Capital Improvements Commission
Regular MeetingGlen Ellyn, IL · September 10, 2025
Minutes
Village of Glen Ellyn
Meeting Minutes
Village of Glen Ellyn
Capital Improvements Commission
September 10, 2025
7:00 PM
Glen Ellyn Civic Center Room 301
Board or Commission: Capital Improvements Date: September 10, 2025
Meeting: Regular Called to Order: 7:00 p.m.
Quorum: Yes Adjourned: 9:32 p.m.
Member Attendance:
Rocco Zucchero Chair Present
Joel Baldin Commissioner Present
Tom Drapinski Commissioner Present
Orion Galey Commissioner Present
John MacDonald Commissioner Present
Adil Saeed Commissioner Absent
David Warnick Commissioner Present
Jill Ziegler Commissioner Present
Donna Jean Simon Trustee Liaison Present
Richard Daubert Staff Liaison/Professional Engineer Present
Also Present:
John Hubsky Public Works Director
Derek Peebles Assistant Village Engineer
A. CALL TO ORDER
The September 10, 2025 meeting of the Capital Improvements Commission was called to order by
Chairman Zucchero at 7:00 p.m. at the Glen Ellyn Civic Center.
B. PUBLIC COMMENT – None
Capital Improvement
September 10, 2025
Meeting Minutes | 2
C. APPROVAL OF MINUTES
APPROVAL OF AUGUST 13, 2025 CAPITAL IMPROVEMENTS COMMISSION
MEETING MINUTES
MOTION TO APPROVE THE AUGUST 13, 2025 CAPITAL IMPROVEMENTS
COMMISSION MEETING MINUTES
MOTION BY: Commissioner Ziegler
SECOND BY: Commissioner Warnick
AYES: Zucchero, Baldin, Drapinski, Galey, MacDonald, Warnick, Ziegler
RESULT: APPROVAL
D. CURRENT BUSINESS
1. 2026-2030 Capital Improvement Plan and 2026 Capital Improvements Budget
Engineer Daubert reviewed the CIP and 2026 Capital Improvements Budget
presentation with the CIC, noting that the plan spans 2026 through 2030 and totals
$140 million in expenditures. Of this amount, $98 million is designated for capital
improvements, primarily roadway projects, $15 million is allocated for debt service
payouts, and $27 million is for water and sewer fund projects. Trustee Simon asked
what is included in the debt service, and Daubert explained that it covers the Civic
Center Remodeling, the Civic Center Parking Garage, the Central Business District Streetscape
and Utility Improvements, and the Metra/Phase 4 Streetscape and Utility Improvements.
Daubert further explained that the plan assumes approximately $38.5 million in grants,
including $33.9 million for the Metra Station, Underpass, and Crescent Boulevard
improvements and $4.6 million for the Street Rehabilitation Program. The plan also
includes an additional $9 million in general obligation bonds, structured to remain
under $10 million in order to secure a better interest rate. Daubert noted that this level
of bonding will be scrutinized by staff and the board. Projections show that even with the
$9 million in bonds, the fund balance is expected to be $330,000 in the red by 2029,
although the fund does recover over time. He added that additional revenue could come
from TIF funds or other village resources and that many project costs have historically
come in below the original estimates.
Daubert reported that major contributors to the 2025–2029 Capital Fund balance
include the Metra Station/Streetscape Phase 4 at approximately $47 million with $34
million in outside funding, the Street Program including construction and engineering at
approximately $35 million with $3.4 million in outside funding, the Traffic Signal
Modernization at approximately $2.6 million, and the Roosevelt Road Streetlight Fixture
Replacement and Streetscape Design at approximately $3.4 million. He also reviewed
the major contributors to the Water and Sewer Fund balance, which include water main
replacement and rehabilitation at approximately $14 million and the lead service line
replacement mandate at approximately $5 million.
Capital Improvement
September 10, 2025
Meeting Minutes | 3
Daubert emphasized that the board has been primed on these issues and that
discussions will continue over the next year. He added that the village will continue to
explore grant opportunities, PCI surveys to guide street rehabilitation timelines, water
and sewer system improvements, future bond financing, project engineering, and
revenue reviews, particularly with regard to water and sewer rates.
Next, Engineer Daubert reviewed the 2026 Capital Project Budget, which includes $15.1
million in capital projects, $4.8 million in water projects, and $2.5 million in sewer
projects. He also provided an update on the 2025 major roadway, water, sewer, and
engineering design projects. Daubert then highlighted the 2026 miscellaneous initiatives
and expenditures, which include the Stormwater Drainage Program at approximately
$10,000, street lighting replacement at approximately $116,000, professional services
such as traffic counts and topographic surveys at approximately $10,000, engineering
software at approximately $6,500, and a speed limit adjustment study and associated
signage, each budgeted at $35,000.
Daubert noted that the speed limit items reflect ongoing discussions at the board level
regarding the possibility of lowering residential speed limits. While there appears to be
interest from the board, it is not yet clear what direction will ultimately be taken. The
budget anticipates the cost of a study, as well as the signage that would be required if
speed limits are reduced. He added that any change would also require consideration of
enforcement measures. Trustee Simon commented that pending state legislation could
mandate reducing residential speed limits to 20 MPH, and the board should consider
this possibility before committing to spending. Daubert confirmed that staff has been
asked to issue an RFP for a speed study and stated that the CIC would be included in
that process.
Commissioner MacDonald expressed concern about spending $70,000 if safety is not
clearly an issue with respect to speed, noting that other factors, such as rolling stops or
drivers ignoring stop signs can also contribute to hazards. He cautioned against being
shortsighted and suggested that enforcement may be a more effective solution. Daubert
responded that a more productive outcome would be for the CIC to recommend
broadening the scope beyond speed alone, by reviewing high-incident areas and
determining whether speed or other factors are the primary cause. Trustee Simon added
that residents have already brought safety concerns to the board, which is why a study
has been requested to gather data on the root causes. Chairman Zucchero noted there
is value in looking at the data, adding that many streets could potentially qualify for
reduced speed limits. He explained that while a speed study would not be a heavy lift, a
broader safety study may be, in light of all the projects already underway. Engineer
Peebles added that funding opportunities, such as Safe Routes to School funds, may
help support the initiative, and although staffing is limited, it remains an important
priority.
Engineer Daubert asked the commission if there were any comments or concerns
regarding the 2026–2030 Capital Improvement Plan or the 2026 Capital Improvements
Budget. Chairman Zucchero stated that he was comfortable with the plan as presented.
Commissioner Galey suggested exploring project contingencies to address the projected
$330,000 shortfall.
Capital Improvement
September 10, 2025
Meeting Minutes | 4
Commissioner Baldin motioned to approve the 2026-2030 Capital Improvement Plan and 2026
Capital Improvements Budget; Commissioner MacDonald seconded the motion. The motion
unanimously passed.
MOTION TO RECOMMEND TO THE GLEN ELLYN VILLAGE BOARD THE APPROVAL
OF THE 2026-2030 CAPITAL IMPROVEMENT PLAN AND 2026 CAPITAL BUDGET
ITEMS
MOTION BY: Commissioner Baldin
SECOND BY: Commissioner MacDonald
AYES: Zucchero, Baldin, Drapinski, Galey, MacDonald, Warnick, Ziegler
RESULT: APPROVAL
2. Metra Station Warming Shelter Followup
Engineer Daubert provided a follow-up on the Metra station warming shelter project, noting he
had received updated cost information from CDM Smith the previous Friday. To help reduce
overall project costs, the current plans are being reconsidered. The original design called for two
elaborate brick and mortar warming shelters, but the inbound shelter is now proposed for
elimination. Passengers would still have access to a covered area at the end of the depot, along
with on-demand heating mechanisms.
On the outbound side, the question remains whether to maintain the originally proposed ornate
brick and mortar structure or to simplify it with a prefabricated structure would result in further
cost savings. Daubert presented an image of the revised shelter concept, explaining it would be a
prefabricated structure with lighting and on-demand heat, but not fully enclosed. Two cost-saving
alternatives were reviewed: Alternate 1 would eliminate the inbound shelter while keeping the
ornate brick and mortar outbound shelter for a cost of $650,000, a savings of $361,000 over two
ornate brick and mortar warming shelters. Alternate 2 would provide a prefabricated outbound
shelter with on-demand heat only, at a cost of $350,000, while still maintaining a heated covered
area on the inbound side.
Commissioner MacDonald questioned the need for an outbound shelter given that none currently
exists. Daubert clarified that Metra requires a shelter for when the depot is closed with the loggia
at the end of the depot serving as the inbound shelter if it has on-demand heat. On the outbound
side, the prefabricated or brick and mortar structure would serve the shelter requirement.
Discussions advanced relative to whether or not a wind screen should be provided for the inbound
shelter area under the station loggia. Commissioner Baldin suggested evaluating the area under
the soffit on the south side of the depot for meeting the inbound shelter requirement. After further
discussion, Commissioners Galey, Baldin, Ziegler, Drapinski, Warnick, and Chairman Zucchero
expressed preference for Alternate 2, which would include the prefabricated shelter on the
outbound (south) side of the tracks and eliminate the warming shelter on the inbound (north) side
of the tracks but use the roof overhand area with on-demand heat and no windscreen. Among
other factors, the wind screen was of concern for aesthetic and functional reasons. Commissioner
MacDonald, however, preferred eliminating warming shelters entirely, relying instead on existing
covered roof areas without heat or wind protection.
Capital Improvement
September 10, 2025
Meeting Minutes | 5
E. TRUSTEE’S REPORT – Trustee Simon provided several updates, noting that the Village is
currently in the budget process, with meetings planned through November. The Board recently
approved funding for lead service line replacements. Additionally, the Village is in the process of
filling the Trustee vacancy on the Village Board. To date, 11 applications have been received, and
several candidates have been interviewed. The appointment is at the discretion of the Village
President, with the Board able to provide input.
F. OTHER BUSINESS – None
G. PUBLIC WORKS REPORT – Public Works Director Hubsky provided several updates, noting that
the Village is still seeking to fill an Assistant Public Works Director position. In the meantime, the
team has been covering those responsibilities, and the goal is to have someone hired soon.
Preparations for winter are underway, including reviewing brine supplies, and equipment with some
new equipment expected to arrive in January. A major focus for the department is assessing space
needs at Village facilities. Staff is reviewing how neighboring communities manage access to their
yards and facilities and are conducting a facilities study to determine the village’s requirements.
H. PROJECT REPORT – Engineer Peebles provided several updates. Work on the
Crescent/Glenwood station parking lot is progressing ahead of schedule and is expected to be
completed by November 7. Full demolition is underway, and once resurfacing begins, the lot will be
fully closed. Drivers will be directed to nearby parking lots during this phase.
For the CBD Streetscape project, the team continues to press Alamp on tree replacement and concrete
brick punch list items. The 2025 Reconstruction project is also moving forward, with much of the
street resurfacing already completed.
Engineer Daubert added that progress continues on the Roosevelt Road bridge work near Baker Hill
Drive, with completion targeted for November. He also noted that the ADA transition plan is
advancing, with a consultant next scheduled to host public outreach on October 4 at 10:00 a.m. at the
fire station downtown.
I. ADJOURNMENT – Commissioner Drapinski motioned and Commissioner Galey seconded to
adjourn the meeting. The motion is unanimously approved, and meeting adjourned at 9:32 p.m.
Submitted by Elisa Pollina, Recording Secretary
Reviewed by: Richard Daubert, Professional Engineer
Agenda
Agenda
Village of Glen Ellyn
Capital Improvements Commission Meeting
Wednesday, September 10, 2025
7:00 PM
Glen Ellyn Civic Center, Room 301
Any individual with a disability requiring a reasonable accommodation in order to participate in a meeting should
contact The Village of Glen Ellyn ADA Coordinator, 630-469-5000, at least five (5) business days in advance of
the next scheduled meeting. All matters on the Agenda may be discussed, amended, and acted upon.
A. Call to Order
B. Public Comment
C. Approval of Minutes
1) Motion to approve the August 13, 2025 Capital Improvements Commission
Meeting Minutes
D. Current Business
1) 2026-2030 Capital Improvement Plan and 2026 Capital Improvements Budget
2) Metra Station Warming Shelter Followup
E. Trustee Liaison's Report
F. Other Business
G. Public Works Report
H. Project Report
1) Engineering Division Project Activity Report September 5, 2025
I. Adjourn
Village of Glen Ellyn
Packet
Agenda
Village of Glen Ellyn
Capital Improvements Commission Meeting
Wednesday, September 10, 2025
7:00 PM
Glen Ellyn Civic Center, Room 301
Any individual with a disability requiring a reasonable accommodation in order to participate in a meeting should
contact The Village of Glen Ellyn ADA Coordinator, 630-469-5000, at least five (5) business days in advance of
the next scheduled meeting. All matters on the Agenda may be discussed, amended, and acted upon.
A. Call to Order
B. Public Comment
C. Approval of Minutes
1) Motion to approve the August 13, 2025 Capital Improvements Commission
Meeting Minutes
D. Current Business
1) 2026-2030 Capital Improvement Plan and 2026 Capital Improvements Budget
2) Metra Station Warming Shelter Followup
E. Trustee Liaison's Report
F. Other Business
G. Public Works Report
H. Project Report
1) Engineering Division Project Activity Report September 5, 2025
I. Adjourn
Village of Glen Ellyn
Page 1 of 51
Glen Ellyn Capital Meeting 9/10/2025 7:00 PM
Improvements Commission Department: Public Works - Internal Services
535 Duane Street Department Head: John Hubsky
Glen Ellyn, IL 60137 Category: Minutes
Prepared By: Richard Daubert
AGENDA ITEM (ID # 2025- DOC ID: 2025-764
764)
Motion to approve the August 13, 2025 Capital Improvements
Commission Meeting Minutes
Statement of the Issue:
The draft meeting minutes for the August 13, 2025 Capital Improvements Commission Meeting are
attached hereto for review and consideration of approval.
Analysis:
Budget Impact:
Contribution to Strategic Plan
Action Requested:
Attachments:
1. CIC Meeting Minutes August 13 2025 - Draft
Page 2 of 51
Village of Glen Ellyn
Meeting Minutes
Village of Glen Ellyn
Capital Improvements Commission
August 13, 2025
7:00 PM
Glen Ellyn Civic Center Room 301
Board or Commission: Capital Improvements Date: August 13, 2025
Meeting: Regular Called to Order: 7:03 p.m.
Quorum: Yes Adjourned: 9:05 p.m.
Member Attendance:
Rocco Zucchero Chair Present
Joel Baldin Commissioner Absent
Tom Drapinski Commissioner Present
Orion Galey Commissioner Present
John MacDonald Commissioner Absent
Adil Saeed Commissioner Present
David Warnick Commissioner Absent
Jill Ziegler Commissioner Present
Donna Jean Simon Trustee Liaison Present
Richard Daubert Staff Liaison/Professional Engineer Present
Also Present:
A. CALL TO ORDER
The August 13, 2025 meeting of the Capital Improvements Commission was called to order by
Chairman Zucchero at 7:03 p.m. at the Glen Ellyn Civic Center.
The Commission took a moment to reflect upon the unfortunate passing of Village Trustee Steve
Szymanski. The Commission expressed its appreciation of his service and significant contributions to
Glen Ellyn.
B. PUBLIC COMMENT – None
Page 3 of 51
Capital Improvement
August 13, 2025
Meeting Minutes | 2
C. APPROVAL OF MINUTES
APPROVAL OF JUNE 11, 2025 CAPITAL IMPROVEMENTS COMMISSION
MEETING MINUTES
MOTION TO APPROVE THE JUNE 11, 2025 CAPITAL IMPROVEMENTS COMMISSION
MEETING MINUTES
MOTION BY: Commissioner Saed
SECOND BY: Commissioner Zucchero
AYES: Zucchero, Drapinski, Galey, Saeed, Ziegler
RESULT: APPROVAL
D. CURRENT BUSINESS
1. DuPage County Safety Action Plan
Engineer Daubert provided an overview of the DuPage County Safety Action Plan. He noted that
generally speaking, fatal and serious injury accidents are on the rise. The plan provides guidance
to DuPage communities to implement countermeasures. Items of focus that the Village has, and/or
will continue to review include speed management, intersection improvements, improved
pedestrian accommodations, and cyclist accommodations.
Engineer Daubert noted that there is a push in the community to adjust the speed limit to 25 miles
per hour. Commissioner Zucchero spoke to the need for more attention to pedestrians. He also
inquired about the speed limit adjustment and the need for more signage.
Engineer Daubert discussed intersection improvements that have been made such as in the
downtown. He also overviewed how the Village has implemented signal timing improvements
such as Park and Sheehan and Kenilworth and Geneva (through DuPage County). He also
discussed how the Village has been upgrading sidewalk throughout the community.
Engineer Daubert noted that we have not done much in terms of bike routes/accommodations.
Chair Zucchero added that we should add sharrows on Park Boulevard and find a way to connect
the downtown to COD. Engineer Daubert noted there was some prior political pushback on
sharrows but we can certainly revisit the matter. Commissioner Saeed expressed a desire for more
protected bike lanes. Engineer Daubert noted we do have them on Lambert Road, other Village
streets are not generally wide enough.
Street lighting was also generally discussed with one focal location being around the train station;
it was noted that it is hard to see people walking particularly by Crescent.
Commissioner Zucchero suggested consideration of a safety plan or mobility plan that would
review where we have the greatest incidents in town and overlay the issue areas with development
and capital plans.
Page 4 of 51
Capital Improvement
August 13, 2025
Meeting Minutes | 3
Roosevelt Road was discussed as one of the higher incident areas. Commissioner Saeed expressed
concerns with safety on Roosevelt Road with mention of sidewalks being right along the travel
lanes.
Engineer Daubert noted that a group of people will be presenting to the Village Board about the
Drive 25 campaign on August 25th. The matter may be revisited by the CIC depending on Village
Board feedback.
Engineer Daubert noted he’s not looking for any particular action from the CIC on this matter but
that we can continue to look at ways to implement traffic safety improvements in capital projects.
E. TRUSTEE’S REPORT – Trustee Simon gave a brief report and noted that there has been some
ongoing training for commissions as to help clarify their roles for the Village. Trustee Simon also
expressed her sorrow for Trustee Steve Szymanski’s passing. She noted that the Board will work
through a process to fill the Trustee vacancy.
F. OTHER BUSINESS – None
G. PUBLIC WORKS REPORT – Engineer Daubert briefly overviewed that the Village is working
through the recruitment process to hire a new Public Works Director.
H. PROJECT REPORT – Engineer Daubert briefly reviewed the Engineering Division Project Activity
Report with the Capital Improvements Commission.
I. ADJOURNMENT – Commissioner Galey motioned and Commissioner Saeed seconded to adjourn
the meeting. The motion is unanimously approved, and meeting adjourned at 9:05 p.m.
Submitted and Reviewed by: Richard Daubert, Professional Engineer
Page 5 of 51
Glen Ellyn Capital Meeting 9/10/2025 7:00 PM
Improvements Commission Department: Public Works - Internal Services
535 Duane Street Department Head: John Hubsky
Glen Ellyn, IL 60137 Category: Budget
Prepared By: Richard Daubert
AGENDA ITEM (ID # 2025- DOC ID: 2025-766
766)
2026-2030 Capital Improvement Plan and 2026 Capital Improvements
Budget
Statement of the Issue:
Please see the attached materials pertaining to this agenda item.
Analysis:
Budget Impact:
Contribution to Strategic Plan
Action Requested:
Attachments:
1. PW Engineering Memo on CY2026 Budget to CIC
2. CY2026 CIP and Budget Presentation
3. 2026 CIP Map
4. CIP Updated 9-4-2025
Page 6 of 51
MEMORANDUM
TO: Capital Improvements Commission
FROM: Rich Daubert, Professional Engineer
DATE: September 8, 2025
RE: 2026-2030 Capital Improvement Plan and CY2026 Budget Items
Introduction
Staff is pleased to present the Public Works Engineering Division Calendar Year 2026 Budget
Items and 2026-2030 Capital Improvement Plan. Staff will utilize the September 10th Capital
Improvements Commission Meeting to review these items with the CIC. The attached
PowerPoint Presentation will be utilized to lead the review. Summaries of the CIP and Budget
Items are as follows.
Executive Summary of the 2026-2030 Capital Improvement Plan
The CIP includes approximately $130M in engineering and construction projects and
approximately $15M in debt service payments for bonds associated with the Police Station, Civic
Center Renovations, Civic Center Parking Garage, CBD Streetscape and Utility Improvements
Project (CBD SUI), and Metra Station/Underpass/Phase 4 CBD SUI.
For 2026-2030, the CIP shows approximately $38.5M in grant revenues for roadway projects and
the Metra Station/Underpass/Phase 4 CBD SUI Project. It is emphasized that the Village has not
secured this total grant amount to date. However, staff does continue to apply for and secure
outside funding for projects. The plan includes the Metra Station/Underpass/Phase 4 Streetscape
Project. However, it is noted that expenditures and grants for the project extend beyond 2030.
$9M in General Obligation Bonds are shown to be issued in 2026 with an estimated coinciding
debt service of approximately $720,000/year.
As it relates to pavement management and roadway condition, staff has looked further out into 10-
and 20-year timelines to ensure that the CIP is including sufficient funding to maintain the
Village’s pavement condition index score of 70. For 2026-2035, approximately $65M in funding
was estimated as necessary to maintain the Village’s streets at a PCI of 70; approximately $69M is
programmed in the outyears of the CIP. For 2026-2045, approximately $146M in funding was
estimated as necessary to maintain the Village’s streets at a PCI of 70; approximately $164M is
programmed in the outyears of the CIP.
CIVIC CENTER 535 DUANE STREET GLEN ELLYN, ILLINOIS 60137 630.469.5000 FAX 630.469.8849
Page 7 of 51
Public Works Engineering Division Presentation of September 8, 2025
CY2026 Budget Items and Draft 5-Year Capital Improvement Plan Page 2
Executive Summary of the 2026 Calendar Year Engineering Budget Items
The Draft 2026 Budget includes rehabilitation of approximately 6.6 centerline miles of Village
streets. The resurfacing of Lambert Road (Woodcroft to Roosevelt Road) as well as Riford Road
(Crescent to St. Charles Road), are eligible and in position for securing approximately $1.5M in
federal funding.
Staff is proposing to continue replacing lead water service lines on streets being rehabilitated as to
minimize disturbance and costs associated with the lead service line replacement. Water main
replacement is proposed on Anthony Street and Marion Avenue. Funding for sewer replacements
and repairs is included as well.
Pavement maintenance and sidewalk repairs continue to be a feature of the Budget. Pavement
maintenance continues to feature surface treatments, cracksealing, and patching. Sidewalk repairs
will be in the form of both removal and replacement as well as sawing of vertical displacements
between sidewalk panels.
Engineering assignments include design of future street rehabilitation projects including future
federal aid eligible resurfacing of South Park Boulevard (Raintree to Roosevelt), Pennsylvania
Avenue (Western to west Village limit), pavement management services, and supplemental funds for
the design of a federal aid eligible project on Sheehan Avenue (Park to Route 53).
Action Requested
Public Works Engineering Staff will present this matter to the Capital Improvements Commission at
its September 10th Meeting. Staff ultimately requests the Capital Improvements Commission’s
review, input, and support on the proposed budget items as to keep the maintenance and
improvement of the Village’s infrastructure moving forward.
Attachments
1. CY2026 Engineering Division Budget Presentation
2. 2026 CIP Major Projects Map
3. 2026-2030 Capital Improvement Plan
Page 8 of 51
Village of Glen Ellyn
Public Works Department
Engineering Division
2026-2030 CIP and
2026 Budget Items
September 10, 2025
Capital Improvements
Commission
Meeting Presentation
1/17
Page 9 of 51
Capital Improvement Plan Overview
5-Year Capital Improvement Plan (2026-2030)
• ~$145M Total Expenditures
o ~$98M Capital Projects Fund Improvements
o ~$15M Capital Projects Fund Debt Service
o ~$32M Water and Sewer Fund
• ~24 Miles of Roadway Rehabilitation
• ~ $16M Allocated For Water Main Replacement Which Can Include
Some Lead Service Line Replacement Work. LSLR Mandate And Plan
Still Needs Development Including Scrutiny Of Water Main
Replacement Work And Funding Mechanisms.
2
Page 10 of 51
Capital Improvement Assumptions
• Plan Assumes ~$38.5M In Grants
o ~$33.9M Metra Station, Underpass, and Crescent Blvd. Imp.
o ~4.6M Street Rehabilitation Program
• Future Street Project DCEO Grant - $1.2M
• Lambert Rd. Resurfacing (Roosevelt to S. Limit) - $1.2M
• Riford Rd. Resurfacing (Crescent to St. Charles) - $340K
• South Park Blvd. Resurfacing (Roosevelt to S. Limit) - $977K
• Pennsylvania Ave (West Limit to Western) - $537K
• Includes Metra Station/Underpass/Phase 4 Streetscape With
Expenditures Beyond 2029
• Includes Additional $9M General Obligation Bond Issuance In 2026
With Assumed Debt Service Of ~$720,000/Year
3
Page 11 of 51
CPF Balances
Draft Capital Projects Fund Balance In Packet
CY2025 CY2026 CY2027 CY2028 CY2029 CY2030
FORECAST FORECAST FORECAST FORECAST FORECAST FORECAST
$ (1,071,912) $ 6,760,809 $ (7,132,082) $ (1,303,815) $ (2,059,159) $ 2,258,077
$ 4,476,729 $ 3,404,817 $ 10,165,625 $ 3,033,544 $ 1,729,728 $ (329,431)
$ 3,404,817 $ 10,165,625 $ 3,033,544 $ 1,729,728 $ (329,431) $ 1,928,646
Major contributors to 2025-2029 fund balance
• Metra Station/Streetscape Phase 4 ~$47M with ~$34M Outside Funding
• Street Program Including Construction and Engineering ~$35M with $3.4M Outside Funding
• Traffic Signal Modernization ~ $2.6M
• Roosevelt Road Streetlight Fixture Replacement and Streetscape Design ~3.4M
4
Page 12 of 51
Water & Sewer Fund Balance
Water & Sewer Fund Balance is Negative in 2030
CY2026 CY2027 CY2028 CY2029 CY2030
FORECAST FORECAST FORECAST FORECAST FORECAST
$ (4,328,233) $ (1,636,001) $ (4,567,425) $ (681,446) $ (703,000)
$ 11,485,501 $ 7,157,267 $ 5,521,266 $ 953,842 $ 272,395
$ 7,157,267 $ 5,521,266 $ 953,842 $ 272,395 $ (430,605)
Major contributors to fund balance are:
• Water Main Replacement/Rehabilitation ~$14M
• Lead Service Line Replacement Mandate ~$5M
5
Page 13 of 51
Capital Improvement Plan Summary
Continued CIP planning and adjustments are needed with the
following items of particular emphasis
• Grant Funding Opportunities
– Metra Station, Street Program
• Street Rehabilitation Timeline and Implications
– PCI Survey Update
• Water and Sewer System Improvements/Master Planning
• Next General Obligation Bond Series Amount/Timeline
• Project Value Engineering and Bids
• Review of Revenues Particularly Water/Sewer
6
Page 14 of 51
Capital Projects
~ $15.5M
2026
Capital
Water Projects
Budget
~ $4.8M
~$22.8M
Sewer Projects
~ $2.5M
7
Page 15 of 51
2025 Major
Roadway Projects
Street Rehabilitation Project
(~6.6 Miles) ~ $7.9M
❑ $5.5M Capital/MFT/Grants
❑ $1.3M Water
❑ $1.1M Sewer
8
Page 16 of 51
2026 CIP
Project Areas
9
Page 17 of 51
2025 Major
Roadway Projects
(Continued)
• Asphalt Pavement Preservation
$390K Capital
– Asphalt Street Patching - $250K
– Rejuvenator - $90K
– Crack Sealing - $50K
• Concrete Street Patching
$250K Capital
10
Page 18 of 51
2025 Major
Roadway Projects
(Continued)
• Sidewalk Removal and
Replacement Program -
$250K Capital
• Sidewalk Sawing Repair
Program - $60K Capital
11
Page 19 of 51
2025 Major Water/Sewer Projects
• Hill Avenue Water and Sewer Improvements ~ $3.3M
– $2.3M Water
– $1M Sewer
12
Page 20 of 51
2025 Major Engineering Design Projects
• Engineering for Future Projects ~ $1,042,816 Capital
– Utility and Roadway Improvements: ~$697K ($508K Capital, $114K
Water, $75K Sewer)
– Federal Aid Projects:
• Park Boulevard (Roosevelt to Raintree): $200,000
• Pennsylvania Avenue (West Limit to Western): $125,000
• Sheehan Avenue (Park to IL-53) IDS Supplement: $124,890
13
Page 21 of 51
2026 Miscellaneous
Initiatives/Expenditures
• Stormwater Drainage Program ~$10K Capital
• Street Lighting Replacement ~$116K Capital
• Prof. Services (Traffic Counts, Topo Survey) ~ $10K Capital
• Engineering Software ~ $6.5K Capital
• Speed Limit Adjustment Study: $35K
• Speed Limit Adjustment Signage: $35K
14
Page 22 of 51
End of Presentation
• Questions, Comments, & Input on CIP &
Budget
15
Page 23 of 51
Village of Glen Ellyn
2026 Major Roadway/Utility Projects
Street Resurfacing
Street/Water/Sewer Rehab.
Federal Aid Eligible Project
Page 24 of 51
VILLAGE OF GLEN ELLYN 2025-2030 CAPITAL IMPROVEMENT PLAN
CAPITAL PROJECTS FUND
CY2025 CY2026 CY2027 CY2028 CY2029 CY2030
Capital Fund FORECAST FORECAST FORECAST FORECAST FORECAST FORECAST
Revenues:
Property Taxes $ 4,746,022 $ 4,905,868 $ 4,979,456 $ 5,054,148 $ 5,129,960 $ 5,206,909
Food and Beverage Tax (1.5%) 1,909,000 1,937,700 1,976,454 2,015,983 2,056,303 2,097,429
Drainage Infrastructure Fee 145,000 145,000 145,000 145,000 145,000 145,000
CBD TIF Contributions to Capital Projects 300,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000
Roosevelt Road TIF Contributions to Capital Projects - - 450,000 150,000 - -
Parking Fund Contributions to Capital Projects 341,902 17,994 - - - -
General Obligation Bond for CBD Projects - 9,000,000 - - - -
Bond Premium - 500,000 - - - -
Telecommunications Tax 345,000 340,000 323,000 306,850 291,508 276,932
Electricity Use Tax 902,000 902,000 950,000 950,000 950,000 950,000
Natural Gas Use Tax 322,000 322,000 322,000 322,000 322,000 322,000
Real Estate Transfer Tax 740,000 700,000 714,000 728,280 742,846 757,703
Grant Revenue 500,000 1,869,709 12,700,000 16,000,000 5,913,947 2,000,000
Forfeiture Funds (Reimburse Police Station) - 150,000 150,000 - - -
Future MFT Projects - - 1,000,000 1,000,000 1,000,000 1,000,000
2025 Street Resurfacing Project MFT Expenditures 1,807,363 - - - - -
2025 Street Resurfacing Rebuild IL (MFT) Expenditures 1,235,544 - - - - -
Crescent Rebuild IL (MFT) Expenditures 149,516 - - - - -
Crescent and Glenwood Parking Lot MFT Expenditures 150,394 8,273 - - - -
Lambert Road Resurfacing MFT Expenditures - 1,000,000 - - - -
Riford Road Resurfacing MFT Expenditures - 300,000 - - - -
General Fund Contribution to Capital Projects - 2,000,000 500,000 500,000 500,000 500,000
Village Links (Panfish one time transfer) 100,000 - - - - -
Interest Income 195,000 102,000 203,000 61,000 35,000 -
Total Revenues $ 13,888,741 $ 25,200,545 $ 25,412,910 $ 28,233,261 $ 18,086,563 $ 14,255,973
PAGE 1/6
Page 25 of 51
VILLAGE OF GLEN ELLYN 2025-2030 CAPITAL IMPROVEMENT PLAN
CAPITAL PROJECTS FUND
CY2025 CY2026 CY2027 CY2028 CY2029 CY2030
Capital Fund FORECAST FORECAST FORECAST FORECAST FORECAST FORECAST
Expenditures:
Non-Roadway Construction Projects:
Minor capital investment/other expenditures $ 14,000 $ 16,500 $ 17,000 $ 17,500 $ 18,000 $ 18,500
Street Lighting Improvements - Repairs and Requests 26,158 116,000 50,000 50,000 50,000 50,000
Stormwater Drainage Improvements Program 3,000 10,000 10,000 10,000 10,000 10,000
Glen Crest Creek Maintenance and Monitoring 2,360 11,200 7,500 7,500 - -
Consultant Reviews For Capital Projects - 7,500 5,000 5,200 5,400 5,600
Traffic Signal Modernization Project 161,353 1,249,700 567,200 - 753,100 -
IDOT Traffic Signal Upgrade IL-53/Spring - 20,000 - - - -
Speed Limit Adjustment Study and Signage (Placeholder) - 70,000 - - - -
Wayfinding Signage - - 100,000 - - -
Bike Plan Update - - - - - -
Panfish Park Improvements 21,965 300,000 - - - -
Duane Street/Forest Avenue Undergrounding (TBD) - - - - - -
GF3 Taylor Avenue Pedestrian Tunnel 306,280 - - - - -
GF4,5,6,7,8, 15, 16 Train Station/Pedestrian Underpass 1,484,428 2,251,227 16,519,958 16,150,000 9,538,000 2,150,000
Sidewalk Removal and Replacement Program 151,298 250,000 250,000 250,000 250,000 250,000
Sidewalk Sawing Repair Program 35,842 60,000 60,000 60,000 60,000 60,000
Retaining Wall Relacement Design - 25,000 - - - -
New Sidewalk Program - - - - - -
Roosevelt Road Streetlighting Replacement - 108,000 1,501,852 1,501,852 - -
Roosevelt Road Streetscape Improvements - - 298,259 - - 2,684,333
Subtotal - Non-Roadway Construction Projects $ 2,206,685 $ 4,495,127 $ 19,386,769 $ 18,052,052 $ 10,684,500 $ 5,228,433
PAGE 2/6
Page 26 of 51
VILLAGE OF GLEN ELLYN 2025-2030 CAPITAL IMPROVEMENT PLAN
CAPITAL PROJECTS FUND
CY2025 CY2026 CY2027 CY2028 CY2029 CY2030
Capital Fund FORECAST FORECAST FORECAST FORECAST FORECAST FORECAST
Expenditures: Roadway Rehabilitation Program
Asphalt Street Patching Program $ 188,701 $ 250,000 $ 250,000 $ 250,000 $ 250,000 $ 250,000
Concrete Street Patching and Rehabilitation Program 300,000 250,000 100,000 100,000 100,000 100,000
Cracksealing 40,074 50,000 50,000 50,000 50,000 50,000
Asphalt Surface Treatment 81,491 90,000 150,000 140,000 90,000 100,000
Pavement Management Program 12,395 29,851 75,000 30,000 13,951 50,000
GF1 North Park/Main Street Improvements 13001 - 412,071 - - - -
2022 Street Program 22002 181,475 - - - - -
GF9 Crescent Boulevard LAFO 157,528 - - - - -
2024 Utility and Roadway Improvements Project 287,202 - - - - -
2025 Street Resurfacing Project 3,050,863 - - - - -
2025 Utility and Roadway Improvements Project 2,954,976 - - - - -
2026 Utility and Roadway Improvements Project - 5,449,251 - - - -
GF10 Lambert Road Improvements 317 2,326,244 - - - -
GF11 Riford Road Improvements 315 681,700 - - - -
Sheehan Avenue Improvements - 124,890 - 3,283,827 - -
Taft Avenue and Exmoor Avenue Roadway Improvements 38,391 46,864 2,151,920 - - -
Wingate Basin Water & Sewer Utility Improvements (TBD) - - - - - -
GF12 Park Boulevard Resurfacing Project - 200,000 - - 1,628,293 -
GF13 Pennsylvania Avenue Resurfacing Project - 125,000 - - 894,952 -
Future Street Resurfacing/Reconstruction Projects - - 6,744,761 4,077,331 2,895,066 2,643,551
Engineering for Future Street Projects 288,587 507,670 306,896 217,908 198,977 234,372
CBD Streetscape and Utility Improvements 15006 993,816 - - - - -
CBD Streetscape and Utility Improvements 15006 - Alley 179,236 8,658 - - - -
Crescent and Glenwood Parking Lot Improvements 15006 1,396,200 70,586 - - - -
IFT / General Fund Engineering 309,000 315,000 321,000 327,000 334,000 341,000
IFT/ Food and Beverage Collection Cost 53,400 53,400 53,400 53,400 53,400 53,400
Subtotal - Roadway Rehabilitation Program $ 10,513,969 $ 10,991,185 $ 10,202,977 $ 8,529,466 $ 6,508,639 $ 3,822,324
Total Improvements - Capital Projects Fund $ 12,720,653 $ 15,486,312 $ 29,589,746 $ 26,581,518 $ 17,193,139 $ 9,050,756
Bond Repayment - 2015 Police Station Bonds $ 818,043 $ 818,394 $ 818,144 $ 817,294 $ 814,056 $ 814,250
Bond Repayment - 2018 Capital Project Bonds 683,469 680,469 681,769 682,819 683,419 678,569
Bond Repayment - 2020 Capital Project Bonds 611,323 607,973 609,323 610,223 610,673 610,673
Bond Repayment - 2021B Refunding Bonds (2015) 127,165 126,588 126,010 125,222 124,435 123,648
Bond Repayment - 2025 ($9M) - 720,000 720,000 720,000 720,000 720,000
Total Expenditures - Capital Projects Fund $ 14,960,653 $ 18,439,736 $ 32,544,992 $ 29,537,076 $ 20,145,722 $ 11,997,896
CY2025 CY2026 CY2027 CY2028 CY2029 CY2030
FORECAST FORECAST FORECAST FORECAST FORECAST FORECAST
Change in Fund Balance, Capital Projects Fund $ (1,071,912) $ 6,760,809 $ (7,132,082) $ (1,303,815) $ (2,059,159) $ 2,258,077
Capital Projects Fund Balance, Beginning of Year $ 4,476,729 $ 3,404,817 $ 10,165,625 $ 3,033,544 $ 1,729,728 $ (329,431)
Capital Projects Fund Balance, End of Year $ 3,404,817 $ 10,165,625 $ 3,033,544 $ 1,729,728 $ (329,431) $ 1,928,646
PAGE 3/6
Page 27 of 51
VILLAGE OF GLEN ELLYN 2025-2030 CAPITAL IMPROVEMENT PLAN
WATER & SANITARY SEWER FUND
CY2025 CY2026 CY2027 CY2028 CY2029 CY2030
Water & Sanitary Sewer Fund FORECAST FORECAST FORECAST FORECAST FORECAST FORECAST
Revenues:
Capital Revenues - Water & Sewer Fund $ 2,907,000 $ 2,965,140 $ 3,024,443 $ 3,084,932 $ 3,146,630 $ 3,209,563
CDBG Grant/Potential SSA to fund Royal Glen $ - $ - $ -
Lombard Contribution To Hill Water Main $ 400,000 $ - $ -
Total Revenues $ 3,307,000 $ 2,965,140 $ 3,024,443 $ 3,084,932 $ 3,146,630 $ 3,209,563
Expenditures:
Water Roadway Related Projects:
North Park/Main Street Improvements - 49,437 - - - -
2022 Roadway Imp. Project 22002 19,127 - - - - -
2024 Utility and Roadway Improvements Project 23,893 - - - - -
2025 Utility and Roadway Improvements Project 1,016,155 - -
2025 Street Resurfacing Project 3,695 - -
2026 Utility and Roadway Related Improvements 1,300,000
Sheehan Avenue Improvements - - - 600,000 - -
Wingate Basin Water & Sewer Utility Improvements (TBD) - - - - - -
Future Street Projects - 1,515,658 1,591,441 1,671,013 1,754,563
Engineering for Future Street Projects 151,518 114,082 119,786 125,775 132,064 133,000
CBD Underground/Streetscape Improvements $ 72,063 $ - $ - $ - $ - $ -
Metra Station Improvements 63,898 - - 1,450,000 - -
Water Non-Roadway Related Projects:
Standalone Main Replacements $ - $ - $ - $ - $ - $ -
Roosevelt Road Water Main - - - - - -
Route 53 Water Main Lining 30,000 18,593 1,000,000 - - -
Hill Avenue Utility Sewer and Water (Water Main Component) - 2,250,000 - - - -
Glen Ellyn-Illinois American Water Interconnection 11,141 - - - - -
McKee House - - - - - -
Royal Glen Infrastructure Improvements - Hold - - - - - -
Water Operations Projects:
Wilson & Newton Pumping Station Rehabilitation $ - $ - $ - $ - $ - $ -
WPAS & NPAS Rehabilitation - - - - - -
Standby Well Rehabilitation - - - - - -
Reservoir Rehabilitation - - - -
SCADA - - - - -
Reno Center Improvements - - - - - -
Miscellaneous equipment - - - - -
Water Model 80,000 44,360 - - - -
Lead Service Line Replacement 476,504 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000
Lead Service Line Potholing - - - - - -
Subtotal - Water Projects $ 1,947,994 $ 4,776,472 $ 3,635,444 $ 4,767,216 $ 2,803,077 $ 2,887,563
PAGE 4/6
Page 28 of 51
VILLAGE OF GLEN ELLYN 2025-2030 CAPITAL IMPROVEMENT PLAN
WATER & SANITARY SEWER FUND
CY2025 CY2026 CY2027 CY2028 CY2029 CY2030
Water & Sanitary Sewer Fund FORECAST FORECAST FORECAST FORECAST FORECAST FORECAST
Sewer Projects:
Expenditures: CY2025 CY2026 CY2027 CY2028 CY2029 CY2030
Sewer Roadway Related Projects: FORECAST FORECAST FORECAST FORECAST FORECAST FORECAST
Point Repairs (Can Be Associated with Future Street Projects) - - 750,000 750,000 750,000 750,000
North Park/Main Street Improvements 13001 - 66,901 - - - -
2022 Street Program 22002 3,862 - - - - -
2024 Utility and Roadway Improvements Project 61,433 - - - - -
2025 Utility and Roadway Improvements Project 846,602 - - - - -
2025 Street Resurfacing Project 66,552 - - - - -
2026 Utility and Roadway Related Improvements 1,125,000
Sheehan Avenue Improvements - - - 410,140 - -
Wingate Basin Water & Sewer Utility Improvements (TBD) - - - - - -
Future Street Projects - - - - - -
Engineering for Future Street Projects 34,301 75,000 75,000 75,000 75,000 75,000
CBD Underground/Streetscape Improvements 15006 $ 120,573 $ - $ - $ - $ -
CBD Streetscape and Utility Improvements 15006 - Alley $ 103,492 - - - - -
Metra Station Improvements 59,905 - - 1,450,000 - -
Sewer Non-Roadway Related Projects:
I/I Reduction (Lining + Point Repairs) $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000 $ 200,000
Hill Avenue Utility Sewer and Water (Sewer Main Component) - 1,050,000 - - - -
Hill Avenue Lift Station - - - - - -
Memory Court Lift Station - - - - -
Surrey Lift Station - - - - -
South Park Lift Station - - - - -
Orchard Place Lift Station - - - - - -
Miscellaneous equipment - - - - - -
Royal Glen Infrastructure Improvements - Hold - - - - - -
Reno Center Improvements - - - - - -
Subtotal - Sewer Projects $ 1,496,720 $ 2,516,901 $ 1,025,000 $ 2,885,140 $ 1,025,000 $ 1,025,000
Total Improvements - Water & Sewer Fund $ 3,444,713 $ 7,293,373 $ 4,660,444 $ 7,652,356 $ 3,828,077 $ 3,912,563
CY2025 CY2026 CY2027 CY2028 CY2029 CY2030
FORECAST FORECAST FORECAST FORECAST FORECAST FORECAST
Change in Capital Balance, Water & Sewer Fund $ (137,713) $ (4,328,233) $ (1,636,001) $ (4,567,425) $ (681,446) $ (703,000)
Water & Sewer Capital Fund Balance, Beginning of Year $ 11,623,214 $ 11,485,501 $ 7,157,267 $ 5,521,266 $ 953,842 $ 272,395
Water & Sewer Capital Fund Balance, End of Year $ 11,485,501 $ 7,157,267 $ 5,521,266 $ 953,842 $ 272,395 $ (430,605)
PAGE 5/6
Page 29 of 51
VILLAGE OF GLEN ELLYN 2025-2030 CAPITAL IMPROVEMENT PLAN
Capital Projects Fund Grants
CY2025 CY2026 CY2027 CY2028 CY2029 CY2030
FORECAST FORECAST FORECAST FORECAST FORECAST FORECAST
GF1 North Park Boulevard/Main Street (STP Grant) $ - $ 329,615 $ - $ - $ - $ -
GF2 Roadway Improvements (DCEO Grant) 500,000 - - - - -
GF3 Taylor Avenue Underpass (STP Grant) - - - - - -
GF4 Metra Train Station (CMAQ Grant) - - 6,500,000 6,000,000 2,000,000 2,000,000
GF5 Metra Station (STP Local Grant) - - - - 1,400,000 -
GF15 Metra Station (STP Shared)
GF6 Metra Train Station (Community Funding Grant) - - 1,000,000 1,000,000 1,000,000 -
GF7 Metra Train Station (ICC Grant) - - 4,000,000 4,000,000 - -
GF16 Metra Station (Section 130 Grant)
GF8 Metra Train Station (Metra Grant) - - - 5,000,000 - -
GF9 Crescent Boulevard Lake to Village Limit (STP Grant) - - - - - -
GF10 Lambert Road Resurfacing (Future STP Grant) - 1,201,306 - - - -
GF11 Riford Road Resurfacing (Future STP Grant) - 338,788 - - - -
GF12 Park Boulevard Resurfacing (Future STP Grant) - - - - 976,976 -
GF13 Pennsylvania Avenue Resurfacing (Future STP Grant) - - - - 536,971 -
GF14 DCEO Grant - - 1,200,000 - - -
Total Grants $ 500,000 $ 1,869,709 $ 12,700,000 $ 16,000,000 $ 5,913,947 $ 2,000,000
PAGE 6/6
Page 30 of 51
Glen Ellyn Capital Meeting 9/10/2025 7:00 PM
Improvements Commission Department: Public Works - Internal Services
535 Duane Street Department Head: John Hubsky
Glen Ellyn, IL 60137 Category: Discussion Item
Prepared By: Richard Daubert
AGENDA ITEM (ID DOC ID: 2025-771
# 2025-771)
Metra Station Warming Shelter Followup
Statement of the Issue:
As discussed with the Capital Improvements Commission in June of 2025, staff is continuing to
explore opportunities to reduce the overall project costs with a more recent focus being on the
warming shelters. Attached are two alternatives to the original proposition which involved
constructing brick and mortar warming shelters on both the inbound and outbound sides of the UP-
West line.
Alternative 1 - This alternative eliminates the inbound shelter. The outbound shelter is constructed
as originally specified with a full cast-in-place footing and foundation, hollow structural steel framing
and roof trusses, brick-faced and cast stone-faced exterior walls with brick veneer interior walls,
tongue and groove roof decking with asphalt shingles, interior lighting, infrared heaters, ventilation
fans, and a fire alarm system with telemetry. The cost of this alternative is currently estimated at
$651,450. This is approximately $268,050 less than the prior estimated cost of two warming
shelters, as originally designed.
Alternative 2 - This alternative eliminates the inbound shelter. The outbound shelter is comprised
of a pre-manufactured shelter with improved aesthetics relative to the previously reviewed pre-
manufactured shelter. The size and amenities are comparable to Alternative 1. The cost of this
alternative is currently estimated at $348,300. This is approximately $571,200 less than the prior
estimated cost of two warming shelters, as originally designed.
A temporary trailer is anticipated to be required on the inbound side.
Analysis:
Based on discussions with CDM Smith,
Budget Impact:
Contribution to Strategic Plan
Action Requested:
Staff is soliciting feedback from the CIC on the two alternatives.
Page 31 of 51
Attachments:
1. Plan Exhibit of Revised Warming Shelters
2. Premanufactured Alternative 1
3. Warming Shelter Cost Analysis
Page 32 of 51
ALTERNATE #1 - Temp Inbound Station
remove
stair/ramp and
elevated
platform area
W1 W2 W3 W6 W5
1
422
SHELTER ROOF
HP
759' - 8"
15' - 7 5/8"
- ACCORDING TO 90% DESIGN
SHELTER FIN FL
744' - 0 1/2"
1 WARMING SHELTER EXTERIOR ELEVATION - SOUTH FACADE
421 3/8" = 1'-0"
Page 33 of 51
ALTERNATE #2 - Temp Inbound Station + Standard Outbound Shelter
remove
stair/ramp and
elevated
platform area
- PREMANUFACTURED
Page 34 of 51
8 7 6 5 4 3 2 1
GENERAL NOTES:
1. ALL STRUCTURAL STEEL, UNLESS OTHERWISE NOTED, SHALL BE ASTM A-36, MINIMUM
YIELD STRENGTH 36,000 PSI. 30'-2"
2. ALL STRUCTURAL ALUMINUM MEMBERS, UNLESS OTHERWISE NOTED, SHALL BE OF ALLOY
6063-T5 OR GREATER.
2'-0" OVERHANG TYP. ALL SIDES
3. ALL HOLES TO BE DRILLED OR PUNCHED.
4. STEEL WELDING SHALL CONFORM TO AMERICAN WELDING SOCIETY STANDARD D1. 1-10.
D ELECTRODES SHALL CONFORM TO AWS 5.1, CLASS E70S-5. D
5. ALUMINUM WELDING SHALL CONFORM TO AMERICAN WELDING SOCIETY STANDARD D1.
2-08. ELECTRODES SHALL CONFORM TO AWS/SFA 5.10 CLASS ER4043.
6. ALL WELDING TO BE DONE AT TOLAR MANUFACTURING COMPANY, INC. FACILITY. JUNCTION BOX,
7. ALL CORPORATE PROCEDURES, INCLUDING FABRICATION, MUST BE IN COMPLIANCE WITH ELECTRICAL COMPONENTS:
TOLAR MANUFACTURING CO. INC'S QUALITY CONTROL MANUAL BREAKER, DRIVER, TIMER, HEAT SENSOR
8. THE CONCRETE PAD SIZES SHOWN ARE STANDARD MINIMUM REQUIREMENTS FOR THE
STRUCTURE AND ARE FOR REFERENCE ONLY. THE PAD MAY NEED TO BE REINFORCED
OR ENLARGED DEPENDING ON LOCAL CODES AND LOADING CONDITIONS AND DOES NOT
INCLUDE ADA CLEAR PATH REQUIREMENTS.
TYPICAL BOW CONNECTION HARDWARE,
3/8-16 BOLT WITH LOCK WASHER, FLAT WASHER
AND HEXNUT
SECTION B-B
SCALE 1 1/2" = 1'-0"
TOP VIEW
SCALE 3/8"=1'-0"
ROOF PANELS,
1/8" ALUMINUM SHEET
C C
12'-4"
PRESSURE RIBS WITH DECORATIVE
RAISED BATTENS 2500W INFRATECH
HEATER (2)
B
REAR/ END WALL PANELS, B 10'-11 1/8"
TOP PORTION: 3/8" CLEAR TEMPERED GLASS
BOTTOM PORTION: FRAMED PERFORATED ALUMINUM
SHEET 8'-0" HEATER CLEARANCE HEIGHT
7'-0" MIN 4'-0"
PATTERN: A A OPEN
1/4 HOLES ON 3/8 STAGGERED
WALKWAY
2'- 5/8"
B A B
FRONT VIEW SIDE VIEW
SCALE 3/8"=1'-0" SCALE 3/8"=1'-0"
208VAC
27'-2 3/8" MIN. CONCRETE SLAB
26'-2 3/8" 6" MIN. FROM EDGE OF CONCRETE
TO EDGE OF SHOE FLANGE TYP.
25'-7 3/8" ALL DIRECTIONS
3'-2 7/16" 3'-2 7/16" 3'-2 7/16" 3'-2 7/16" 3'-2 7/16" 3'-2 7/16" 3'-2 7/16" 3'-2 7/16" 9"
n2" ELECTRICAL STUB-IN
1'-7 5/16" 1'-7 5/16" 3 1/4" MIN
PUSH BUTTON CONTROLLER "A"
6"
FOR HEATER (2)
"A"
DETAIL A
9'-4 5/8" MIN. CONCRETE SLAB 8'-4 5/8" 7'-9 5/8" 4'-7" 4'-0" OPEN WALKWAY 4'-0" OPEN WALKWAY 4'-7" SCALE 2" = 1'-0"
#4 REBAR @ 12" OCEW
A 1'-7 5/16" 1'-7 5/16" A
THE DESIGN AND DRAWINGS REMAIN THE
INTELLECTUAL PROPERTY OF TOLAR MFG. TOLAR MANUFACTURING COMPANY, INC
AND ARE PROTECTED BY LAW. THEY MAY 258 Mariah Circle, Corona CA. 92879
NOT BE ALTERED, REPRODUCED OR USED
FOR FABRICATION WITHOUT EXPRESSED DESCRIPTION
WRITTEN CONSENT FROM TOLAR MFG. 30'X12' CUSTOM NIA. HIGH PEAK SHELTER
ALL DOCUMENTS TO BE RETURNED TO CUSTOMER/VENDOR PAGE:
SECTION A-A TOLAR MFG.. AT COMPLETION OF WORK. CHICAGO, IL 1 OF 2
CONTRACTOR TO SITE VERIFY ALL DETAILS
SCALE 3/8"=1'-0" AND DIMENSIONS AND REPORT ANY AND SIZE MATL. VARIES DWG NO. REV
ALL DISCREPANCIES TO TOLAR MFG.. D 55601-00 -
BEFORE COMMENCING WITH THAT RELATED
SCALE DATE DRAWN BY:
PORTION OF THE WORK. AS NOTED 8/13/2025 RFarr
8 7 6 5 4 3 2 1
T:\Inventor\SHELTERS - CUSTOM\CHICAGO\55601-00.idw
Page 35 of 51
8 7 6 5 4 3 2 1
D D
C C
B B
A A
THE DESIGN AND DRAWINGS REMAIN THE
INTELLECTUAL PROPERTY OF TOLAR MFG. TOLAR MANUFACTURING COMPANY, INC
AND ARE PROTECTED BY LAW. THEY MAY 258 Mariah Circle, Corona CA. 92879
NOT BE ALTERED, REPRODUCED OR USED
FOR FABRICATION WITHOUT EXPRESSED DESCRIPTION
WRITTEN CONSENT FROM TOLAR MFG.
ALL DOCUMENTS TO BE RETURNED TO CUSTOMER/VENDOR PAGE:
TOLAR MFG.. AT COMPLETION OF WORK. CHICAGO, IL 2 OF 2
CONTRACTOR TO SITE VERIFY ALL DETAILS
AND DIMENSIONS AND REPORT ANY AND SIZE MATL. VARIES DWG NO. REV
ALL DISCREPANCIES TO TOLAR MFG.. D
BEFORE COMMENCING WITH THAT RELATED
SCALE DATE DRAWN BY:
PORTION OF THE WORK. AS NOTED 8/13/2025 RFarr
8 7 6 5 4 3 2 1
T:\Inventor\SHELTERS - CUSTOM\CHICAGO\55601-00.idw
Page 36 of 51
Warming Shelters Potential Cost Savings
DRAFT 09.05.2025
Item 90% Design Alternate #1 Alternate #2
Inbound (North) Warming Shelter $335,000
Outbound (South) Warming Shelter $335,000 $335,000
Inbound Ramp to Platform $115,000
Temporary Inbound Station Trailer $170,000 $170,000
Premanufactured Shelter $100,000
Subtotal $785,000 $505,000 $270,000
markups $227,650 $146,450 $78,300
Total $1,012,650 $651,450 $348,300
Potential Cost Savings $0 $361,200 $664,350
notes:
Construction cost subtotals from the 90% estimate were used for warming shelters and ramps, excluding portions of electrical and structural work still required.
Temp trailer costs are a Rough Order of Magnitude from Vistara cost estimating. Temp trailer to include stairs/ramps and TVMs.
Premanufactured shelter costs obtained from Tolar manufacturer, based on design as shown in '55601-00'
Markups include general conditions (6%), bond and insurance (3%), phasing (10%), profit (8%), and contingency (2%) according to the 90% cost estimate.
Page 37 of 51
Glen Ellyn Capital Meeting 9/10/2025 7:00 PM
Improvements Commission Department: Public Works - Internal Services
535 Duane Street Department Head: John Hubsky
Glen Ellyn, IL 60137 Category: Report
Prepared By: Richard Daubert
AGENDA ITEM (ID # 2025- DOC ID: 2025-765
765)
Engineering Division Project Activity Report September 5, 2025
Statement of the Issue:
The September 5, 2025 Engineering Division Project Activity Report is attached for review by the
Capital Improvements Commission.
Analysis:
Budget Impact:
Contribution to Strategic Plan
Action Requested:
Attachments:
1. Engineering Project Report 9-5-25
Page 38 of 51
Septmber 5, 2025
ENGINEERING DIVISION PROJECT ACTIVITY REPORT
CONSTRUCTION PROJECTS IN PROGRESS
CRESCENT-GLENWOOD PARKING LOT AND MEDIAN REHABILITATION –
Contractor: Abbey Construction (Value of Construction Contract = $1,208,252.93)
This project involves the resurfacing and modest reconfiguration of the parking lot along with
reconstruction of the north side median with addition of new trees and other plantings, and the
addition of new parking lot lighting. At their July 28th meeting, the Village Board approved
awarding of the construction contract to the low bidder, Abbey Construction. At the same meeting
the Board approved a construction engineering contract with BLA, Inc..
Construction on the project started on August 20 with the removal of the remaining trees and some
other woody vegetation. Since that time the temporary wood light poles and luminaires were
installed and activated, existing light poles were removed and luminaires delivered to Sternberg
for refurbishment, and sawcutting was completed for upcoming median work. Demolition of the
existing sidewalk and median is anticipated to commence the week of September 8th. The contract
completion date is November 7, 2025.
Augering for Temporary Wood Light Pole at the Crescent-Glenwood Lot
Page 1 of 13
Page 39 of 51
2025 MFT/Rebuild Illinois Street Resurfacing Project – Contractor: A Lamp Concrete
Contractors
(Project No. 25001; Value of Construction Contract = $3,052,075.77)
This project involves utility and roadway
improvements along approximately 2.4
centerline miles of streets shown in the
location map to the right. The project was
awarded to A Lamp Concrete Contractors at
the February 24 Village Board Meeting.
Substantial completion is required by August
29th
The contractor has divided the project area
into three phases, with the Anthony-Cottage-
Newton plus Evergreen area being phase 1,
the Hillside-Montclair-Annandale area
streets being phase 2, and the Arlington-
Regent area being phase 3.
Asphalt surface was paved on Evergreen
Avenue the week of June 9th and sodded in
early July. All items except sod have been
completed in the Phase 1 area, which is
anticipated to be completed in September.
Asphalt surface paving work was completed
in the Phase 2 & 3 areas the week of August
18th, prior to school activities. Sodding in the
Phase 2 & 3 areas is expected to be completed
with the remainder of Phase 1 by the end of
September.
2025 UTILITY AND ROADWAY IMPROVEMENTS PROJECT DESIGN – Contractor: John
Neri Construction Company
(Project No. 25002; Value of Construction Contract = $4,568,404.95)
Over the last month, the contractor substantially completed all utility, concrete curb and flatwork,
parkway restoration, and street paving work within the Grandview/May/Revere/Lowell/Valley
area of the project.
The underground sanitary, water, storm, and gas utility replacement work was substantially
completed on Traver Avenue this week. The contractor will now begin putting the street back
together. Work will begin with sidewalk removal and replacement the week of September 8th, and
then proceed into roadway excavation and grading, concrete curb and apron replacements, and
finally asphalt paving. The resurfacing of Melrose Avenue is anticipated to be completed
concurrently with concrete and asphalt work on Traver. Traver and Melrose are anticipated to be
Page 2 of 13
Page 40 of 51
substantially completed by Mid-October. Punch list work will likely extend through the balance
of October but the goal is to have the project wrapped up well before the end of the construction
season.
Asphalt Surface Paving on May Avenue 9/4/2025
CBD STREETSCAPE AND UTILITY IMPROVEMENTS – Phase 1 – Contractor: A Lamp
Concrete Contractors
(Project No. 15006; Value of Construction Contract = $5,704,293)
Minor remaining items in the Phase 1 area include: completion of a remaining electrical item at
504 Hillside (in coordination with ComEd and Nicor), and replacement of concrete around the
trench drain behind Fire & Wine. These items are targeted to be completed this year as part of
final closeout of the Phase 1 project.
The other big item in the Phase 1 area is the sanitary sewer replacement, storm sewer work, and
pavement reconstruction in the Main Street alley (west of Main, south of Duane). As per previous
communication, this alley work was not part of the original Phase 1 construction contract, but was
an add-on item in response to the inability to line the alley sanitary sewer as part of the Phase 1
work. Plans were finalized and the project was advertised for bid on July 18, 2025, wth the bid
opening conducted on July 7th.
There was wide range amongst the four as-read bids received. Based upon contractor feedback,
this was attributed to contractor concerns over the challenging construction conditions for the
project, with the constrained zero-setback alley with utility poles as an additional complicating
factor. That said, the low bid received from R.W. Dunteman Company ($269,403.93) was within
the margins of the engineer’s estimate of cost. A construction contract with R.W. Dunteman is
being presented to the Village Board for review at their September 8th meeting.
Page 3 of 13
Page 41 of 51
CBD STREETSCAPE AND UTILITY IMPROVEMENTS – Phase 2-3 – Contractor: A Lamp
Concrete Contractors
(Project No. 15006; Value of Construction Contract = $16,298,499
Staff is continuing work with the contractor to complete the remaining punchlist items for full
project closure this year. Updates on the remaining larger items are below.
• Concrete sidewalk/driveways – As mentioned previously, there are some areas where the
concrete surface has signs scaling and/or spalling. These are concentrated along the north
side of Pennsylvania Ave (Main to Prospect) and the west side of Main Street (Anthony to
Crescent). After further research and multiple field walks, we have reached agreement with
the contractor on areas of concrete sidewalk for replacement.
A key consideration was identifying sidewalk squares with surface deterioration that may
be progressive versus a more aesthetic surface condition not likely to be progressive and
where the solution (disturbance associated with full concrete replacement) may not be
warranted by the superficial condition. In the end, the primary areas targeted for full
sidewalk replacement are concentrated at driveways where the loading and future salt
exposure are greater. The concrete replacement work is targeted for September, with an
eye toward avoiding impact to any of the major downtown events.
• Brick pavers – As mentioned previously, there are select bricks throughout the project
area that are showing signs of deterioration. While most of the bricks are fine, some are
visibly deteriorating. After further investigation and multiple field walks with the paver
brick supplier and contractor, we have now identified select furniture zone bricks for
replacement. Due to the mixing of brick batches, the bricks for replacement are scattered
throughout the various furniture zone fields rather than being concentrated in one area like
the concrete. In some fields there are just a few bricks slated for replacement whereas in a
few concentrated areas (east side of Fire Station) most of the soldier course bricks are
proposed for replacement. The brick paver replacement is planned to occur after the
concrete sidewalk work, since some sidewalk work may impact brick pavers, and there is
a desire to do the brick paver punchlist work just once
• Plants – The Phase 2-3 plantings punchlist has been finalized. Due to the significant loss
of plants, staff are coordinating with a representative of the Environmental Commission on
and the project design consultant on an alternate selection of plant species that while not
native, can still meet many of the goals of native plants (e.g. sustainable, pollinator-
friendly) but may be better suited to the small planter streetscape setting, rather than
replacing the plants that did not survive in kind.
• A final re-planting plan was submitted to the contractor for them to coordinate with their
landscaping subcontractor. Staff are now working with the contractor on the plantings
dates, anticipated to be in September. Note that the plants punchlist includes the
replacement of 8 trees that are not expected to survive. Six of the trees are London
Planetrees which for whatever reason have not fared well in the downtown. Another tree
is a Swamp White Oak that is struggling. And the final is a Marmo Maple that was struck
by a vehicle last year and therefore needs replacement. With the exception of the maple,
Forestry has identified alternate species for the replacement trees to better ensure future
survival.
Page 4 of 13
Page 42 of 51
2024 UTILITY AND ROADWAY IMPROVEMENTS – Contractor: John Neri Construction
(Value of Construction Contract = $13,148,961)
Construction was largely completed last November. A handful of remaining work items including
isolated sod placement, landscaping installation, and culvert epoxy injection at Glen Crest creek
were completed this spring. The project team is currently reviewing the punchlist in order to
proceed to project closeout. As part of the punchlist, portions of Forest Avenue and High Avenue
were re-paved at the Contractor’s expense to address some deficiencies the week of August 11th.
OTHER AGENCY PROJECTS
Butterfield Road Reconstruction (IDOT)
The State continues to advance its project to reconstruct Butterfield Road from 700 feet west of
Arboretum Drive to I-355. The project involves complete reconstruction of IL-56 with the end
deliverable being 3 through travel lanes in each direction from Route 53 to IL-355. The
intersection of IL-56 and IL-53 will also be improved with all approaches to the intersection to
have dual left- turn lanes and exclusive right-turn lanes. The intersection improvements will
extend north and south along IL-53 with the State continuing to work through the design process
for future reconstruction of IL-53 down to Park Boulevard.
The project will also include the construction of a 10-foot-wide shared use bicycle path on the
north side of IL-56 between Arboretum Drive and Lloyd Avenue. As part of the shared use path
construction, a new pedestrian bridge will be constructed over the East Branch of the DuPage
River. New sidewalks will also be constructed along the west side of IL-53 from the southern
Walmart entrance to Pinegrove Court and along the south side of IL-56 from the Abbington to
IL-53.
The Contractor has been working on widening the north side of Butterfield Road with temporary
pavement which will allow staging of future traffic to the outside lanes of Butterfield Road.
Utility relocations continue to be a controlling item in advancing the roadway reconstruction
work. However, the construction team is hopeful that work will be able to be started on the
bridge over the East Branch in the coming months.
Roosevelt Road Bridge Repair (Over IL-53/West of Baker Hill Drive (IDOT)
This IDOT project involves reconstructing the joints at each end of the bridge, partial and full
depth bridge deck and abutment repairs, overlaying the bridge with a latex modified concrete,
asphalt overlay of ~40’ of the concrete pavement approaching the bridge, sidewalk replacement,
railing/fencing replacement, guardrail replacement, and other various items of work.
Per the original project schedule, there was generally anticipated to be approximately two weeks
work on the south side of the bridge (Stage 1), then two weeks in the middle (Stage 2), and two
weeks on the north side of the bridge (Stage 3), with traffic diverted around the work zone in
each stage. With project completion in mid to late July.
Page 5 of 13
Page 43 of 51
However, during Stage 1 removals, an issue was identified with the bridge joint that required
evaluation and re-design through various divisions of IDOT. As a result, the project was stuck in
Stage 1 (south side work zone). A resolution was finally approved through IDOT at the end of
July, which allowed the project to again move forward. The project moved into Stage 2 (middle
lanes workzone) on August 28th. The new anticipated project completion date offered by IDOT
is the first week in November.
Route 53 Resurfacing from Bemis Road to ~ 400’ south of Pershing Avenue (IDOT)
This IDOT project consists of pavement patching, milling of the asphalt surface, placing new
binder and surface course, replacing aggregate shoulders with asphalt shoulders, drainage
structures adjustment and cleaning, placement of pavement markings, sidewalk ADA
improvements, detector loops replacement, and incidental and collateral work necessary to
complete the improvement.
IDOT let the project on June 13, 2025 with award of the project to R.W. Dunteman Company. A
pre-construction meeting was conducted on August 19th. IDOT anticipates the project will begin
In mid to late September, with estimated completion in November.
Route 53/Spring Avenue Traffic Signal Installation and APS Pushbuttons at IL-38/Nicoll
(IDOT)
IDOT was working through the design of a project involving the replacement of the temporary
cable hung (trombone) traffic signal equipment at Route 53 and Spring Avenue, along with the
replacement of the the pedestrian pushbuttons at IL-38 and Nicoll Way/Ave with Accessible
Pedestrian Signal (APS) pushbuttons. However, the two elements of the project were split into
two separate projects.
The Route 53/Spring Avenue project is still in design. The project proposes to install all new
permanent traffic signal equipment including a new controller cabinet and electrical service, post
and mast arm mounted signal heads, accessible pedestrian signals, and sidewalk ADA
improvements. The State is reviewing Village staff’s request that the project be communicated
to residents within a logical vicinity of the intersection of 53/Spring. Staff provided sample
notification letters to IDOT along with a phone conversation as to outline communication
expectations.
Meanwhile, the IL-38/Nicoll Way/Ave APS project was folded into another traffic signal
modernization contract with four other intersections around the region and is scheduled for a
September 19th bid opening. APS pushbuttons provide non-visual walk and don’t walk
indications (audible and vibrotactile) for visually impaired individuals. Staff will follow up with
the State after the bid opening to confirm if the project is awarded and get an update on the
anticipated timing for the work.
Page 6 of 13
Page 44 of 51
ENGINEERING PROJECTS
LAMBERT AND RIFORD FEDERAL AID PROJECTS – Engineer: AECOM
These projects involve the potential use of federal funding through the Local Surface
Transportation Program. They are on contingency lists for funding in the amounts of $1,201,306
for Lambert and $338,788 for Riford. The Lambert Road project involves the resurfacing of
Lambert Road from Roosevelt Road to the southern Village Limit which is just south of the
College of DuPage. The Riford Road project involves the resurfacing of Riford Road between
Crescent and Saint Charles Road.
The Prefinal plans, specifications, and cost estimate were submitted to the State in advance of a
July 28th deadline to stay on track for the November State letting. A request for proposals was
also issued to consultants for construction engineering services for the two projects. Seven
proposals for Lambert and five proposals for Riford were received and evaluated by staff according
to the Village’s Qualification Based Selection procedures. Staff held interviews with the top
ranked firms for each project and re-ranked them after interviews were complete. Staff has since
completed negotiations with the top ranked firm (for both projects). The engineering agreements
are being prepared with staff to work with the State to prepare the final Engineering and
Construction agreements/resolutions for consideration of Village Board Approval as soon as
September 22.
HILL AVENUE UTILITY IMPROVEMENTS – Engineer: Walter E. Deuchler Associates
(Project No. 00511)
This project involves the construction of sanitary sewer and water distribution system
improvements on Hill Avenue between Golf Avenue and the East Branch of the DuPage River.
The improvements will ultimately result in the Village’s water main being continuous and looped
along both Hill Avenue and Crescent Boulevard. Also, this will allow the Village to serve the
fronting properties on Hill Avenue with potable water service.
Easement documentation was prepared for the Elliot Construction property with the documents
signed by the respective party. A similar easement is needed on the north side of Hill Avenue;
staff has met with the property owner to review draft easement documents. Most recently, staff
evaluated an alternative corridor that the property owner requested and a follow up meeting was
held with the property owner and his attorney to discuss the complications of an alternative
alignment for the utilities. Having said that, staff was able to identify and opportunity to reduce
the footprint of the easement which was of interest to the property owner. Next step is to revise
the design plans to align with the revised easement. Other various comments will also need to be
addressed by the Engineer. This will allow the project design to ultimately be finalized, easements
secured, permits amended or refreshed, and project to be competitively bid.
Page 7 of 13
Page 45 of 51
TRAIN STATION / PEDESTRIAN TUNNEL – Engineer: CDM Smith/KMI Architects
(Project No. 16016)
The Phase 1 Engineering Project Development Report (PDR) is being amended to update the
project environmental clearances, incorporate the Section 106/4(f) approvals, incorporate the most
recent crash data, etc. Staff anticipates receipt of the amended PDR from the consultant by mid-
September with the goal to review and submit the PDR to IDOT by the end of September. The
design exceptions largely associated with the design exceptions on Crescent Boulevard were
informally approved but the State has requested some changes to the design exception forms. Staff
will amend them accordingly and resubmit to the State this month.
The Phase 2 Engineering 90% plans are still under review by staff, Metra, and Union Pacific with
the goal for reviews to be completed by late September. Staff is also pushing for IDOT to start its
reviews of the Phase 2 Engineering Plans although the State tends to want to wait until Phase 1
Engineering is fully approved.
Land Acquisition procedures are now underway with staff having recently secured IDOT’s Bureau
of Land Acquisition approval of the members of the land acquisition team. A meeting is being
held with the Bureau of Land Acquisition on September 5 to discuss the development of the plats
and legals for the Land Acquisition Process.
Regarding other various items, staff is awaiting submittals of the design of interpretive signage to
document/commemorate the existing depot. In terms of grant pursuits, while the project did not
secure the most recently requested ~$10M in CMAQ/STP Shared Funding, CMAP did recently
confirm the project is eligible to be on the STP Shared Fund Contingency Program. Staff
submitted the required forms to secure the project on the contingency program.
TRAFFIC SIGNAL MODERNIZATION PROJECT – Engineer: AECOM
(Project No. 23006)
Work is underway on design of the improvements to the six Village-owned traffic signals,
consistent with the 2024 Recommendations Report created by AECOM. While work on the six
Village-owned traffic signals is to be spread over three years (2026-2028), initial design on all six
signals is being conducted this year. The intent is to be ready to package the first bid package in
late 2025, for 2026 construction. The target intersections for each construction year are still under
discussion and will be part of budget discussions.
The AECOM contract also provides for optimization of the Village intersections in 2025. Traffic
counts, using video detection technology, were conducted the week of May 12th, before schools
let out for the year. AECOM is now using these counts to model the intersection operations and
determine optimal timings for each location.
On Thursday, July 24th, the traffic signal cabinet at the Lambert/Fawell intersection sustained
damage from a lightning strike. As a result, the signals are currently operating in a pretimed pattern
that is less efficient than the former actuated, traffic responsive mode. The intersections of
Lambert/Tallgrass and Lambert/College, while not damaged by the lighting, are part of an
interconnect with Lambert/Fawell and are therefore also affected to a degree.
Page 8 of 13
Page 46 of 51
The surge damaged much of the equipment in the cabinet. Temporary equipment is currently in
place allowing for basic signal operation. However, given the age of the cabinet and equipment,
replacements for some of the equipment are not readily available and new equipment is not
compatible with some of the older systems.
Village staff is continuing to work with AECOM and Meade Electric on the potential acceleration
of the planned replacement/upgrades at the Village intersections along this corridor. The
remaining signalized intersection improvements that are part of the overall modernization
recommendations would still be part of future year improvements, only the cabinet upgrades would
be accelerated at this time, and out of more immediate necessity.
ADA PUBLIC RIGHT-OF-WAY TRANSITION PLAN – CMAP TECHNICAL ASSISTANCE
– Project Partner: Chicago Metropolitan Agency for Planning (CMAP)
In March of 2024, Public Works applied to CMAP for assistance with creation of its federally-
required ADA Transition Plan, as part of CMAP’s 2024 Technical Assistance Call for Projects.
Out of a competitive process (122 applications submitted, 30 awarded), the Village was selected
to receive assistance.
Since the last update, Village staff met with the consultant and were given a preview of the lidar
survey data of the sidewalks in the Village. The data dashboard allows for weighting of curb ramp,
cross-slope, running slope, and vertical displacement deficiencies in order to develop priority areas
for sidewalk improvements. The consultant is working to clean up some of the data and make the
data dashboard directly available to Village staff for further review.
As the next stage of public outreach, there was discussion of CMAP and the project consultant
setting up a table at the October 4th Fire Open House, to publicize the planning effort and solicit
additional feedback from residents. The next Steering Committee meeting is not yet set, but will
include wider review of the Lidar sidewalk survey data, as well as revisiting of the prioritization
discussion started at the last Steering Committee meeting.
The overall planning process will likely extend beyond October, but is still proposed to be
completed this year.
WATER DISTRIBUTION SYSTEM STUDY – Engineer: Christopher B. Burke Engineering
Limited (CBBEL)
This project involves the development of a model of the Village’s water distribution system which
will be used to optimize operation of the system as well as identify and confirm needed capital
improvements. The model and a technical report will be the ultimate deliverables of the
assignment. Through a competitive RFP Process, staff identified CBBEL as the best firm for the
completion of the assignment. The Village Board approved an agreement with CBBEL on January
27th. The project is expected to be completed in 2025.
The consultant has completed the initial modeling of the Village’s pipe network and water
facilities. Hydrant flow testing, conducted at eleven locations the week of May 5th, was used to
help calibrate the model. Public Works staff met with CBBEL on July 1st to review preliminary
Page 9 of 13
Page 47 of 51
results. There was significant discussion around the areas of four-inch watermain in the Village
that result in reduced fire-flow volumes, and are a likely first priority for replacement. The
consultant will be working on a matrix to help weight the various factors involved with prioritizing
watermain needs in the face of constrained budgets. These factors are to take into account historic
watermain breaks, concentrations of lead services, interaction with the Village’s pavement
management program, etc.
CONSTRUCTION MAINTENANCE PROGRAMS
Public Works seeks the best vendor prices for various annual municipal and utility maintenance
and operations activities. This effort includes local bidding of projects or joint purchasing
initiatives, including the Municipal Partnering Initiative (MPI), a consortium of DuPage County
communities.
2025
Project Estimated Status
VGE Cost*
The project scope includes roadway patching throughout the Village.
Locations will be determined by staff utilizing both the Village’s 2024
2025 Asphalt Pavement Management System Data and field inspections. This program had
$188,630
Roadway Patching a February 26th bid opening and R.W. Dunteman provided the low bid of
$188,630. R.W. Dunteman was awarded the contract at the March 10th Board
Meeting for the full bid amount. Work will be completed this month.
The 2025 Crack Sealing program targets candidate locations using Pavement
Condition Index (PCI) Study data and visual inspections. The 2025 budget
for the program is $45,000. Bids were opened on February 12th with Denler,
Inc. providing the low, responsible, and responsive bid of $33,700. Denler,
Inc. was awarded the contract at the March 10th Board meeting in the not-to-
2025 Crack Sealing $40,000
exceed amount of $40,000, which resulted in $5,000 in savings in the Capital
Projects Fund. The contract specifies that crack sealing takes place between
August 1st-October 15th, which is the ideal time for this maintenance. Staff
had a pre-con meeting with Denler in late August and was told that Denler is
ready to start work shortly.
This annual program includes repairs to deteriorated or damaged sidewalk
and concrete roadway infrastructure and the installation of new sidewalk
throughout the Village. The low bidder, Schroeder and Schroeder (S&S),
was awarded the contract at the March 10th Board Meeting in the not-to-
exceed amount of $398,620. Staff has been coordinating with the DuPage
County DOT for months to get a permit approved to remove the brick
2025 Sidewalk and crosswalk removal at Main St. and St. Charles. DPC finally approved the
$400,000
Concrete Street Maintenance of Traffic plan; however, they requested a few additional notes
Repairs be added to the plan sheet regarding temporary signal timing. S&S will close
Main St. between St. Charles and Elm St. to remove both brick crosswalks.
They will excavate the pavement starting at 6 p.m. on a Friday evening using
a high-early concrete mix as base course and place hot-mix asphalt on top the
next morning. This will allow them to open Main Street to traffic by noon on
Saturday. This work and the rest of the sidewalk and concrete street R&R
will take place in mid-September.
Staff proposed using Safe Step to evaluate sidewalks for trip hazards in three
Sidewalk Sawing areas (the Derby Glen neighborhood, the Surrey/Briar neighborhood, and
$35,842 Revere Rd between Main and Park Blvd.) based on the defect identification
Repair Program
criteria that Safe Step and the Village developed together. Safe Step’s
patented process uses waterless saws, which eliminates slurry and water
Page 10 of 13
Page 48 of 51
2025
Project Estimated Status
VGE Cost*
runoff contamination, and a dust-abatement system designed to capture fine
dust. Safe Step makes sawcut repairs tapered to a 1:12 slope ratio with a
smooth, uniform finish and are ADA-compliant. Safe Step was awarded a
contract at the April 14th Board Meeting. In May, Safe Step surveyed three
areas and provided a report with locations, descriptions, suggested repair
types, and photos of each identified defect. The Village reviewed the data
and gave the go-ahead to Safe Step to make 393 sawcut repairs. Several
locations with more severe defects were recorded by Safe Step and added to
the Village’s sidewalk removal and replacement list. The sidewalk
sawcutting work was completed in mid-July. The Village received positive
feedback via email from a resident in the Surrey neighborhood who
complimented the construction workers on their professionalism and
neatness and thanked the Village for making repairs in the area.
Page 11 of 13
Page 49 of 51
2025
Project Estimated Status
VGE Cost*
This program allows Public Works to use one contractor to restore Village
right-of-way following in-house utility repairs instead of relying on the
availability and coordination of the Village’s separate concrete and asphalt
contractors. The program requires the contractor to make up to three
mobilizations throughout the construction season. The contractor must be
capable of doing full-depth concrete and asphalt pavement patches, and
concrete sidewalk, driveway, and curb and gutter repairs. Bids were opened
on February 26, 2025, with the low bid being provided by G.A. Paving, of
2025 Utility Bellwood, IL, in the amount of $58,340, which was just under the 2025
Pavement $74,557.33 budget of $60,000. G.A. Paving was awarded the contract at the March 10th
Restoration Board Meeting. As of June 20th, approximately $74,000 worth of right-of-
way restorations were needed so the Village Manager approved a change
order increasing the amount of the contract by $16,500. The increased
number of water main breaks last winter, which was experienced by
municipalities across the Chicagoland area, and numerous 50/50 sewer cost
share projects and lead service investigations accounted for the need for
more right-of-way restorations than were originally estimated. Last year,
G.A. Paving completed eight restorations for the Village. In 2025, G.A.
Paving made twenty-seven utility restorations by mid-July.
For the last fifteen years, the Village has utilized local purchasing cooperatives to
obtain competitive pricing for pavement marking work. In 2024, the Village joined
the Suburban Purchasing Cooperative’s contract and entered an agreement with the
low bidder, Superior Road Striping (SRS), to refresh pavement markings in Glen
Ellyn. SRS was overwhelmed with work demands around the region and was
unable to complete their work in Glen Ellyn before temperatures dropped too low
to meet the specifications for pavement marking installation. SRS will hold their
unit prices and complete the balance of the 2024 work this spring. After last year’s
experience with scheduling delays, staff decided to bid out this project locally in
order to have more control over project completion dates and to be higher on the
contractor’s priority list.
2025 Pavement The bid opening was held on February 26th; Precision Pavement Marking was
$84,676
Markings the lowest bidder out of four with a bid proposal of $101,908, which was
slightly over the $100,000 budget. Precision Pavement Marking agreed to
reduced quantities to allow the Village to stay under budget; however, the total
price still came at a significant premium compared to historic cooperative
pricing. DuPage County (DPC) awarded a contract to Precision on April 8th.
Suburban Purchasing Cooperative (SPC) negotiated 2025 prices as part of a
2024 contract extension with Superior Road Striping and these unit prices
provided the most value to the Village. On April 28 th, the Board formally
rejected all of the bids from the February 26th bid opening and awarded a
contract to Superior Road Striping based on the Village’s membership in the
SPC. SRS began working on the 2025 contract on June 30 th. SRS is expected
to be done with the contract work by September 30 th.
Page 12 of 13
Page 50 of 51
2025
Project Estimated Status
VGE Cost*
Superior Road Striping refreshing the double yellow lines on Pershing Ave. between
IL-53 and Roosevelt Rd.
The annual line striping contract was awarded to Superior Road Striping
(SRS), the low bidder of both the DuPage County and Suburban Purchasing
Cooperative contracts, on April 22, 2024, in the not-to-exceed amount of
$100,000. SRS began pavement marking in October 2024, but could not
complete the Village’s worklist due to weather delays and SRS’workload.
They finished installing modified urethane pavement markings in early June
2024 Pavement and completed the 2024 thermoplastic work on June 30th.
$81,842*
Markings
The Streets Division refreshed pavement markings using paint in various
locations, including the handicap symbols in all of the Village-owned parking
lots. The Streets Division’s 2024 budget for paint materials was $5,000.
*The Village paid Superior Road Striping $17,912.39 for work completed in
2024; the P.O. was carried over and Superior was paid an additional
$63,929.16 for work completed in 2025.
Candidate locations include streets that have been resurfaced one to three
years prior. On August 25th, 2025, the Board awarded a contract to single
2025 Asphalt
source vendor Corrective Asphalt Materials(CAM), who extended MPI joint
Surface $90,000
bid unit prices to the Village. The Village is awaiting final paperwork from
Rejuvenation
CAM so the P.O. can be processed. Work is expected to take place in mid-
September.
The 2025 program will provide for sanitary sewer lining and repairs
2025 Sanitary Sewer
$200,000 throughout the Village including within the Street Improvements Project
Lining and Repairs
Areas. The proposed budget for this program is $200,000.
*All costs are rounded to nearest dollar.
X:\Public Works\ENGINEER\Monthly Construction Reports\Engineering Project Report 9-5-25.docx
Page 13 of 13
Page 51 of 51