199 72,448 71,200
50,000
SEPT 66,294 67,296 62,116
OCT 73,034 76,054 66,795
40,000
NOV 50,850 51,977 53,007
DEC 46,716 57,012 56,314
30,000
JAN FEB MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC
TOTALS 708,393 681,925 705,165
2025 2024 2019 2008
*Underlined numbers are future estimates
Page 36 of 36