Charleston Sanitary Board
Regular MeetingCharleston, WV · April 10, 2025
Agenda
CHARLESTON SANITARY BOARD
APRIL 10, 2025 BOARD MEETING – 9:00 A.M.
VIA ZOOM TELECONFERENCE
NOTICE AND AGENDA
For: Members: Chairwoman Mayor Amy Shuler Goodwin and Messrs. Kanti
Patel, PE and Jack Rossi, CPA, Treasurer
Others: Steve A. Cooper, General Manager; Louis S. Southworth, II, Legal
Advisor; Tim Haapala, Operations Manager; Crystal Sanders, Finance
Manager; and Teresa Dawson, Board Secretary and Administrative
Assistant
Since this meeting with be conducted via Zoom , anyone wishing to comment
during the public comments portion of the meeting is asked to email
comments to info@csb-wv.com by April 10 th , 2025, at 9:00 AM. Any
comments received will be read into the record during the meeting. Any
member of the public who wishes to comment live during the meeting can do
so by calling 304-348-1084 ext 250 at 9:00 AM on Apr 10 th , 2025.
I. Approval of the February 13, 2025 Board Meeting Minutes (to be
e-mailed by 4-8).
II. Unaudited Financial Reports and Check Registers for the periods
ended February 28 and March 31, 2025 (to be e-mailed by 4-8).
III. Public Speakers.
IV. New Business.
1. Consider for approval, the FYE 2026 Budget (to be e-mailed by
4-8).
2. Consider for approval and authorize the General Manager, or
his designee, to execute such documents as necessary, to
recover from the West Virginia State Treasurer’s Office, funds
escheated to the State by CSB debtors.
3. Consider, for approval, the Petition to the Charleston City
Council to enact an ordinance approving the Charleston
Sanitary Board’s plan for the design, acquisition and
construction of the Magazine Branch Sanitary Sewer
CHARLESTON SANITARY BOARD
APRIL 10, 2025 BOARD MEETING
NOTICE AND AGENDA, CONTINUED
Improvements Project, and authorize the CSB General
Manager to take all actions necessary to support its adoption
and implementation.
4. Consider, for approval, the Petition to the Charleston City
Council to enact an ordinance to authorize the issuance of not
to exceed $30,000,000.00 in aggregate principal amount of
Sewerage System Revenue Bonds, in one or more series, for
the Charleston Sanitary Board to expend to finance in part the
cost of the design, acquisition and construction of the
Magazine Branch Sanitary Sewer Improvements Project, and
authorize the CSB General Manager to take all actions
necessary to support its adoption and implementation.
5. Consider for approval, and authorize the CSB General
Manager, or his designee, to take all actions necessary to
effect Change Order No. 2, the final adjusting change order, to
Insight Pipe Contracting, LLC for the FYE25 Pipe Lining
Contract, in the amount of $76,304.50, thus revising the
contract price from $324,624.00 to $400,928.50. The
additional cost associated with this change order is for pipe
lining on three additional sections of sanitary sewer main.
CSB FYE25 Capital Budget for this item is $400,000.00.
6. Consider for approval, and authorize the CSB General
Manager, or his designee, to effect the award of a construction
contract to EPM, LLC of Mineral Wells, WV, the lowest
responsible bidder, for the Asphalt Sealing and Striping
Contract, in the amount of $38,000.00, plus $4,000.00
contingency for use at CSB managerial discretion, for a total
of $42,000.00. There were four other bidders: Elevate Asphalt
Services, LLC of Princeton, WV, with a bid of $39,610.00;
2
CHARLESTON SANITARY BOARD
APRIL 10, 2025 BOARD MEETING
NOTICE AND AGENDA, CONTINUED
Paving Solutions of Huntington, WV, with a bid of $40,375.00;
The Striping Company, LLC of Poca, WV, with a bid of
$71,100.00; and Cummings Seal Coating and Striping of
Sissonville, WV, with a bid of $73,473.50. CSB FYE25 capital
budget remaining for this item is approximately $63,000.00.
7. Consider for approval, and authorize the CSB General
Manager, or his designee, to effect the award of a
construction contract to Tribute Contract and Consultants,
Inc. of South Point, OH, the lowest responsible bidder, for the
Lovell Drive Sanitary Sewer Improvements Project, in the
amount of $983,778.00, plus $49,000.00 in contingency for
use at CSB managerial discretion, for a total of
$1,032,778.00. There was one other bidder, C.J. Hughes
Construction Company of Huntington, WV, with a bid of
$1,175,689.00. CSB FYE25 Capital Budget for this item is
$600,000.00.
V. Executive Session matters.
VI. Personnel matters.
VII. Legal matters.
a) Karl Nester vs. CSB.
VIII. Other matters for information and discussion.
a) Shadybrook Village sanitary sewers.
b) Rate case.
IX. Next scheduled meeting: June 12, 2025.
X. Adjourn.
April 3, 2025– Copies via e-mail to Board members, advisors and staff and for
posting, to the CSB IT Manager and Charleston City Clerk.
3