A. CALL TO ORDER:
Friant called the October 4, 2022 Naperville Riverwalk Planning, Design
and Construction Committee (PDC) meeting to order at 7:31 a.m. The
meeting was held in the lunchroom of the Naperville Municipal Center
located at 400 S. Eagle St., Naperville, IL.
B. ROLL CALL:
Present: John Cuff; Jan Erickson; Jeff Friant, PDC Chairman; and Bill
Novack (Not enough members present to establish a quorum, so no action
taken over the course of the meeting)
Absent: Valla Aguilar; Pam Bartlett; Mary Gibson; Ian Holzhauer; Pat
Kennedy, Riverwalk Commission Chairman; Tom Stibbe; Mike Sullivan;
and Carl Wohlt
Also Present: Rebecca DeLarme, City Staff; Mike DiCristina, Naperville
Park District; Brian Dusak, ERA; Monica Goshorn-Maroney, GRWA; and
Carl Peterson, GRWA
C. PUBLIC FORUM:
There was no public forum.
D. OLD BUSINESS:
1. Approval of Minutes - Jeff Friant
Approve minutes from the September 6, 2022 Planning, Design and Construction
Committee meeting
Attachments: 22PDCMinutes0906
No vote was taken to approve the September 6, 2022 minutes as there
was not a quorum of the Riverwalk Commissioners present.
2. Park District - Mike DiCristina
DiCristina reported that staff has been busy removing summer annuals and
City of Naperville Page 1 Printed on 11/4/2022
Riverwalk Planning, Design and Meeting Minutes October 4, 2022
Construction Committee
planting fall annuals. A lot of tree work is being done to include overstory
tree pruning. Trees and shrubs were planted last week. Staff is going
through the pathways and replacing any heaved bricks. They have recently
hired a Park Specialist and a Park Maintenance IV employee.
Cuff commented on the great job done by the crew of three volunteers that
have been assisting on the east extension. DiCristina provided more
information on these three individuals that live in the area with Erickson
noting the importance of recognizing them for their efforts. Cuff will speak
with Stephanie Penick regarding this and work with DiCristina.
3. Moser Tower Rehabilitation - Bill Novack
Novack reported that the contractor is back and working on the façade at
the bottom. They have a meeting later this morning. Dusak said they will
be walking the site for a final look over and review of punch list items
before the concrete sealer is applied. Coping stones will be going in soon
and then waterproofing will be performed at the base. Landscaping will
follow and this project is scheduled to be wrapped up this year. Dusak will
obtain a schedule from the contractor this morning to communicate with the
group.
4. Riverwalk Master Plan - Jan Erickson for Pat Kennedy
Erickson advised the task force/Communications Team will be providing
an update on the Master Plan to the Riverwalk Foundation Board tomorrow
evening and they will also discuss fundraising. A presentation has been
scheduled with the Naperville Sunrise Rotary and the PowerPoint and
leave behind document/brochure will be finalized.
5. Riverwalk Master Plan Signage - Bill Novack
Novack reported no progress has been made due to the donation issues
with the QR code and this will not be pursued this year. It will be removed
from the agenda.
6. Riverwalk Master Plan CIP/Budget Review - Bill Novack
Novack advised that all Master Plan Capital Improvement Projects as
previously reviewed with the Commission were submitted. An additional
project was added that will be discussed under New Business. The CIP
review/budget workshops with City Council will be held in Council
Chambers at 7:00 p.m. on October 24th, November 9th and November
21st. Novack will not be in attendance at the November 9th meeting but
there will be representatives from the City’s Transportation, Engineering
and Development business group (TED) attending in his place.
7. Erosion at the river bend downstream from Jefferson - Bill Novack
City of Naperville Page 2 Printed on 11/4/2022
Riverwalk Planning, Design and Meeting Minutes October 4, 2022
Construction Committee
The object has been identified and the City’s Department of Public Works
(DPW) will work to remove it when the river flow is down.
8. Accessibility audit of Riverwalk - Bill Novack
Discussion on this item was deferred until next month’s meeting.
E. NEW BUSINESS:
1. Initial scope of repairs for the Fredenhagen Park fountain - Bill Novack and Mike
DiCristina
Receive the initial scope of repairs for the Fredenhagen Park fountain
Attachments: FredenhagenParkCAR20220922
Novack met with Park District staff to discuss the report prepared by
Fountain Technologies that was included in the agenda packet. They
confirmed the leak in the fountain and prepared a scope of work to be
performed. The cost is approximately $400,000 and would include
repairing the leak outside of the vault, the leak under the fountain, replacing
the lighting, and addressing safety issues with the vault. They are unable to
phase the project but Novack was able to go back to Finance and include
an amount in next year’s CIP budget to begin design and repairs.
Discussion will need to continue on other possibilities for the area and this
item will be included on the agenda for the next Riverwalk Commission
meeting on October 12th.
Novack provided an update on the construction timing for the Washington
Street bridge, which is scheduled to begin in late February or early March
of next year.
2. Future updates to Riverwalk 2031 Master Plan - Jeff Friant
Discussions began on the possibility of updating the 2031 Master Plan and
the timing of future reviews of the Plan taking place to coincide with
budgeting and the Asset Management Plan Walk scheduled in April or May
of each year. Going forward, the PDC will plan to review the document in
June and bring recommendations to the Riverwalk Commission each July.
Suggestions discussed included 1) changing the conceptual illustrations to
match the revised plans, 2) noting the status of each project as being in the
design, construction or building phase to include the year, 3) including
“funding approved” information, 4) updating cost information, and 5) not
including too much information that would create legibility issues. Novack
suggested this be reviewed at the end of the year with the consultants to
identify funds available to make any changes. This will be discussed at
next month’s PDC meeting and will be brought before the Riverwalk
Commission in December.
City of Naperville Page 3 Printed on 11/4/2022
Riverwalk Planning, Design and Meeting Minutes October 4, 2022
Construction Committee
3. Fredenhagen Park Renovations - John Cuff
Cuff distributed photos that illustrated some restoration issues at
Fredenhagen Park. The trellises and other woodwork, which are made of
Ipe wood, were originally a reddish color but have faded and are in need of
maintenance. It was noted that with proper care, Ipe wood is designed to
last up to seventy-five years. The original reddish color can be brought
back or it can go to a rustic look but it all will need to be maintained with
sanding, possibly staining and sealing. Discussion followed on the current
Trumpet vines on the trellises, if they could be replaced by something less
invasive such as Virginia Creeper which does not flower, or if vines were
needed at all since the area may already be well-shaded. Cuff also noted
that part of the stone on the clock tower and columns and pillars are dirty
and need to be cleaned up. This item will be included on next month’s
PDC agenda for further discussion.
4. South Gateway preliminary design discussion - Brian Dusak
Goshorn-Maroney and Peterson distributed a document with photos of the
existing conditions of the south extension to begin design discussions on
the South Gateway project of the Riverwalk 2031 Master Plan. Some
suggestions for consideration included 1) having a crosswalk at the
southwest section of Martin Avenue and Washington Street, 2) buffering
noise from Washington Street, 3) possibly pulling the sidewalk back along
Washington Street to tie into the Riverwalk path, and 4) including a bikeway
from Edwards Hospital that tied into the North Central College bikeway.
Potential funding from the Illinois Transportation Enhancement Program
funding (ITEP) was also discussed as it related to the bikeway as an
alternative route of transportation.
Discussion continued on the area where the Naperville Jaycees community
event sign is located in William Friedrich Memorial Park with Erickson
noting this should be discussed with the Naperville Park District. It was
also noted that informational meetings with existing neighbors should be
held once the initial design is created that would include a five year time
lapse of what the area would look like after the improvements.
F. MEETING SCHEDULE:
Riverwalk Commission, October 12, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
Riverwalk Planning, Design & Construction, November 1, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
Riverwalk Commission, November 9, 2022, 7:30 a.m.
City of Naperville Page 4 Printed on 11/4/2022
Riverwalk Planning, Design and Meeting Minutes October 4, 2022
Construction Committee
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
Riverwalk Planning, Design & Construction, December 6, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
G. ADJOURNMENT:
No quorum was present and the meeting ended at 8:52 a.m.
Respectfully submitted by
Rebecca DeLarme, City Staff
City of Naperville Page 5 Printed on 11/4/2022
Agenda
400 S. Eagle Street
City of Naperville Naperville, IL 60540
Meeting Agenda
Riverwalk Planning, Design and Construction Committee
Tuesday, October 4, 2022 7:30 AM Municipal Center Lunchroom
A. CALL TO ORDER:
B. ROLL CALL:
C. PUBLIC FORUM:
D. OLD BUSINESS:
1. Approval of Minutes - Jeff Friant
22-1190 Approve minutes from the September 6, 2022 Planning, Design
and Construction Committee meeting
2. Park District - Mike DiCristina
3. Moser Tower Rehabilitation - Bill Novack
4. Riverwalk Master Plan - Pat Kennedy
5. Riverwalk Master Plan Signage - Bill Novack
6. Riverwalk Master Plan CIP/Budget Review - Bill Novack
7. Erosion at the river bend downstream from Jefferson - Bill Novack
8. Accessibility audit of Riverwalk - Pat Kennedy and Bill Novack
E. NEW BUSINESS:
1. Initial scope of repairs for the Fredenhagen Park fountain - Bill Novack and
Mike DiCristina
22-1191 Receive the initial scope of repairs for the Fredenhagen Park
fountain
City of Naperville Page 1 Printed on 9/29/2022
Riverwalk Planning, Design and Meeting Agenda October 4, 2022
Construction Committee
2. Future updates to Riverwalk 2031 Master Plan - Jeff Friant
F. MEETING SCHEDULE:
Riverwalk Commission, October 12, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
Riverwalk Planning, Design & Construction, November 1, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
Riverwalk Commission, November 9, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
Riverwalk Planning, Design & Construction, December 6, 2022, 7:30 a.m.
Municipal Center Lunchroom, 400 S. Eagle St., Naperville, IL
G. ADJOURNMENT:
Any individual with a disability requesting a reasonable accommodation in order to
participate in a public meeting should contact the Communications Department at least
48 hours in advance of the scheduled meeting. The Communications Department can
be reached in person at 400 S. Eagle Street, Naperville, IL., via telephone at
630-420-6707 or 630-305-5205 (TDD) or via e-mail at info@naperville.il.us. Every effort
will be made to allow for meeting participation.
City of Naperville Page 2 Printed on 9/29/2022