Riverwalk Planning, Design and Construction Committee
Regular MeetingNaperville, IL · February 1, 2022
Minutes
400 S. Eagle Street
City of Naperville Naperville, IL 60540
Meeting Minutes
Riverwalk Planning, Design and Construction Committee
Tuesday, February 1, 2022 7:30 AM Municipal Center Lunchroom
A. CALL TO ORDER:
Planning, Design and Construction Committee Chairman Friant called the
February 1, 2022 Naperville Riverwalk Planning, Design and Construction
Committee (PDC) meeting to order at 7:31 a.m. The meeting was held in
the lunchroom of the Naperville Municipal Center located at 400 S. Eagle
St., Naperville, IL.
B. ROLL CALL:
Present: Pam Bartlett; John Cuff; Jan Erickson; Jeff Friant, PDC
Chairman; John Joseph; Pat Kennedy, Riverwalk Commission Chairman;
Bill Novack; and Tom Stibbe
Absent: Valla Aguilar; Mary Gibson; Ian Holzhauer; and Debra Lellbach
Also Present: Rebecca DeLarme, City Staff; Brian Dusak, ERA; Monica
Goshorn-Maroney, GRWA; and Carl Peterson, GRWA
C. PUBLIC FORUM:
There were no public comments.
D. OLD BUSINESS:
1. Approval of Minutes - Jeff Friant
Approve minutes from the November 30, 2021 Planning, Design and Construction
Committee meeting
Attachments: 21PDCMinutes1130
A motion to approve the November 30, 2021 Planning, Design and
Construction Committee meeting minutes was made by Erickson and
seconded by Kennedy. MOTION CARRIED with Stibbe abstaining
2. Park District - Tom Stibbe
Stibbe reported that staff has been removing snow and the Christmas
decorations have been taken down except for two items that are frozen to
City of Naperville Page 1 Printed on 5/5/2022
Riverwalk Planning, Design and Meeting Minutes February 1, 2022
Construction Committee
the ground and will be removed once they thaw.
The Park District’s Trades Department is finishing up the Fredenhagen
Park restroom renovations, which should be completed within the next
couple of weeks. Discussion followed on if the improvements would last
longer with better security. Stibbe noted the conflict with having video in
restrooms, but advised that this year’s improvements were like the ones
completed at the warming shelters a few years ago, and those have held
up well to date. Cuff inquired if the Park District was still looking to acquire
security cameras. Stibbe will have to check, stating he knew that at one
point they were looking to purchase a mobile security camera.
Stibbe advised that flower orders are in and will be ready to go in May. He
also noted that Ray McGury is leaving his position at the Park District and
Brad Wilson will be the new Executive Director.
3. 2022 Riverwalk Work Plan (PA022) - Bill Novack and Tom Stibbe
Novack and Stibbe will review items as the weather improves and get a
plan together for 2022. Funds for the Master Plan sign attachments will
come from PA022.
4. Moser Tower Rehabilitation - Bill Novack
Novack reported that the majority of work has been completed and the
scaffolding is being removed. After reviewing alternatives for the exterior
of the base treatment, the decision was made to use a field applied
concrete veneer. Details are being worked through on the curbing at the
bottom and waterproofing the exposed areas, which will be completed in
the spring. A change order has been approved and will extend the contract
to the middle of May to allow for the landscaping and waterproofing.
Kennedy inquired about the possibility of a grand re-opening. Suggestions
were made to include working with Sameera Luthman of the Park District,
timing an event to coincide with the Memorial Day weekend events, and
including the Downtown Naperville Alliance with promoting the event. More
discussion will follow.
5. Riverwalk Master Plan Signage - Bill Novack
Receive and discuss the Master Plan Sign Attachment Pricing Summary and Sign
Bracket Detail
Attachments: MasterPlanSignAttachmentPricingSummaryandBracketDetail
Novack reviewed the updated Master Plan Sign Attachment Pricing
Summary. The Park District staff will perform the installation of the sign
attachments to the existing Riverwalk signs and a purchase order will be
City of Naperville Page 2 Printed on 5/5/2022
Riverwalk Planning, Design and Meeting Minutes February 1, 2022
Construction Committee
put through to purchase the materials from Fossil Industries, who made the
original sign inserts.
Discussion followed on the timing and if the QR code material would be
ready. Stibbe would like to have the Park District staff work on assembly in
advance to make sure there are no issues and then complete the others on
the date decided by the Commission. It was also suggested to have the
QR codes tested before they were made public.
There will be two QR codes on each sign attachment, one for “Donate” and
one for “Learn More”. The “Donate” QR code will link to the Foundation’s
website and the “Learn More” QR code will link to the City’s website where
the Riverwalk 2031 Master Plan is located.
GRWA will reserve the QR codes and complete the artwork once they
receive the landing page or URL information. Goshorn-Maroney will work
with Stephanie Penick, the Riverwalk Foundation’s website representative,
to confirm the “Donate” page location.
It was agreed that the QR codes or the content that they point to could both
be changed in the future. Novack will work on the “Learn More” URL and
Cuff will work with Penick on the Foundation’s URL for “Donate”.
Goshorn-Maroney noted they will work on printing the QR codes to scale
before submitting them to the sign fabricator.
6. Riverwalk Master Plan - Pat Kennedy
Kennedy reported that plans are moving forward with the design and
permitting for the Eagle Street Gateway project, with Novack adding that a
purchase order has already been issued. They are currently awaiting the
proposal for the preliminary design for the South Gateway project, which
should be received this week.
An outline for fundraising has been developed and a 2031 Master Plan
Fundraising Committee will be created with a liaison from the Riverwalk
Commission and the Riverwalk Foundation. The committee would consist
of eight to twelve members and could pull in additional volunteers from
outside. Kennedy inquired if anyone was interested or had suggestions for
potential members.
Joseph and Rick Hitchcock have put together an outline for engaging a
consultant for presentations, videos, and other communication materials. A
request for funding has been made to the Foundation so a budget can be
created. Cuff advised that the Foundation should be meeting within the
next week.
City of Naperville Page 3 Printed on 5/5/2022
Riverwalk Planning, Design and Meeting Minutes February 1, 2022
Construction Committee
Erickson and Holzhauer met with the Young Professionals Network of the
Naperville Chamber in January. Erickson provided copies of their
PowerPoint presentation, which included Riverwalk history with pictures
and each Master Plan project. She also provided a list of names of those
interested in participating with the Master Plan and the Commission.
Stibbe inquired about a timeline for starting on the projects, expressing
concern about the Park District operating on significantly less seasonal
labor hours. Discussion followed about the maintenance agreement
between the City and the Park District and the procedures for covering
costs with each addition to the Riverwalk, which needs City Council and
Park District Board approval. Stibbe reviewed the different staff positions
and the suggestion of considering storage facilities in the project design of
the south extension was discussed.
E. NEW BUSINESS:
There was no new business to discuss.
F. MEETING SCHEDULE:
Riverwalk Commission, February 9, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
Riverwalk Planning, Design & Construction, March 1, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
Riverwalk Commission, March 9, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
Riverwalk Planning, Design & Construction, April 5, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
G. ADJOURNMENT:
A motion to adjourn the meeting was made by Novack and seconded by
Joseph at 8:29 a.m. MOTION CARRIED
Respectfully submitted by
Rebecca DeLarme, City Staff
City of Naperville Page 4 Printed on 5/5/2022
Agenda
400 S. Eagle Street
City of Naperville Naperville, IL 60540
Meeting Agenda
Riverwalk Planning, Design and Construction Committee
Tuesday, February 1, 2022 7:30 AM Municipal Center Lunchroom
A. CALL TO ORDER:
B. ROLL CALL:
C. PUBLIC FORUM:
D. OLD BUSINESS:
1. Approval of Minutes - Jeff Friant
22-0134 Approve minutes from the November 30, 2021 Planning, Design
and Construction Committee meeting
2. Park District - Tom Stibbe
3. 2022 Riverwalk Work Plan (PA022) - Bill Novack and Tom Stibbe
4. Moser Tower Rehabilitation - Bill Novack
5. Riverwalk Master Plan Signage - Bill Novack
22-0135 Receive and discuss the Master Plan Sign Attachment Pricing
Summary and Sign Bracket Detail
6. Riverwalk Master Plan - Pat Kennedy
E. NEW BUSINESS:
City of Naperville Page 1 Printed on 1/27/2022
Riverwalk Planning, Design and Meeting Agenda February 1, 2022
Construction Committee
F. MEETING SCHEDULE:
Riverwalk Commission, February 9, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
Riverwalk Planning, Design & Construction, March 1, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
Riverwalk Commission, March 9, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
Riverwalk Planning, Design & Construction, April 5, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
G. ADJOURNMENT:
Any individual with a disability requesting a reasonable accommodation in order to
participate in a public meeting should contact the Communications Department at least
48 hours in advance of the scheduled meeting. The Communications Department can
be reached in person at 400 S. Eagle Street, Naperville, IL., via telephone at
630-420-6707 or 630-305-5205 (TDD) or via e-mail at info@naperville.il.us. Every effort
will be made to allow for meeting participation.
City of Naperville Page 2 Printed on 1/27/2022