Planning & Zoning Commission
Regular MeetingDeKalb, IL · May 20, 2020
Minutes
Planning and Zoning Commission
May 20, 2020
Page 1 of 5
MINUTES
CITY OF DEKALB
PLANNING AND ZONING COMMISSION
May 20, 2020
The Planning and Zoning Commission held a Meeting on May 20, 2020, at the City of
DeKalb Municipal Building, 200 South Fourth Street, DeKalb, Illinois. Chair Max Maxwell
called the meeting to order at 6:00 PM.
Chair Maxwell stated he wanted to thank everyone for being here tonight, including
Commission members who are attending remotely and for those who are watching
on Channel 14 or streaming live. He referenced the Governor’s Executive Order in
March that allows Commission members to participate remotely. He said member
Chris Doe will be joining the meeting remotely by calling in and mentioned for those
attending the meeting the room has been set up to meet the CDC recommended
distancing guidelines and the Executive Order from the Governor.
A. ROLL CALL
Principal Planner Dan Olson called the roll. Planning and Zoning Commission
members present were: Chair Max Maxwell, Ron Klein, Jerry Wright and Trixy
O’Flaherty. Vice Chair Christina Doe attended the meeting remotely by an audio
conference call. Commissioners Vicki Buckley and Steve Becker were absent.
Principal Planner Dan Olson was present representing the City.
B. APPROVAL OF THE AGENDA (Additions/Deletions)
Chair Maxwell requested a motion to approve the May 20, 2020, agenda as
presented. Mr. Klein motioned to approve the agenda as presented. Ms. O’Flaherty
seconded the motion, and the motion was approved by unanimous voice vote.
C. APPROVAL OF MINUTES
1. April 22, 2020 – Chair Maxwell requested a motion to approve the April 22,
2020 minutes as presented. Mr. Wright motioned to approve the minutes as
presented. Mr. Klein seconded the motion, and the motion was approved by
unanimous voice vote.
D. PUBLIC PARTICIPATION (Open Floor to Anyone Wishing to Speak on Record)
None
E. NEW BUSINESS
Planning and Zoning Commission
May 20, 2020
Page 2 of 5
1. Public Hearing – A petition by Christa and Matt Gehrke for approval of the
rezoning of 421 Grove Street from the “CBD” Central Business District to the
“PD-C” Planned Development – Commercial District and approval of a
preliminary and final development plan to accommodate a building contractor’s
office and material storage on the subject site.
Matt Gehrke, owner of Swedberg Associates, stated he had submitted a
petition to the City of DeKalb to move his 9-year old construction company from
Sycamore to DeKalb. He advised the business has outgrown its current facility
and has decided the subject site would be the best for his expanding business.
He noted the property has both office space and a warehouse, which is perfect
for a construction company.
Mr. Gehrke advised a fence will be constructed to screen the outdoor storage.
He stated the majority of the storage would be trailers, work vehicles, and
staged construction materials. He noted the fence would be installed along the
alley, parallel with S. 5th Street, and be flush with the south side of the building.
He noted he prefers to install a corrugated metal fence (Option #1), which
would be easy to repair and would be a solid privacy fence. He added they
would install splash planks on the bottom of the fence to prevent damage to the
landscaping.
Mr. Gehrke provided examples of two other fence styles, which could be
installed at the recommendation of the Commission and City Council. He
advised the second option would be a chain link fence with a mesh cover
(Option #2). He advised this type of fencing requires the most maintenance and
has the worst overall aesthetics. He noted the third option is also a corrugated
metal fence but is slightly more expensive and labor intensive to install
compared to the initial option (Option #1).
Mr. Gehrke advised the landscaping would be cleaned up on the site and 17
shrubs added along S. 5th Street and 10 shrubs added along S. 4th Street.
Mr. Gehrke noted all parking for visitors and employees would be along the
front or side of the building. He advised there are approximately 20 parking
spaces on the site (outside proposed fenced area) and his employees would
occupy about four of those spaces. He advised there would be low activity on
the lot, as most of his employees are working at jobs sites.
Principal Planner Dan Olson went through the staff report dated May 15, 2020.
He advised under the current zoning classification (CBD), building contractor’s
office with materials storage is not specifically listed as permitted use or special
use. He noted the CBD District currently prohibits outside storage when it’s a
principal use. He advised the proposed “PD-C” zoning will allow the applicant
Planning and Zoning Commission
May 20, 2020
Page 3 of 5
to have the building contractor’s office with materials storage. He stated the
request also involves a waiver to the Unified Development Ordinance for a
Planned Development less than two acres. He advised the City has previous
granted similar waivers for the Cornerstone and Plaza DeKalb projects.
Mr. Olson said the subject property is approximately 1.24 acres and has a
building that is mostly vacant and a parking lot around all four sides. He noted
the property has been listed for sale since 2013. He stated the building’s office
area is being leased out to three business, however its underutilized. He noted
the current owner rents the interior of the building for vehicle, RV and boat
storage.
Mr. Olson stated an 8-foot tall fence would be installed along 5th Street and the
rear alley to screen construction materials and storage. He reiterated the three
fence option details given by Mr. Gehrke, with a detail of a third option provided
to the Commission at the meeting.
Mr. Olson noted 18 parking spaces are required based on the formula in the
UDO. He advised there are a total 22 marked parking spaces on the lot outside
of the fenced area.
Mr. Olson mentioned staff is recommending approval with conditions to bring
the site further into compliance with the UDO including re-striping of the parking
lot, painting the parking lot light poles, and adding landscaping.
Chair Maxwell gave the public an opportunity to speak.
Dana Doty, of 323 S 6th St, and owner of the adjacent Archer Alignment stated
his concerns regarding traffic in the alley. He stated the City broke its’ own
ordinances with the Dunkin Donuts drive-through was approved. He advised
the alley is always blocked and would prefer if the petitioner limited traffic going
through the alley. He advised he would prefer option #3 for the fence. He
advised he did support a business moving into the vacant building and
welcomed the petitioner to the neighborhood.
Louise Calderone, of 308 S 3rd St, noted her concerns of increased traffic
between 1st St and 4th St. She advised she does not want to see more semi-
trucks and construction vehicles in the neighborhood. Mr. Gehrke advised there
would only be four staff members in the office, which would have very minimal
impact on any traffic. He advised his construction crews go to their job sites
very early in the morning and might have to return to the subject site only once
or twice a day. He noted the Grove Street access will be used most often.
Planning and Zoning Commission
May 20, 2020
Page 4 of 5
Rita McNatt, of 220 S 5th St, said she preferred options #1 or #3 for the fence.
She noted she also lives on a cobblestone street and would like to keep traffic
out of the area to preserve the street.
Chair Maxwell gave the commissioners a chance to speak.
Mr. Klein questioned what vehicles would be parked within the fence area, and
which would be outside. Mr. Gehrke advised office staff would be parking
outside the fenced area and work vehicles would be parked in the fenced in
area. He noted most materials will be stored inside the warehouse and it would
mainly be work vehicles stored outside but behind the fenced area.
Mr. Klein stated he preferred option #3 for the fence and would prefer if traffic
off S. 4th St be limited. Mr. Gehrke advised the majority of traffic would use the
access off Grove St.
Ms. O’Flaherty advised she is excited for someone to move into the building,
as it has been vacant for so long. She noted option #3 for the fencing was
preferred, and she was happy to hear of the new landscaping.
Mr. Wright questioned what a splash plank was. Mr. Gehrke advised it is a
baseboard for a fence, to keep mulch and dirt from getting underneath the
fence. Mr. Wright questioned if any semi-trucks would be making any deliveries
and what the corner lot (along 4th St.) would be used for. Mr. Gehrke advised
there would be no semi-truck traffic and the corner lot would only be used for
vehicle parking.
Chair Maxwell advised he approved of the request and stated it was a great
use of the property.
Chair Maxwell gave the public one more opportunity to speak. There was none.
Mr. Wright moved that the Planning and Zoning Commission forward its
findings of fact and recommend to the City Council approval of a Zoning Map
Amendment from the “CBD” Central Business District to the “PD-C” Planned
Development – Commercial District; approval of a waiver to the Unified
Development Ordinance for a Planned Development less than two acres and
approval of a preliminary and final development plan to accommodate a
building contractor’s office and materials storage on the subject site at 421
Grove Street per the plans dated 5-15-20 and labeled as Exhibit A, Fence
Detail Option #3 labeled as Exhibit B, and per the conditions listed in Exhibit C.
Ms. O’Flaherty seconded the motion.
Planning and Zoning Commission
May 20, 2020
Page 5 of 5
A roll call vote was taken. Mr. Klein – yes, Ms. Doe – yes, Ms. O’Flaherty – yes,
Mr. Wright – yes, Chair Maxwell – yes. Motion was passed 5-0-2. Ms. Buckley
and Mr. Becker were absent.
F. REPORTS
Mr. Olson advised the City Council approved Project Ventus and the NuMed
Cannabis Business establishment at their April 27th meeting. He reminded the
Commission the next meeting would be June 3rd and there will be a hearing for
a mixed-use project at Oakland Dr. and Sycamore Rd. called Isaac Executive
Suites
G. ADJOURNMENT
Ms. Flaherty motioned to adjourn, Mr. Wright seconded the motion, and the
motion was approved by unanimous voice vote. The Planning and Zoning
Commission adjourned at 6:41PM.
Agenda
DeKalb Municipal Building
City Council Chambers
200 S. Fourth St., 2nd Floor
DeKalb, IL 60115
AGENDA
Planning and Zoning Commission
May 20, 2020
6:00 PM
Please Note: On March 16, 2020, Illinois Governor JB Pritzker issued executive order 2020-07 which
declared that during the duration of the Gubernatorial Disaster Proclamation pertaining to the coronavirus
outbreak, “the provisions of the Open Meetings Act, 5 ILCS, requiring or relating to in-person attendance
by members of a public body are suspended. Specifically, (1) the requirement in 5 ILCS 120/2.01 that
‘members of a public body must be physically present’ is suspended; and (2) the conditions in 5 ILCS
120/7 limiting when remote participation is permitted are suspended.” The executive order further states
that when a public meeting is considered necessary by the governing body, “public bodies are
encouraged to provide video, audio, and/or telephonic access to meetings to ensure members of the
public may monitor the meeting, and to update their websites and social media feeds to keep the public
fully apprised of any modifications to their meeting schedules or the format of their meetings due to
COVID-19, as well as their activities relating to COVID-19.” The City of DeKalb has taken prudent steps to
assure that Planning and Zoning Commission member remote participation and public access are
available and will be provided within the provisions of the Governor’s executive order.
A. ROLL CALL
B. APPROVAL OF AGENDA (Additions or Deletions)
C. APPROVAL OF MINUTES
1. April 22, 2020
D. PUBLIC PARTICIPATION (Open Floor to Anyone Wishing to Speak on Record)
E. NEW BUSINESS
1. Public Hearing – A petition by Christa and Matt Gehrke for approval of the
rezoning of 421 Grove Street from the “CBD” Central Business District to the “PD-
C” Planned Development – Commercial District and approval of a preliminary and
final development plan to accommodate a building contractor’s office and materials
storage on the subject site.
F. REPORTS
G. ADJOURNMENT
Planning and Zoning Commission
April 22, 2020
Page 1 of 11
MINUTES
CITY OF DEKALB
PLANNING AND ZONING COMMISSION
April 22, 2020
The Planning and Zoning Commission held a Meeting on April 22, 2020, at the City of
DeKalb Municipal Building, 200 South Fourth Street, DeKalb, Illinois. Chair Max Maxwell
called the meeting to order at 6:00 PM.
Chair Maxwell stated he wanted to thank everyone for being here tonight, including
Commission members who are attending remotely and for those who are watching
on Channel 14 or streaming live. He referenced the Governor’s Executive Order in
March that allows Commission members to participate remotely. He said member
Chris Doe will be joining the meeting remotely by calling in and mentioned for those
attending the meeting the room has been set up to meet the CDC recommended
distancing guidelines and the Executive Order from the Governor.
A. ROLL CALL
Principal Planner Dan Olson called the roll. Planning and Zoning Commission
members present were: Chair Max Maxwell, Steve Becker, Ron Klein, Jerry Wright
and Trixy O’Flaherty. Vice Chair Christina Doe attended the meeting remotely by
an audio conference call. Commissioner Vicki Buckley was absent. Principal
Planner Dan Olson was present representing the City. Attorney Matthew Rose and
City Engineer Zac Gill attended the meeting remotely by an audio conference call
and were representing the City also.
B. APPROVAL OF THE AGENDA (Additions/Deletions)
Chair Maxwell requested a motion to approve the April 22, 2020, agenda as
presented. Mr. Klein motioned to approve the agenda as presented. Mr. Wright
seconded the motion, and the motion was approved by unanimous voice vote.
C. APPROVAL OF MINUTES
1. April 8, 2020 – Chair Maxwell requested a motion to approve the April 8, 2020
minutes as presented. Ms. O’Flaherty motioned to approve the minutes as
presented. Mr. Wright seconded the motion, and the motion was approved by
unanimous voice vote.
D. PUBLIC PARTICIPATION (Open Floor to Anyone Wishing to Speak on Record)
None
E. NEW BUSINESS
Planning and Zoning Commission
April 22, 2020
Page 2 of 11
1. Continued Public Hearing – Petition by Ventus Tech Services LLC for the
approval of the rezoning, preliminary and final development plans, and
subdivision plat for a data center approximately 505 acres of property generally
located east of Route 23 and south of Gurler Road.
Principal Planner Dan Olson noted Attorney Karl Camillucci was present
representing Project Ventus. He advised Project Ventus Engineer Matt Fillmore
was present via audio conference call as well as City Engineer Zac Gill, and
City Attorney Matthew Rose.
Mr. Olson went through the staff report dated April 17, 2020. He noted another
public hearing notice was sent out to property owners within 250 ft of the site
due to the continuation of the hearing and the addition of a more detailed
engineering plans being submitted. He noted the revised plans were more in
line with the current Unified Development Ordinance “UDO” requirements for
preliminary and final development plans.
Mr. Olson advised the petitioner is requesting approval of the annexation and
rezoning of approximately 505 acres of property generally located east of Route
23 and south of Gurler Road to accommodate a data center in an approximately
970,000 sq. ft. facility with an option to expand. He noted the request would
change the zoning of the subject site from the “SFR1” Single-Family Residential
District to the “PD-I” Planned Development Industrial District. He stated the
petitioner also seeks approval of a Preliminary and Final Development Plan
and Plat of Subdivision, which are part of the petition, along with the approval
of associated development standards for the subject site.
Mr. Olson advised on March 9, 2020 the DeKalb City Council unanimously
approved a Pre-Development Agreement with the petitioner, which established
the City’s intent to appropriately annex and rezone the subject site. He noted
the agreement also established the intent to extend financial incentives
including a property tax abatement program through the DeKalb County
Enterprise Zone program that is tied to job creation and retention goals,
minimum square footage goals, and project wage levels. He stated in order to
accommodate the incentives, the City Council approved an extension to the
DeKalb County Enterprise Zone map on January 13, 2020 to include the
subject property, and include new property tax incentives for high impact
knowledge-based companies or data centers with a minimum of $800 million
of investment and a minimum of 900,000 square feet of development area. He
said on April 2, 2020 the DeKalb County Enterprise Zone approved a
Memorandum of Understanding to deliver these benefits to the petitioner within
the reciprocal obligations defined by the Enterprise Zone program.
Planning and Zoning Commission
April 22, 2020
Page 3 of 11
Finally, Mr. Olson noted on April 13, 2020 the City Council approved on first
reading the Annexation and Development Agreement with Ventus Tech
Services, LLC for the data center. He noted the second reading is scheduled
to occur at the April 27, 2020 City Council meeting.
Mr. Olson also stated there will be a public hearing and action by the City
Council on the April 27th meeting to approve the vacation of Crego Road
between Gurler Road and the southern boundary of the site. Mr. Olson advised
after the approval of the annexation, mass grading on the subject site is
scheduled to start in early May.
Mr. Olson said the petitioner is proposing an initial investment of more than
$800 million to construct the data center facility, with the option to expand in
additional phases. He noted the skilled workforce will consist of high wage
technology professionals and would include a minimum of 40 high paying jobs.
Mr. Olson mentioned the proposed rezoning request and plan approval will
generate new business opportunities and support existing commerce in the
surrounding area, while increasing property values and other development
opportunities. He noted over the next 20 years the proposed data center is
projected to yield tax revenue for the participating taxing bodies, even with the
tax abatements, that is comparable to the five largest existing industrial
companies in the City, combined.
Mr. Olson described the main access to the site will be provided by Peace Road
at Gurler Road, which will have strict security measures. He stated there will
also be access along Gurler Road, Crego Road, and other possible locations
on the proposed site as it is developed. He noted there will be an electrical
substation to the southwest of the building as well. He stated the vacation of
Crego Road is vital and necessary for the data centers security. He advised a
new north-south road from Gurler Road to Keslinger Road will be constructed
just to the east of the data center site, which will include two 12’ wide driving
lanes.
Mr. Olson noted the initial building plan covers approximately 970,000 sq. ft.,
which will also include the parking and landscaped areas for the project. He
advised the majority of the proposed building will be 54 feet in height and just
under 57 at the highest point. The maximum height in the Light Industrial and
Heavy Industrial Districts is 75 feet.
Mr. Olson advised the landscaping around the perimeter of the initial phase of
development will meet the UDO requirements. He noted the plan has
landscaping along Route 23, which exceeds the UDO requirements by 30 trees
and will include a 20-foot berm to match what is proposed for the Chicago West
Business Center to the north.
Planning and Zoning Commission
April 22, 2020
Page 4 of 11
Mr. Olson advised the recommended setback along Route 23 was increased
from 150 feet to 400 feet since the initial draft of the development standards.
The 400-foot setback will be consistent with the Chicago West Building Center
to the north. He stated a Plat of Subdivision was submitted indicating the
creation of one lot for the entire site. He advised the plat includes the dedication
of 50 feet of right-of-way along Gurler Road for roadway improvements and the
establishment of a 20-foot easement along Route 23 for the Kishwaukee Water
Reclamation District to extend a future sanitary sewer line.
Mr. Olson advised the petitioner requested the construction of additional
buildings and improvements be allowed without further zoning review or public
hearings if approved by the City Manager. He stated the existing T-intersection
at Peace Road and Gurler Road will be reconstructed and made into a
roundabout, capable of accommodating year-round truck traffic. He noted there
will be intersection traffic control improvements at both ends of Gurler Road
adjacent to the project site. He stated the vacation of Crego Road between
Gurler Road and the development of a new north-south roadway will be funded
from the State’s 2019 Capital Projects Fund. Mr. Olson noted a watermain will
be extended to the site, with two 16” water connections being proposed to
extend into the subject site during the initial phase. He added a separate water
agreement will be provided in the annexation and development agreement,
which will ensure an adequate and reliable water supply is provided to the
development.
Mr. Olson advised several public comments were received. He stated an email
was received from Joseph Gormley, who represents 240 acres of property
south of the site. He noted Mr. Gormley had concerns about future access to
the property, the vacation of Crego Road, and the value of the property. Mr.
Olson discussed the addition of the new north-south roadway, as well as the
extension of utilities and upgraded roadways, which will increase the value of
adjacent parcels for future development.
Mr. Olson noted since the April 8th Planning and Zoning Commission meeting,
the City has received written correspondence from Michael Hammett
representing about 120 acres on Crego Road, south of Keslinger Road (1.1
miles from the Ventus site). He advised City staff spoke to Mr. Hammett and
he indicated support for the data center, however, had concerns regarding the
timing of the vacation of Crego Road in relation to the construction of the new
road east of the site. Mr. Olson noted he advised Mr. Hammett of the need for
the data center to have Crego Road vacated after the annexation. In addition,
Mr. Olson stated to Mr. Hammett there are alternate routes (Rt. 23 and Lynch
Road), one can take to get to Gurler Road/Peace Road and I-88.
Planning and Zoning Commission
April 22, 2020
Page 5 of 11
Mr. Olson advised the City also received a resolution from the DeKalb County
Economic Corporation (DCEDC) dated April 10, 2020 indicating their full
support for the proposal. He stated the resolution notes, in part, the data center
will generate significant economic benefits to the Dekalb County economy in
the form of investment, construction, new tax revenue and job creation.
Mr. Olson noted a response form was received from Gerald and Kaye Kempson
along Crego Road, stating their concern over the vacation of Crego Road. They
were advised the portion of Crego Road adjoining their property will still be
accessible.
Mr. Olson advised a letter was received from John and Marlen Norris of 350
Gurler Road, stating their concern for drainage issues along Route 23 and
Gurler Road. Mr. Olson stated they were advised both Ferrara Candy Co. and
Project Ventus have stormwater management systems that should help
improve drainage issues in the area.
Mr. Olson described an email was received from Jamie Walter, CEO of
Whiskey Acres Distillery located along Keslinger Road, stating their support for
the project and the importance of a new road just east of the site with the
vacation of Crego Road.
Finally, Mr. Olson advised letters of support were received from Northern Illinois
University, Paul Callighan of 1512 Crayton Circle East, and Jerry Wahlstrom
and Sue Elsner of Century 21 Real Estate and were entered into the record.
Mr. Olson stated the proposed data center will be a transformative development
that will impact generations of DeKalb County residents. He advised the project
will generate new business opportunities and support existing commerce in the
surrounding area, while spurring increased property values and other
development opportunities. He stated, in addition, the data center will generate
significant benefits to the Dekalb County economy in the form of investment,
construction, new tax revenue and job creation and staff strongly recommends
approval of the project.
Chair Maxwell gave the public an opportunity to speak. He advised several
speaker request forms were received, and he would call each participant in the
order the forms were received.
Randy Bourdages, of 10315 Keslinger Road, representing Afton Township
stated his support for the project. He wanted to thank City staff and City
Manager Bill Nicklas for making this project possible. He advised some
Township residents had concerns of illegal dumping on and around Crego
Road, and he would work with the Township to avoid such issues in the future.
Planning and Zoning Commission
April 22, 2020
Page 6 of 11
Cohen Barnes, of 234 Greenwood North, representing DCEDC stated he fully
supports the project. He advised both Project Ventus and Ferrara are
transformative projects that will be a great benefit to DeKalb.
Matt Swanson, president of DeKalb County Building Trades and Laborer’s
Local 32, stated his organization’s full support the project. He stated the data
center will be a great benefit to DeKalb and surrounding communities.
Lance McGill, of 3715 Pebble Beach Ct., business representative for the Illinois
Union of Operating Engineers Local 150 stated his support for the project. He
said he is extremely excited to see the work going on, as well as the berm that
will be constructed along Rt. 23.
Chair Maxwell gave the Commissioners a chance to speak.
Mr. Becker stated he believed this is a wonderful project for the community.
Ms. O’Flaherty agreed.
Mr. Klein advised he fully supports the project, but always has a concern when
large amounts of farmland are developed. He stated he would like to see
preservation of some farmland in the community. He also had concerns
regarding large farm equipment having access on the new north-south road.
Chair Maxwell stated he believes this will be a transformative project for DeKalb
and thanked everyone who came to give their thoughts on the proposal.
Mrs. O’Flaherty moved that the Planning and Zoning Commission forward its
findings of fact and recommend to the City Council approval of a Zoning Map
Amendment, upon annexation, from the “SFR1” Single-Family Residential
District to the “PD-I” Planned Development Industrial District and approval of a
Preliminary and Final Development Plan and Subdivision Plat as listed in the
revised Exhibit A for an approximately 505 acre property generally located east
of State Rt. 23 and south of Gurler Road for a data center and accessory uses
and subject to the development standards listed in the revised Exhibit B as
stated in the staff report and provided to the Commission.
Mr. Wright seconded the motion.
A roll call vote was taken. Mr. Becker – yes, Mr. Klein – yes, Ms. Doe – yes,
Ms. O’Flaherty – yes, Mr. Wright – yes, Chair Maxwell – yes. Motion was
passed 6-0-1. Ms. Buckley was absent.
2. Public Hearing – A petition by the City of DeKalb to add a definition for “data
center” and to add it as a permitted use in the “ORI”, “LI”, and “HI” Zoning
Districts and to remove the requirement that only certain specific uses may be
Planning and Zoning Commission
April 22, 2020
Page 7 of 11
allowed in the “PD-C” and “PD-I” Zoning Districts and to provide for a process
for approval of minor changes to the final plan and plat of subdivision for
planned developments over a certain size.
Principal Planner Dan Olson went over the Staff Report dated April 17, 2020.
He advised the City of DeKalb proposes text amendments to Chapter 23
“Unified Development Ordinance (UDO)” of the Municipal Code to amend
several articles of the UDO which are related, in part, to the Project Ventus
development. He noted the term “data center” does not appear anywhere in the
UDO. He stated an amendment is proposed to add “data center” as a definition
and to add it as a permitted use in the Industrial Zoning Districts. He advised a
proposed amendment is requested to remove the requirement that only certain
specific uses be allowed in the “PD-C” and “PD-I” Districts and an amendment
is proposed to provide for a process for approval of minor changes to the final
plan and plat of subdivision for planned developments over a certain size.
Mr. Olson advised the definition for “data center” was added to Article 3 of the
UDO based on the definition provided by applicants of Project Ventus. He
advised “data center” was added as a permitted use to the “ORI”, “LI”, and “HI”
districts in Article 5. He noted the current language states a development in the
PD-I District may only include those uses listed as permitted or special in the
“ORI”, “LI” and “HI” Districts. He advised since “data center” is not specifically
mentioned in those three zoning districts, an amendment is proposed to
remove the word “only”. He stated the change will also be beneficial for future
developments to allow for more flexibility of uses to be included in Planned
Developments, which often include a mix of uses. He noted the changes are
also proposed for the PD-C District.
Mr. Olson advised the request also proposes that all amendments, changes, or
revisions to the final plan and plat of a subdivision for any planned development
located on parcels of property under common ownership which are at least 500
acres in size, shall constitute minor change and may be authorized by the City
Manager or Community Development Director without additional public
hearings. He noted the proposed language further states the authorization is
contingent upon said amendments, changes, or revisions conforming to the
conditions and development standards established in the Ordinance adopted
by the City Council governing the planned development.
Chair Maxwell gave the public an opportunity to speak. There was none.
Mr. Becker moved that the Planning and Zoning Commission recommend to
the City Council approval of City of DeKalb initiated text amendments to
Chapter 23 “Unified Development Ordinance (UDO)” of the Municipal Code to
add a definition for “data center” and to add it as a permitted use in the “ORI”,
“LI”, and “HI” Zoning Districts and to remove the requirement that only certain
Planning and Zoning Commission
April 22, 2020
Page 8 of 11
specific uses be allowed in the “PD-C” and “PD-I” Zoning Districts and to
provide for a process for approval of minor changes to the final plan and plat of
subdivision for planned developments over a certain size as indicated on the
attached Exhibit A of the staff report.
Mr. Klein seconded the motion.
A roll call vote was taken. Mr. Becker – yes, Mr. Klein – yes, Ms. Doe – yes,
Ms. O’Flaherty – yes, Mr. Wright – yes, Chair Maxwell – yes. Motion was
passed 6-0-1. Ms. Buckley was absent.
3. Public Hearing – A petition by NuMed Partners LLC for approval of a special
use permit for a “Cannabis Business Establishment” in order to locate an adult
use and medical cannabis dispensary at 818 W. Lincoln Hwy.
Jim Hughes, representing Next Generation Development and in partnership
with NuMed Partners LLC, stated they are proposing an adult use and medical
cannabis dispensary at 818 W Lincoln Hwy. He stated the proposed location
was perfect, as it is close to downtown, Northern Illinois University, and has
plenty of parking.
Robert Fitzsimmons, representing NuMed Partners LLC, advised he runs a
series of companies that are invested primarily in medical marijuana. He stated
they will have 6 stores by the end of the year in Illinois and are applying for 36
more locations. He advised they have locations in Peoria, Chicago, and
Urbana. He noted they have special programs that mitigate the effect on
communities. He stated 75% of orders are done online and they are highly
invested in security at their locations. Mr. Fitzsimmons also noted they are
strong on the “social equity” program of the cannabis regulations.
Principal Planner Dan Olson went through the staff report dated April 17, 2020.
He noted the location is a 6,600 sq. ft. tenant space in The Junction Shopping
Center. He advised the tenant space is located in the corner of the shopping
center building and was the former location of Book World. He stated the
subject site is zoned “LC” Light Commercial District and a “Cannabis Business
Establishment” is a special use in that district. He noted “Cannabis Business
Establishment” is defined in the UDO as “an adult-use cannabis dispensing
organization and a medical cannabis dispensing organization.”
Mr. Olson advised a floor plan indicating the layout of the facility has also been
provided. He noted the floor plan and security measures have been forwarded
to the Police Department for an initial review. He stated as a condition of
approval, staff is recommending a security plan be approved between the
Police Department and applicant prior to final occupancy of the tenant space.
Planning and Zoning Commission
April 22, 2020
Page 9 of 11
Mr. Olson noted there are several requirements in the UDO for “Cannabis
Business Establishments”, including setbacks to schools, day care facilities
and residential areas. He advised a “Cannabis Business Establishment” cannot
be located within 250 feet of the property line of a property zoned or used
primarily for residential purposes that contains residential dwelling units. He
noted the nearest residential property is an apartment complex to the west and
about 315 feet from the proposed tenant space. Mr. Olson advised a “Cannabis
Business Establishment” cannot be located within 250 feet of the property line
of a nursery school, preschool, primary or secondary school, day care center,
daycare home, residential home and an academic building or residence hall of
a State University. He advised none of these mentioned uses are within 250
feet of the proposed tenant space.
Mr. Olson stated the parking requirement for cannabis dispensaries in the UDO
is the same requirement applicable to “Commercial Service Facility and Retail
Sales” uses, which is one parking space per 250 sq. ft. of floor area. He advised
they are required to have 167 parking spaces and there is a total of 170 parking
spaces provided in the shopping center excluding the lot for Pizza Villa.
Mr. Olson advised on November 25, 2019 the City approved an Ordinance
granting the zoning for a medical cannabis dispensary for BQ Enterprises at
700 Peace Road. He noted the State has separate licensing requirements and
limits on the number of facilities, however, the Commission’s focus for this
request should be on the standards for a special use found in the UDO. The
UDO does have a limit of five special use permits for adult use cannabis
dispensaries in the City. He stated the City is recommending the applicant
obtain a state-issued adult-use and medical cannabis dispensary license for
the subject site within one year of approval of the ordinance granting the special
use permit.
Chair Maxwell gave the public an opportunity to speak. There were none.
Chair Maxwell gave the Commission an opportunity to speak.
Mr. Wright questioned if NuMed’s other locations are the same size as the
proposed location. Mr. Fitzsimmons stated his facilities range in size, with the
Chicago location under-sized, at 3,300 sq. ft. He advised Peoria has 8,000 sq.
ft. and Urbana is a 7,700 sq. ft. space.
Mr. Wright questioned if the existing customer base in DeKalb will support his
business. Mr. Fitzsimmons advised most of his customers are professional
workers, due to the price of the product. He stated DeKalb has a large
Planning and Zoning Commission
April 22, 2020
Page 10 of 11
professional workforce, including NIU employees, that will provide a strong
customer base.
Mr. Wright questioned what security measures will be taken. Mr. Fitzsimmons
stated the proximity to the police department is extremely beneficial. He
advised they haven’t had any security issues with any of their other sites and
will work with the police department as much as possible and have provided a
security plan to them.
Mr. Becker asked what percent of sales are expected to be recreational. Mr.
Fitzsimmons advised he is expecting approximately a 50-50 split between
recreational and medical. Mr. Becker questioned how he conducts online
ordering. Mr. Fitzsimmons advised the customer must upload a picture of their
ID during their purchase and must present the same ID when picking up their
product.
Mr. Klein referenced an article (Health Dept. in Northern Illinois) about a study
on smoking cannabis. He stated it can impair short term memory, learning
intelligence, and that the brain is still developing until the age of 25. He
questioned whether Mr. Fitzsimmons agrees with those findings. Mr.
Fitzsimmons stated he does agree and would prefer the legal age of use was
25. He stated they have led various studies and programs to promote the
positive and safe use of cannabis.
Ms. Doe questioned what the hours of operation would be. Mr. Fitzsimmons
stated the state regulates business hours and they typically run 10AM to 6PM.
Ms. Doe asked what their plans are regarding excessive customer lines, as
seen at other adult-use marijuana facilities. Mr. Fitzsimmons advised they
primarily conduct business electronically and inform their customers as such
and haven’t had problems with long lines at their other locations.
Chair Maxwell the gave public an opportunity to speak. There were none.
Ms. O’Flaherty moved that the Planning and Zoning Commission forward its
findings of fact and recommend to the City Council approval of a Special Use
Permit for a “Cannabis Business Establishment” - Adult Use and Medical
Cannabis Dispensary for the property located at 818 W. Lincoln Highway in the
tenant space as shown on Exhibit A and subject to the conditions listed in
Exhibit B of the staff report.
Mr. Becker seconded the motion.
A roll call vote was taken. Mr. Becker – yes, Mr. Klein – no, Ms. Doe – yes, Ms.
O’Flaherty – yes, Mr. Wright – yes, Chair Maxwell – yes. Motion was passed 5-
1-1. Ms. Buckley was absent.
Planning and Zoning Commission
April 22, 2020
Page 11 of 11
F. REPORTS
Mr. Olson advised there are no public hearings scheduled for the May 6, 2020
Commission meeting, so it will most likely be cancelled. He noted the City
Council approved the second reading of the J&S Tri-State towing facility special
use at their April 13th meeting.
G. ADJOURNMENT
Mr. Klein motioned to adjourn, Mr. Wright seconded the motion, and the motion
was approved by unanimous voice vote. The Planning and Zoning Commission
adjourned at 7:25PM.
STAFF REPORT
May 15, 2020
TO: Planning and Zoning Commission
FROM: Dan Olson, Principal Planner
RE: Rezoning of 421 Grove St. from the “CBD” Central Business District to the
“PD-C” Planned Development – Commercial District; Approval of
Preliminary and Final Development Plan (Christa and Matt Gehrke)
I. GENERAL INFORMATION
A. Purpose Zoning Map Amendment from the “CBD”
District to the “PD-C” District; Approval of
a Preliminary and Final Development Plan
to allow for a building contractor’s office
and materials storage
B. Owner/Applicant Timber Creek Properties, LLC/Christa
and Matt Gehrke
C. Location and Size 421 Grove St./1.24 acres
D. Existing Zoning and Land Use “CBD” Central Business District;
underutilized office space, indoor storage;
parking lot
E. Surrounding Zoning and Land Use North: CBD and PD-I; Various
Commercial Uses, Automotive Repair
South: CBD and RC-1; City Hall and
Single-Family Residential
East: CBD; Theater, Post Office
West: CBD; Various Commercial Uses,
City Parking Lot
F. Comprehensive Plan Designation Commercial
II. BACKGROUND AND ANALYSIS
Request/Background
The City has received a rezoning petition from Christa and Matt Gehrke to rezone the
property at 421 Grove St. (northwest corner of S. 5th St. and Grove St.) from the “CBD”
Central Business District to the “PD-C” Planned Development – Commercial District. The
applicant is also requesting approval of a preliminary and final development plan. The
applicant, Matt Gehrke with Swedberg Associates in Sycamore, is planning to move their
contractor’s office and materials storage area to the subject site. Under the current zoning
classification (CBD), building contractor’s office with materials storage is not specifically
listed as permitted use or special use. In addition, the CBD District currently prohibits
outside storage when a principal use. The proposed “PD-C” zoning will allow the applicant
to have the building contractor’s office with materials storage. The request also involves
a waiver to the Unified Development Ordinance for a Planned Development less than two
acres. The City has previous granted similar waivers for the Cornerstone and Plaza
DeKalb projects.
The property is 1.24 acres and has a building that is mostly vacant and a parking lot
around all four sides. The property has been listed for sale since 2013. The building’s
office area is being leased out to three business, however its underutilized. An
engineering firm uses space in the building as an occasional field office, an architecture
firm has some storage space and there is a pest control operation also in the building. In
addition, the current owner rents the interior of the building for vehicle, RV and boat
storage. For much of the time, the parking lot is empty throughout the day. If the rezoning
is approved, the applicant will close on the property and the current leases will be
terminated.
The outdoor materials storage will be located to the north and east of the building (see
plan in packet). The applicant is proposing to construct an eight-foot-high fence along S.
5th St. and the rear alley to screen the construction materials that will be stored outside.
The applicant has proposed two options for the fence materials. Option #1 consists of
treated wood posts with wood framing with corrugated metal. Option #2 is a chain link
fence with privacy slats, which provide about 90% screening. Staff would recommend
Option #1, which provides a full screen and will be constructed of materials that will last
longer and will be compatible with the surrounding area. With the construction of the
fence, the applicant will be planting 17 shrubs along the S. 5th St. fence line. In addition,
the applicant will be planting 10 shrubs along the S. 4th St. frontage to help increase the
landscaping/buffering along that corridor.
There are 18 parking spaces required based upon the formula in the UDO for
contractors’ offices and shops. The formula is one parking spaces for every 300 sq. ft.
of floor area of sales and office area, one space for every employee on the maximum
shift, plus one space for every vehicle customarily used in the operation of the use or
Page 2 of 5
stored on the premises. There will be 2,500 sq. ft. of office floor area, four employees
on the maximum shift and six work vehicles used in the operation, which results in 18
required parking spaces. There is a total of 22 marked parking spaces on the lot,
outside of the proposed fenced area. The large paved area generally between the
building and S. 4th St. will not be striped at this time, as there is potential for a future
commercial out-lot in that area.
The staff is recommending some conditions of the approval to bring the site further into
compliance with the UDO including re-striping the parking lot, painting the parking lot
light poles and adding landscaping along S. 5th St. and S. 4th St.
IV. STANDARDS FOR ZONING MAP AMENDMENT
1. The proposed rezoning conforms to the Comprehensive Plan, or conditions
have changed to warrant the need for different types of land uses in that area. The
proposed rezoning is appropriate considering the length of time the property has
been vacant, as originally zoned, and taking into account the surrounding areas
trend in development.
The 2005 Comprehensive Plan recommends the subject site for commercial use. The
property has been listed for sale since 2013. The building’s office area is being leased
out to three business, however its underutilized. The proposed use of a building
contractor’s office and materials storage is consistent with the Comprehensive Plan and
the surrounding area. The proposed outdoor storage area will be screened from view from
S. 5th St. by a fence. The proposed rezoning request will allow the redevelopment of a site
that has remained mostly vacant and underutilized for seven years.
2. The proposed rezoning conforms to the intent and purpose of the Unified
Development Ordinance.
The rezoning of the subject property to PD-C provides the opportunity to more directly
shape the development, use and appearance of this property in accordance with the
City’s UDO regulations and the Comprehensive Plan. The request involves a waiver to
the Unified Development Ordinance for a Planned Development less than two acres,
which has been granted in other locations in the downtown area. The proposal will meet
all other regulations of the UDO and conditions are made part of the approval that will
bring the site further into compliance with the UDO including re-striping the parking lot,
painting the parking lot light poles and adding landscaping along S. 5th St. and S. 4th St.
3. The proposed rezoning will not have a significantly detrimental effect on the
long-range development of adjacent properties or adjacent land uses.
The proposed rezoning should not have a detrimental effect on the adjacent properties
or land uses as it entitles the subject property to a re-use of the property that is
complementary with the adjacent area. The PD-C zoning will allow the outside storage of
materials which will be screened from adjoining properties by a fence and landscaping.
Page 3 of 5
The applicant will be making improvements to the property including adding landscaping,
striping the parking spaces and painting the existing parking lot light poles.
4. The proposed rezoning constitutes an expansion of an existing zoning
district that, due to the lack of undeveloped land, can no longer meet the demand
for the intended land uses.
The subject property is currently zoned “CBD” Central Business District. Rezoning the
property to “PD-C” will allow the site to have outside storage in conjunction with the
contractor’s office. The rezoning will allow for flexibility by the applicant to develop the
property in a manner that will be compatible with the surrounding neighborhood.
5. Adequate public facilities and services exist or can be provided.
Adequate public services are already provided to the subject property. There is a total of
22 parking spaces on-site and 18 spaces are required. In addition, the subject property
lies within adequate service areas for other City services, such as police and fire
protection.
V. PUBLIC INPUT
As of May 15, 2020, there has been no comments submitted to the City from the public
regarding the proposal.
VI. RECOMMENDATION
Sample Motion:
Based upon the submitted petition and testimony presented, I move the Planning and
Zoning Commission forward its findings of fact and recommend to the City Council
approval of a Zoning Map Amendment from the “CBD” Central Business District to the
“PD-C” Planned Development – Commercial District; approval of a waiver to the Unified
Development Ordinance for a Planned Development less than two acres and approval of
a preliminary and final development plan to accommodate a building contractor’s office
and materials storage on the subject site at 421 Grove St. per the plan dated 5-15-20 and
labeled as Exhibit A, Fence Detail Option #1 labeled as Exhibit B and per the conditions
listed in Exhibit C.
Page 4 of 5
Exhibit C – Conditions
1. The storage of all materials must occur indoors or within the eight (8) foot high
fenced area as shown on Exhibit A.
2. No stacking of construction materials higher than eight (8) feet.
3. The following items shall be completed within 30 days after final occupancy of the
building. The time frame may be extended with the City Manager’s approval.
a. Removal of the large bush in front of the handicap accessible parking
space.
b. Stripe the required number of parking spaces (22) in compliance with the
preliminary and final development plan labeled as Exhibit A, and per the
Unified Development Ordinance, the City of DeKalb Municipal Code and the
Illinois Accessibility Code.
c. Clean up the existing landscape areas and remove underbrush, including
the area of the former 18” Spruce as shown on the preliminary and final
development plan labeled as Exhibit A.
d. Plant a minimum of 17 shrubs (mix of deciduous, decorative and evergreen)
along the fence line adjacent to S. 5th St. as shown on the preliminary and
final development plan labeled as Exhibit A.
e. Plant a minimum of 10 shrubs (mix of deciduous, decorative and evergreen)
along the S. 4th St. frontage as shown on the preliminary and final
development plan labeled as Exhibit A.
f. Paint the parking lot light poles.
Page 5 of 5
EXHIBIT B
GENERAL CONTRACTOR
1135 East State Street, P.O. Box 333
Since 1927 Sycamore, Illinois 60178-0333
815/895-9116
Fax 815/895-9324
Rezoning Petition
April 30, 2020
To: City Counsel, City Clerk, and Mayor of DeKalb
Attention: Dan Olsen
Reason for Request:
My wife Christa and I would like to move our 90+year old Construction Company to DeKalb Il. I was raised here,
Christa and I met here. We both went to NIU. Currently our farm is in DeKalb and our kids attend school here. We
recently attained 100% Ownership of Swedberg and Associates currently located in Sycamore. I have been an
owner for nearly 10 years. In that time, we have increased our share almost 400% We are a growing Construction
Company that is looking to continue growth. The location of 421 Grove Street looks to be an ideal place for us to
do business. The office space attached to the connected warehouse is perfect for our operation and gives us room to
grow into. However, that being said, there is one lack of space. Outside storage. We would like to build a fence
from the southern most face of the building North along Fifth Street to encompass the entire lot east and north of
the current building footprint. We want to be good neighbors but need a little extra room to park trailers, trucks
Construction Machines, etc.
Additional Information from Petition Request:
a. We believe this use is still in accordance with the City of DeKalb’s Comprehensive Plan.
b. We believe there to be no impact on adjacent land uses now or in the foreseeable future.
c. We believe this will have a positive impact on adjacent land values as we will rehab a derelict structure
which has been empty for years.
d. By adding a construction Company to the heart of DeKalb, there will be a benefit to the welfare of the
cities population. We will bring jobs to the area. We will purchase goods in the vicinity. We will add
minimal traffic to the area as our construction crews work off site.
Thank you for your time. We hope to become great neighbors and extend relationships within the community.
Matthew H. Gehrke
President
Swedberg and Associates, Inc.
815/895-9116
815/739-6293
mgehrke@swedbergs.com
Since 1927
LEGAL NOTICE
NOTICE is hereby given that a public hearing will be held before the DeKalb Planning and Zoning
Commission at its regular meeting on Wednesday, May 20, 2020, at 6:00 p.m. in the DeKalb
Municipal Building, 200 South Fourth Street, DeKalb, Illinois, on the petition by Christa and Matt
Gehrke for approval of the rezoning of 421 Grove St. from the “CBD” Central Business District
to the “PD-C” Planned Development – Commercial District and approval of a preliminary and
final development plan to accommodate a building contractor’s office and materials storage on the
subject site. Consideration to approve a waiver to the Unified Development Ordinance for a
Planned Development less than two acres is also requested and other approvals as required for the
subject property to allow for the development as proposed. The subject site is 1.24 acres and has
PIN’s of 08-23-302-024 and 08-23-302-013 and is commonly known as 421 Grove St., DeKalb,
IL.
All interested persons are invited to appear and be heard at the time and place listed above.
Interested persons are also encouraged to submit written comments on the proposal to the City of
DeKalb, Community Development Department, 200 South Fourth Street, DeKalb, Illinois, 60115
by 4:00 p.m. on Wednesday, May 20, 2020, by e-mail to dan.olson@cityofdekalb.com or the
Online Public Comment Submission Form at https://www.cityofdekalb.com/FormCenter. Further
information regarding the petition is available from the Community Development Department at
(815) 748-2070 or on the City of DeKalb’s web page at
https://www.cityofdekalb.com/1103/Public-Hearings.
Max Maxwell, Chair
DeKalb Planning and Zoning Commission