Board of Building Appeals
Regular MeetingLombard, IL · March 21, 2013
Minutes
Village Hall
Village of Lombard 255 East Wilson Ave.
Lombard, IL 60148
villageoflombard.org
Minutes
Board of Building Appeals
Members Bob Mueller, Marty Igoe, Steve Flint,
John Cullen and Maurice Bernardi
Staff Liaisons:
Director of Community Development William Heniff and
Building Official Keith Steiskal
Thursday, March 21, 2013 6:30 PM Village Hall/L22
Call to Order and Pledge of Allegiance
The meeting was called to order by Keith Steiskal, Building Official, at
6:32 p.m.
Mr. Steiskal led the Pledge of Allegiance.
Roll Call
Present 4 - Stephen Flint, Marty Igoe, John Cullen, and Bob Mueller
Also present: Chuck Riforgiate, Fire Marshal and Janet Downer,
Administrative Coordinator.
Public Hearings
None.
Business Meeting
Approval of Minutes
A motion was made by Stephen Flint, seconded by Bob Mueller, to approve
the minutes of the February 29, 2012 meeting. The motion passed by a
unanimous vote.
Prior to discussing the amendments to the Building Code, Mr. Steiskal
Village of Lombard Page 1
Board of Building Appeals Minutes March 21, 2013
updated the members of the changes that have occurred since the
last time the Board of Building Appeals met:
· Staff Changes - Len Farina, the Electrical Inspector, has retired
and come back in a part-time capacity. The Village is looking to
hire another part-time position and with the two part-time
positions, the hours will be equal to one full-time position. The
Village still employs a full-time building inspector, a plumbing
inspector and himself. With the new part-time electrical
inspector and Len coming back part-time, we will have a total of
five inspectors.
Changes to Code include the following:
· The furnace law that was to start May 1, requiring furnaces to
be 90% efficient instead of 80%, was never instituted but may
resurface at a later date.
Bob Mueller asked why. Mr. Steiskal replied there was concern that
people couldn’t afford to purchase them and as a result, they might be
apt to do work without permits or possibly use space heaters instead
of buying a new furnace which would be more dangerous. They are
considering a grant program for those who cannot afford it, but that is
being worked out. 2015 is the new target date.
Marty Igoe asked if this was State or Federal Code. Mr. Steiskal
answered Federal.
· On January 1, 2013 the Village started using the 2012 Energy
Code. The last time this Board met, the Village was using the
2009 Energy Code.
· Inspections now needed which previously were visual:
o Blower door test inspection - This test helps determine a
house’s air tightness. The thought is that if your house if
is sealed tight, there are less air leaks which results in
energy efficiency.
o Energy efficient window inspection
o High efficiency light inspection
Bob Mueller asked what the failure point is for the blower door test.
Mr. Steiskal answered that the results are measured off of air leakage.
He explained how the test is performed. A fan is mounted into the
frame of an exterior door. This fan then pulls air out of the house
lowering the air pressure inside. The higher outside air pressure flows
in through all unsealed cracks. There are seven air exchanges that
measure the amount of air pulled out of the house by the fan. The
Village of Lombard Page 2
Board of Building Appeals Minutes March 21, 2013
data that is collected quantifies the amount of air leakage. If you do
not pass the first time, corrective measures like caulking are
performed to address the inefficiencies. The test can be performed
multiple times until you hit an appropriate number.
Bob Mueller commented that foam insulation in the roof would work
well in houses to seal air leaks. Mr. Steiskal replied that you could do
that also.
Bob Mueller asked if the conduit is sealed when a blower door test is
performed. Mr. Steiskal answered that all conduit that goes to any
exterior electrical box needs to have duct seal around it. In
commercial uses, they are using putty pads around the electrical
boxes but he has also seen the application being used on ceilings in
residential uses.
John Cullen asked how fresh air would enter a house. Bob Mueller
answered from the outside of the house via the air return. Mr.
Steiskal added that having your furnace on a cycle keeps from getting
abnormal air exchange.
John Cullen mentioned possible problems with mold. With the 90%
energy efficient furnace, you need a thermostat that cycles the fresh
air intake through the furnace. Mr. Steiskal indicated that you can also
have a continuous fan running throughout your house.
Mr. Steiskal stated that overall the house performs better but there are
concerns about sealing up a house too tight.
· New Radon Law
Mr. Steiskal stated radon can be a concern. Lombard is located in
Zone 2 and Kane County is considered Zone 1 which is the most
dangerous. Radon is the second leading cause of lung cancer. When
a house is sealed up tighter, radon can be more of a problem.
The State passed a new radon law which requires all new houses built
after June 1, 2013 to have a passive radon pipe installed. The pipe is
run through the heated part of the house. It is enough to depressurize
the soil to pull the radon out of the house rather than having it vent
into the house. This requirement is not costly, maybe a few hundred
dollars, but can save money in the long run if you need to install a
radon mitigation system as the pipe would already be in place.
Lastly, Mr. Steiskal mentioned that he is a member of the Suburban
Building Officials Conference (SBOC) and is President for this term.
He went to an International Code Council (ICC) meeting, and one
Village of Lombard Page 3
Board of Building Appeals Minutes March 21, 2013
looming issue being discussed is that the State Fire Marshal wants to
adopt the newest version of the Life Safety Code. The issue is that
the newest version of the Life Safety Code references another code
which would require that sprinklers be installed in all residential
houses in the State of Illinois. The reason for wanting this change is
unknown. The Homebuilders Association does not have a lot of
representation in Springfield and has no influence to counteract the
proposal.
Bob Mueller asked what he thought might happen. Mr. Steiskal
replied that this issue is being discussed and he believes the State
Fire Marshal would have the votes he needs in order for this to pass.
Bob Mueller asked when it would take effect in the Village if it were to
pass. Mr. Steiskal added that it would only affect new structures and
not additions.
Steve Flint thought maybe January next year. Mr. Steiskal stated he
didn’t know.
Bob Mueller commented on how hard this would be for the builders as
it will involve additional costs. He added that he is not against saving
energy or being safe.
· High Efficiency Lighting
Mr. Steiskal stated that the 2012 Energy Code requires that 75% of
fixtures in a home must have high efficiency lighting instead of 50%.
John Cullen added that the consumer is paying more for the bulbs and
commented that this is so ComEd doesn’t have to build another power
plant. Mr. Steiskal mentioned how the CFL’s have come down in price
but they contain mercury so you have to be careful of their disposal.
John Cullen asked how an individual or business owner can address
the State about some of these matters. Mr. Steiskal indicated that you
can approach your congressman or through the Village. We can relay
your opinion against this going forward. Fire Marshal Riforgate
exampled how the State funding works and how it is tied to the Energy
Code. If you don’t follow the Code, the funding gets cut off.
New Business
130136 Amendments to the Building Code, Chapter 150, of Village Code
Review and discussion of proposed amendments to the Building Code,
Chapter 150 of Village Code. (ALL DISTRICTS)
Mr. Steiskal then referred to staff’s memo about the local amendments
Village of Lombard Page 4
Board of Building Appeals Minutes March 21, 2013
being proposed. He indicated that the proposed changes to Code are
meant to clarify the Code and be more business friendly in order to
help designers, architects, engineers and property owners find things
easier.
The proposed amendments are being presented in a redlined version
of the Code. Text being added to Code was denoted by underlining
and any deletions were struck.
1. Section 150.008 - Number of copies of Code available for
study at Village Hall
Mr. Steiskal referred to the Code books that he brought as samples
and stated that they are required to be available at Village Hall for
review. He pointed out how voluminous the books are and how costly
they are to maintain especially as updates are occurring more
frequently. He also noted that there is not and never has been a
demand for three copies and that digital versions are available.
Consequently, staff is recommending that the number of Code books
available for study at Village Hall be changed from three to two.
Mr. Steiskal asked if anyone had any questions or comments. The
members agreed with the amendment and had no questions or
comments.
2. Section 150.011 - Add Design Criteria
Mr. Steiskal exampled an experience where the architect who was
doing a commercial project questioned if the Residential Code was
applicable to the Commercial Code and why he had to meet specific
design criteria as it was not adopted in the Commercial Code. While
the Residential Code is referenced in the Commercial Code to
eliminate any confusion, staff is suggesting that the Design Criteria
found in the Residential Code be added to the beginning of the
Commercial Code in Section 150.011. This way it can be found in both
locations and there is no ambiguity in Code. This additional language
will be introduced by the following sentence with the design criteria
following:
“All structures built within the Village, the following design criteria shall
be followed:”
Ground Snow Load 25
Wind Pressure 80
Seismic Conditions 1
Weathering Severe
Frost Depth 42”
Termite Yes
Winter Design Temp 14
Village of Lombard Page 5
Board of Building Appeals Minutes March 21, 2013
RadonZone 2
Mr. Steiskal asked if anyone had any questions or comments. The
members agreed with the amendment and had no questions or
comments.
3. Section 150.011- Metal Roof Trusses
Mr. Steiskal explained that some designers screw the drywall to the
metal truss. As the cold metal at the top contracts and the warm metal
expands, this results in a buckled truss which lifts the ceiling and
cracks the drywall. Staff wants to ensure that this does not happen.
We want to make known that there are alternate installation methods
that can be used such as spray foam insulation or hanging the ceiling
from the bottom of the truss to isolate it from the truss. Truss uplift can
be significant which was experienced by the Lombard Station building
located at Charlotte and Grove. They had minimum insulation and this
was a problem for them. Having alternate installation methods can be
simple and uncostly, but will ensure that our residents will not
encounter a hardship.
Staff recommends that the following sentence be added to Section
150.011 after the design criteria (found in 2. above).
“All metal trusses shall be installed with a method approved by the
licensed designer that prevents “truss uplift”, or the finished ceiling
material shall not be directly attached to the metal truss.”
Mr. Steiskal asked if anyone had any questions or comments. The
members agreed with the amendment and had no questions or
comments.
4. Section 903.2(5)(a) - Fire Alarms
Mr. Steiskal explained that this amendment is significant. Staff is
proposing to allow the installation of a fire alarm in place of a sprinkler
system when a building addition is less than 1,000 square feet.
Mr. Steiskal provided a brief history of existing code which says that if
you have a commercial building and you propose a 500 square foot
building addition increasing the total area to 2,500 square feet or
more, currently you are required to install a sprinkler system
throughout the whole building not just the addition. The problem with
this is that a sprinkler system can cost anywhere from $60,000 to
$100,000 and the building in most cases is not appraising for enough
money. Consequently, business owners do not expand their
operations and outgrow their location and move out resulting in a lost
opportunity to maintain a business and gain important fire protection
features.
Village of Lombard Page 6
Board of Building Appeals Minutes March 21, 2013
As a result, staff is introducing an amendment whereby we can at
least get that first level of protection by requiring a fire alarm. This
amendment would not apply to high risk occupancy types such as a
fireworks manufacturing building or a condominium building
constructed of wood.
Chuck Riforgiate, Fire Marshal, stated that in a multi-family building
with 16 units or more, a fire alarm system is required in the building.
The next threshold is a high rise residential building that has units
higher than 75 feet above grade.
Mr. Steiskal indicated that staff is not proposing to back off from the
State requirements or expand those uses without a sprinkler system,
we are taking about an office building, or a small storage business
which, if approved, this amendment will enable them to survive while
offering some form of fire protection.
Fire Marshal Riforgiate indicated that he has provided updated
language which he distributed to the members. He indicated that this
amendment does not include occupancy types A, F, H, I or R.
Mr. Steiskal stated that this amendment would be a benefit because if
someone wants to do a commercial addition, we will be getting a fire
alarm where there was not one before. He explained that A stands for
assembly which includes restaurants with a capacity of over 49
people. Anything under 50 is not classified as assembly but as
business.
Mr. Steiskal asked if anyone had any questions or comments. The
members agreed and stated this was a great amendment.
5. Section 309.6 - Gutters and Garages
Mr. Steiskal indicated that language would be added to Section 309.6
that all garages built after May 1, 2013 shall have gutters installed, or
equal as approved by the Community Development Director or his/her
designee. “Equal” would mean something like a French drain, a
trench with gravel, etc. which would have to be approved. What we
want to avoid is water being directed to a neighbor’s yard or having a
trench dug too close to the side of the garage where it end up will
rotting the side. Code currently states that gutters are required on
habitable structures.
Mr. Steiskal asked if anyone had any questions or comments. The
members agreed that the amendment made sense and had no other
comments or questions.
Village of Lombard Page 7
Board of Building Appeals Minutes March 21, 2013
6. Section 150.141(X) - Plan Review Fees
Mr. Steiskal indicated that staff is proposing that the following
language to be added into the plan review section fees.
“Plan review fees shall be paid if plan review has been completed.
This would apply even if the permit applicant withdraws the permit, or
does not pick up the permit.”
There is a loophole that currently exists in Code which we want to
close. This happened not too long ago when a homeowner wouldn’t
pay the plan review fee because the Code was unclear. The thought
would be to not charge the fee upfront; rather, staff will send them a
bill. If they choose to not pay it, we can send it to collections. This
amendment would be forcing people to pay for a service they already
received.
Mr. Steiskal asked if anyone had any questions or comments.
Steve Flint suggested charging upfront. Mr. Steiskal responded that
some towns do it that way but we decided otherwise because in most
cases, people come unprepared to pay. We can still begin the permit
and when they pick it up, they can pay.
John Cullen suggested setting up an escrow account for people who
process multiple permits throughout the year. Marty Igoe added that it
was a great idea. Mr. Steiskal added that staff will look at this
possibility with the New World software when E-Suite is up and
running.
A motion was made by Stephen Flint, seconded by Marty Igoe, to recommend
to the Board of Trustees the adoption of the proposed building amendments to
Chapter 150. The motion passed by a unanimous vote.
Mr. Steiskal then updated the members on what was going on in the
Village.
Staff is now beginning to do preliminary review plans electronically.
The technology is allowing you to buy a TV as large as the plans. He
indicated he has a 50” flat TV screen in his office and how it is hooked
up to a computer. The computer also has software which enables
them to review the plans. The cost of the software was free.
Reviewing plans in this fashion is more cost effective as it eliminates
shipping, energy, paper and storage costs and cuts down on review
time. The software forces us to go through a pre-defined checklist so
it helps avoid errors. Staff is currently working out the bugs before this
new procedure is being announced.
Village of Lombard Page 8
Board of Building Appeals Minutes March 21, 2013
Bob Mueller asked if permit fees would be going down since the
Village is saving money with this new technology. Mr. Steiskal
answered no.
John Cullen asked if there was state funding for this type of
technology. Mr. Steiskal responded that we do apply for grants but
they mainly apply toward the promotion of building permits such as for
pamphlets and the like. The Village has applied for and received a
$50,000 lighting grant. This enabled the Village to upgrade or replace
the lights in the entire building. While these types of initiatives as well
as staffing reductions have cut costs, we have to keep taking
advantage of these incenvites in order to keep up.
Bob Mueller asked how staff determines if a house is 75% efficient.
Mr. Steiskal answered that we count the light bulbs. The Village has
not increased fees even though codes are being mandated. We also
have interns that work here for free but the inspection work that is
required is considered speciality work and these mandates cost
money in order to enforce.
John Cullen added that everyone at the local level needs to go back to
the State. Mr. Steiskal mentioned that the Village Manager
participates in the DuPage Mayor & Managers which is a forum for
local DuPage officials to speak their concerns which are then taken to
Springfield.
Steve Flint mentioned how he went down to Springfield last week with
other architects.
Marty Igoe asked if there was any talk about Lombard using smart
meters. Mr. Steiskal indicated it is up to ComEd. Right now it is
voluntary and you get a discount if you use it. The smart meters can
register when you are using certain appliances at a specific time and
would know when the electrical grid is becoming too burdened. They
can then turn off the applicances to avoid a blackout. Unfortunately,
there is a concern that ComEd would collect information about your
lifestyle which raises privacy concerns.
Marty Igoe asked about ComEd controlling the electricity. There was
talk about ComEd giving a discount to residential users if they allow
something on their air conditioning to turn it off during peak times. Mr.
Steiskal added that ComEd gives the Village a discount for turning on
generators during peak electrical times.
Bob Mueller questioned if the costs would be higher for using gas and
would offset the electrical savings. Mr. Steiskal answered that our
Village of Lombard Page 9
Board of Building Appeals Minutes March 21, 2013
generators are diesel.
Mr. Steiskal mentioned how the Village has begun using a new
software program, New World Systems which is specially made for
government. The hope is that the new software will enable customers
to do more online than we have done in the past. This would include
using a smart phone to make payments, check the status of permits or
schedule inspections.
Marty Igoe asked about the number of permits. Mr. Steiskal replied
that we are over 2,500 permits right now. He exampled how Yorktown
has submitted several permits for over $5 million and with the new
mandates for energy efficient windows the numbers are climbing.
John Cullen commented that every time the Village requires a new
permit with an associated fee, you either lose people upgrading their
homes due to the cost or they bypass the permit process. Mr. Steiskal
exampled house flippers who usually gut the whole house and don’t
get permits.
Lastly, Mr. Steiskal updated the Board about the status of the house in
Yorkshire Woods that has been sitting unfinished for years as well as
the house that has the Manco sign still in front of it even though the
house is finished.
Unfinished Business
Other Business
Adjournment
A motion was made by Stephen Flint, seconded by Bob Mueller, to adjourn the
meeting at 7:55 p.m. The motion passed by a unanimous vote.
Village of Lombard Page 10