Public Works & Environmental Concerns
Regular MeetingLombard, IL · December 12, 2016
Minutes
Village of Lombard
Village Hall
255 East Wilson Ave.
Lombard, IL 60148
villageoflombard.org
Minutes
Monday, December 12, 2016
6:00 PM
Public Works Conference Room
Public Works & Environmental Concerns
Trustee Bill Ware - Chairperson
Trustee Dan Whittington - Alternate Chairperson
Art Kuehl, John Kaforski, Mark Dvorak,
Mike Kuderna, David Arnold,
Robert Bachner and Joe Glazier
Staff Liaison:
Public Works & Environmental Minutes December 12, 2016
Concerns
1.0 Call to Order and Pledge of Allegiance
Meeting called to order by Chairperson Ware at 6:10 PM.
2.0 Roll Call
Brian Jack, Utilities Superintendent, Village of Lombard
Present 8 - Bill Ware, Arthur Kuehl, John Kaforski, Mark Dvorak, Mike Kuderna, David
Arnold, Joe Glazier Jr., and Robert Bachner
3.0 Public Participation
4.0 Approval of Minutes
A motion was made by John Kaforski, seconded by Joe Glazier, Jr., that the
minutes be approved . The motion passed by an unanimous vote.
5.0 Unfinished Business
6.0 New Business
160496 FY2016 Sewer Lining, Final Balancing Change Order No. 2
Reflecting a decrease to the contract with Insituform Technologies
USA, LLC in the amount of $984.20. (DISTRICTS - ALL)
A motion was made by David Arnold, seconded by Robert Bachner, that this
Resolution be recommended to the Board of Trustees for approval. The
motion passed by an unanimous vote.
160497 FY2016 Sidewalk, Curb & Driveway Restoration, Final Balancing
Change Order No. 1
Reflecting a decrease to the contract with Strada Construction in the
amount of $24,124.44. (DISTRICTS - ALL)
A motion was made by David Arnold, seconded by Robert Bachner, that this
Resolution be recommended to the Board of Trustees for approval. The
motion passed by an unanimous vote.
160498 FY2016 Concrete Rehabilitation & Utility Cuts Patching, Final
Balancing Change Order No. 1
Reflecting a decrease to the contract with Triggi Construction in the
amount of $17,630.17. (DISTRICTS - ALL)
A motion was made by David Arnold, seconded by Robert Bachner, that this
Resolution be recommended to the Board of Trustees for approval. The
motion passed by an unanimous vote.
160503 FY2016 Asphalt Paving & Patching Program, Final Balancing
Change Order No. 2
Village of Lombard Page 1
Public Works & Environmental Minutes December 12, 2016
Concerns
Reflecting a decrease to the contract with G.A. Paving LLC in the
amount of $222,919.04. (DISTRICTS - ALL)
Bachner: why was the reduction so large? Goldsmith: explained the
significant changes that caused this reduction.
A motion was made by David Arnold, seconded by Robert Bachner, that this
Resolution be recommended to the Board of Trustees for approval. The
motion passed an unanimous vote.
160509 IL Route 53 Storm Water Pump Station, Change Order No. 1
Reflecting an increase to the contract with Rausch Infrastructure in the
amount of $127,692.68. (DISTRICT #1)
Kaforski: asked for more explanation. Goldsmith: reviewed the
change order with the committee members. Further discussion took
place.
A motion was made by David Arnold, seconded by Robert Bachner, that this
Resolution be recommended to the Board of Trustees for approval. The
motion passed by an unanimous vote.
7.0 Other Business
Kuehl: Madison and 53 looks great - when will signal be installed?
Goldsmith: in the Spring. Glazier: are there any precautions taken
with the Brine Spreader? Goldsmith: yes. Bachner: questioned our
water quality - has had conversations with Tropi-quatics about fish
dyeing. Goldsmith: haven't heard of this. Water Quality Report is out
on the Village Website.
8.0 Information Only
160460 SL-RAT Acoustic Pipeline Monitoring & Assessment Project
Staff recommendation that the Public Works Committee support this
technology and future program when presented to the Village Board in
2017.
This Item was moved to first Item on the Agenda. Brian Jack, Utilities
Superintendent, in attendance to review this Item with the committee.
Jack: played short video for the committee members of the SL-RAT
(Sewer Line - Rapid Assessment Tool). Discussion ensued during the
presentation. Jack: reviewed reports that are generated by the
system. Ware: this is more preventative correct? Jack: yes.
Goldsmith: will allow significantly reduced costs for sewer televising
program. Discussion regarding costs/who will perform the work, etc.
took place. Goldsmith: just wanted to make committee aware of this
and you will be seeing more of these type of programs down the line.
9.0 Adjournment
Village of Lombard Page 2
Public Works & Environmental Minutes December 12, 2016
Concerns
A motion was made by Joe Glazier, Jr., seconded by John Kaforski, that the
meeting be adjourned at 7:03 PM. The motion passed by an unanimous vote.
Village of Lombard Page 3
Agenda
Village Hall
Village of Lombard 255 East Wilson Ave.
Lombard, IL 60148
villageoflombard.org
Meeting Agenda
Public Works & Environmental
Concerns
Trustee Bill Ware - Chairperson
Trustee Dan Whittington - Alternate Chairperson
Art Kuehl, John Kaforski, Mark Dvorak,
Mike Kuderna, David Arnold,
Robert Bachner and Joe Glazier
Staff Liaison:
Monday, December 12, 2016 6:00 PM Public Works Conference Room
1.0 Call to Order and Pledge of Allegiance
2.0 Roll Call
3.0 Public Participation
4.0 Approval of Minutes
5.0 Unfinished Business
6.0 New Business
160496 FY2016 Sewer Lining, Final Balancing Change Order No. 2
Reflecting a decrease to the contract with Insituform Technologies USA,
LLC in the amount of $984.20. (DISTRICTS - ALL)
160497 FY2016 Sidewalk, Curb & Driveway Restoration, Final Balancing
Change Order No. 1
Reflecting a decrease to the contract with Strada Construction in the
amount of $24,124.44. (DISTRICTS - ALL)
160498 FY2016 Concrete Rehabilitation & Utility Cuts Patching, Final
Balancing Change Order No. 1
Reflecting a decrease to the contract with Triggi Construction in the
amount of $17,630.17. (DISTRICTS - ALL)
160503 FY2016 Asphalt Paving & Patching Program, Final Balancing
Change Order No. 2
Reflecting a decrease to the contract with G.A. Paving LLC in the
amount of $222,919.04. (DISTRICTS - ALL)
Village of Lombard Page 1 Printed on 12/8/2016
Public Works & Environmental Meeting Agenda December 12, 2016
Concerns
160509 IL Route 53 Storm Water Pump Station, Change Order No. 1
Reflecting an increase to the contract with Rausch Infrastructure in the
amount of $127,692.68. (DISTRICT #1)
7.0 Other Business
8.0 Information Only
160460 SL-RAT Acoustic Pipeline Monitoring & Assessment Project
Staff recommendation that the Public Works Committee support this
technology and future program when presented to the Village Board in
2017.
9.0 Adjournment