Public Works & Environmental Concerns
Regular MeetingLombard, IL · February 14, 2017
Minutes
Village of Lombard
Village Hall
255 East Wilson Ave.
Lombard, IL 60148
villageoflombard.org
Minutes
Tuesday, February 14, 2017
7:00 PM
Lorraine G. Gerhardt Community Room
Public Works & Environmental Concerns
Trustee Bill Ware - Chairperson
Trustee Dan Whittington - Alternate Chairperson
Art Kuehl, John Kaforski, Mark Dvorak,
Mike Kuderna, David Arnold,
Robert Bachner and Joe Glazier
Staff Liaison:
Public Works & Environmental Minutes February 14, 2017
Concerns
1.0 Call to Order and Pledge of Allegiance
Meeting called to order by Chairperson Ware at 7:01 PM.
2.0 Roll Call
Present 5 - Bill Ware, Arthur Kuehl, Mike Kuderna, David Arnold, and Robert Bachner
Absent 3 - John Kaforski, Mark Dvorak, and Joe Glazier Jr.
3.0 Public Participation
4.0 Approval of Minutes
A motion was made by Robert Bachner, seconded by Mike Kuderna, that the
minutes be approved . The motion passed by an unanimous vote.
5.0 Unfinished Business
6.0 New Business
170079 Street Lighting Expansion Request
Recommendation of Staff that continued emphasis be placed on
maintaining existing street lights rather than expanding the network.
Goldsmith: reviewed this item and memo with the committee
members present. Arnold: Berkshire and Ridge - cover missing off of
ComEd light. Drove this area and there are some really dark areas.
Could use street lights but now is just not the right time.
A motion was made by David Arnold, seconded by Arthur Kuehl, that
committee concur with staff on this item. The motion passed by an
unanimous vote.
170046 2018 Budget Forecast & Plan Development
2018 Budget Planning Discussion.
A motion was made by David Arnold, seconded by Mike Kuderna, that this
Discussion item be tabled to the March 14th meeting. The motion passed by
an unanimous vote.
170080 Village Board Policy Amendment 6.D - Modifications
Staff recommends that the Committee agree to the proposed
modifications to the Policy and forward the recommendation to the
Village Board.
Goldsmith: apologized that this item is not in everyone's packet.
Requested to table this item to the next committee meeting on March
14th. Will notify committee members when we are going out to check
a few locations to try out the grinder if they would like to stop by and
Village of Lombard Page 1
Public Works & Environmental Minutes February 14, 2017
Concerns
see the process.
A motion was made by David Arnold, seconded by Mike Kuderna, that this
Resolution be tabled . The motion passed by an unanimous vote.
170045 Roosevelt Road Water Main Lining, Final Balancing Change Order
No. 2
Reflecting a net decrease to the contract with Fer-Pal Infrastructure
USA, Inc. in the amount of $706,065.32. (DISTRICTS #2 & #6)
Goldsmith: reviewed the change order with the committee members
present. Also, thanked the committee for all of their support on Village
projects.
A motion was made by David Arnold, seconded by Mike Kuderna that this
Resolution be recommended to the Board of Trustees for approval on the
Consent Agenda. The motion passed by an unanimous vote.
170055 TIF District Lighting Improvements, Change Order No. 2
Reflecting an increase to the contract with Thorne Electric Inc. in the
amount of $25,887.03. (DISTRICTS #1 & #4)
Goldsmith: reviewed the change order with the committee members
present. Arnold: why did we do this in the winter instead of the
summer? Goldsmith: this was originally a 2017 project - but moved
up because of some issues presented by the downtown businesses
and the public.
A motion was madeby David Arnold, seconded by Mike Kuderna, that this
Resolution be recommended to the Board of Trustees for approval. The
motion passed by an unanimous vote.
170073 MSI Sewer Inspection, Change Order No. 1
Reflecting an increase to the contract with Redzone Robotics, Inc. in
the amount of $10,000.00. (DISTRICTS #1, #2 & #5)
Goldsmith: reviewed the change order with the committee members
present.
A motion was madeby Arthur Kuehl, seconded by Robert Bachner, that this
Resolution be recommended to the Board of Trustees for approval. The
motion passed by an unanimous vote.
7.0 Ratification
160457 Transmission Main, Final Balancing Change Order No. 3
Reflecting an increase to the contract with Swallow Construction in the
amount of $204,269.61 reflecting changes to the contract as agreed.
(DISTRICT #6)
A motion was made by David Arnold, seconded by Arthur Kuehl that this item
be ratified. The motion passed by an unanimous vote.
Village of Lombard Page 2
Public Works & Environmental Minutes February 14, 2017
Concerns
8.0 Other Business
9.0 Information Only
170077 Capital Improvements Tracking
This report is being presented as information only and will be
presented to the Committee on a quarterly basis.
Goldsmith: reviewed the CIP tracking with the committee members
present. Gave presentation of the report that will be distributed to the
committee on a quarterly basis. Discussion ensued regarding Rte. 53
signal at Madison.
170078 Professional Services Selection Process
Engineering Shortlist
Goldsmith: reviewed the process that Public Works uses to procure
Professional Engineering Services. Discussion ensued regarding
types of Engineering Services that the Village utilizes on Capital
Projects.
10. Adjournment
0
Goldsmith: there will be a joint meeting on March 14th, immediately
following the PW/ECC meeting. The PW/ECC meeting will be 6:00
PM.
Arnold: interesection of Grace and Maple going eastbound - salt to
intersection sooner.
A motion was made by Arthur Kuehl, seconded by Robert Bachner to adjourn
the meeting at 7:56 PM. The motion passed by an unanimous vote.
Village of Lombard Page 3
Agenda
Village Hall
Village of Lombard 255 East Wilson Ave.
Lombard, IL 60148
villageoflombard.org
Meeting Agenda
Public Works & Environmental
Concerns
Trustee Bill Ware - Chairperson
Trustee Dan Whittington - Alternate Chairperson
Art Kuehl, John Kaforski, Mark Dvorak,
Mike Kuderna, David Arnold,
Robert Bachner and Joe Glazier
Staff Liaison:
Tuesday, February 14, 2017 7:00 PM Lorraine G. Gerhardt Community Room
1.0 Call to Order and Pledge of Allegiance
2.0 Roll Call
3.0 Public Participation
4.0 Approval of Minutes
5.0 Unfinished Business
6.0 New Business
170079 Street Lighting Expansion Request
Recommendation of Staff that continued emphasis be placed on
maintaining existing street lights rather than expanding the network.
170046 2018 Budget Forecast & Plan Development
2018 Budget Planning Discussion.
170080 Village Board Policy Amendment 6.D - Modifications
Staff recommends that the Committee agree to the proposed
modifications to the Policy and forward the recommendation to the
Village Board.
170045 Roosevelt Road Water Main Lining, Final Balancing Change Order
No. 2
Reflecting a net decrease to the contract with Fer-Pal Infrastructure
USA, Inc. in the amount of $706,065.32. (DISTRICTS #2 & #6)
170055 TIF District Lighting Improvements, Change Order No. 2
Reflecting an increase to the contract with Thorne Electric Inc. in the
amount of $25,887.03. (DISTRICTS #1 & #4)
Village of Lombard Page 1 Printed on 2/9/2017
Public Works & Environmental Meeting Agenda February 14, 2017
Concerns
170073 MSI Sewer Inspection, Change Order No. 1
Reflecting an increase to the contract with Redzone Robotics, Inc. in the
amount of $10,000.00. (DISTRICTS #1, #2 & #5)
7.0 Ratification
160457 Transmission Main, Final Balancing Change Order No. 3
Reflecting an increase to the contract with Swallow Construction in the
amount of $204,269.61 reflecting changes to the contract as agreed.
(DISTRICT #6)
8.0 Other Business
9.0 Information Only
170077 Capital Improvements Tracking
This report is being presented as information only and will be presented
to the Committee on a quarterly basis.
170078 Professional Services Selection Process
Engineering Shortlist
10.0 Adjournment
Village of Lombard Page 2 Printed on 2/9/2017