GIS Steering Committee Meeting
January 12, 2012
Co-Chairs: Andrew Przybylo – Trustee
George Van Geem – Village Manager
Persons in attendance:
Robert Callero Mayor
Steve Cusick MIS Dept.
Mousa Nazzal Engineering
Andrew Przybylo Trustee
Bill Shaw MIS Dept.
Andrew Vitale MIS – Sr. GIS Coordinator
Rich Wlodarski Community Development
The meeting was called to order by Trustee Przybylo at 8:03 a.m.
Agenda Item #1 – Approval of Minutes
The minutes of the December 8, 2011 meeting were approved.
Agenda Item #2 – Old Business – Project Updates
GPS Equipment
A.Vitale reported that he will take delivery of the new GPS equipment tomorrow (Friday,
January 13) morning. User training is scheduled for the same time but may have to be postponed
and rescheduled due to predicted snowfall.
MMS Update (Maintenance Management System)
B. Shaw reported that MMS administrators received training earlier this week. They then met
with Fred Braun and Bob Pilat to give them a template for information that we still need to
gather, and will meet with them again on Tuesday, January 17 to enter the information. User
training is scheduled for January 25.
B.Shaw continued that we were initially going to go live with water, sewer and signs. Public
Services has asked that we go live with these features as well as service requests and work orders
for forestry, streets - basically all aspects of Public Works. This may require a second training
class. This second class was not budgeted for, but there is money in the budget to cover it. We
are still on track to go live in early February.
Trustee Przybylo asked if we were planning on issuing a press release announcing MMS.
B.Shaw responded that when a department automates for the first time, it is a difficult process.
He would like to wait until the department is comfortable with it and has proven results. He
would like to wait until the summer.
He continued that Phase II will open MMS to all Village departments, and will allow them to
document service requests, etc. Phase III will have a resident portal (a web interface) that will
allow residents to interact with the system. This will be available this summer.
Trustee Przybylo suggested that we not wait until we interface with all the departments to
announce MMS to the public. We spent approximately $25,000 on this project and it will save a
lot of money. This is Niles management at its best. We have to show it off and impress people.
We should announce it to the press in 30 to 45 days.
Mayor Callero agreed, saying that we will tell them that when a complaint comes in, it will be
addressed and responded to. We then say that in the upcoming months, we plan to implement
Phases II and III.
Trustee Przybylo further suggested that we have the press conference at the Public Services
facility rather that Village Hall because the P.S. facility will provide a better background for
photos. The press conference should be well-planned and should allow for questions. He asked
that this committee be informed of the details of the press conference. B. Shaw stated that we
will formalize it and present it at the next meeting.
M. Nazzal asked if MMS will be linked to Atlas. S. Cusick responded that both systems use the
same data.
Stormwater Commission
A.Vitale reported that the mapping related to the non-capital improvement project has been
completed. It has been presented to the Stormwater Commission; comments have already been
made. He and Steve Vinezeano are moving forward with those comments and other related
tasks. This work is on-going; there will not be many additional updates to this committee.
Atlas Training (not on the agenda)
Mayor Callero asked about the status of Atlas training for the remaining departments: Fire
Department and Trustees. A.Vitale responded that the Fire Department has been trained.
B.Shaw stated that Trustee training is on the list but has been pushed back by three, more
pressing projects. Responding to a question about the training sessions, B. Shaw stated that most
of the feedback has been positive; employees are using the system. R.Wlodarski added that
Community Development uses it all the time and that realtors are successfully using it after a
simple, over-the-phone explanation.
Mayor Callero suggested that we tout Atlas at the press conference for MMS. Trustee Przybylo
strongly suggested that we schedule a date for Trustee training.
2
Agenda Item #3 – New Business
Sewer Infrastructure Gathering
A.Vitale reported that the sewer infrastructure data gathering will be the first project undertaken
with the new GPS unit. Community Development will help out with this project this winter. He
will also coordinate that effort with Hey and Associates; he will get their manhole invert and rim
elevation measurements and coordinate with Community Development. Responding to a
question about the reason for doing this, A.Vitale stated that this project is important to capture
data (sewer, catch basins, etc.) that is on private property and out of the right-of-way that was not
captured by the initial GPS data collection effort. Having this information will help us better
predict how and where sewers surcharge and how much inflow is coming into the main, helping
us to predict why some sewers overflow and others don’t. R.Wlodarski added that this will make
the whole sewer system more complete. Trustee Przybylo acknowledged that this will ultimately
help in storm sewer water relief and in pursuing a 30-year program for transmission and storage
of stormwater.
Cook County Data Sharing
As stated last month, A.Vitale received a download of data from Cook County as part of our
annual Data Sharing Agreement. The work is ongoing and should be available next month.
When he gets the assessment tables from the Cook County assessor’s office, he will work with S.
Cusick to implement those along with the new parcels. He will inform Community
Development as soon as those are available.
Cook County Zoning Layer
A.Vitale reported that Cook County is gathering zoning layers from participating municipalities,
and that he is prepared to share ours. It is one more data sharing that we have been asked to
enter into with the county. The zoning information that Cook County collects from the
municipalities will become part of the annual data download that they share. We will get a layer
of zoning in addition to the parcels that the county already gives us for a three-mile buffer
around Niles.
*****
A.Vitale stated that the Village Clerk has asked him to look into the new political district
boundary updates (re-districting occurs every ten years.) He is comparing the county
information to the state information; this includes the state legislature, state senate, congressional
districts and new precinct boundaries. These should be ready in a few days.
A.Vitale stated that M. Nazzal gave him the 2011 water main improvements for Main, Cleveland
and Keeney. They have been put into the system and are now available on Atlas and the PDF
documents.
Agenda Item #4 – Schedule Next Meeting (recommended date: February 9, 2012)
The next meeting will be Thursday, February 9, 2012 at 8:00 a.m. in the 2nd floor conference
room 218.
The meeting was adjourned at 8:25 a.m.
3
Steering Committee Members
Andrew Przybylo Trustee atp@vniles.com 847-588-8003
George Van Geem Village Manager gvg@vniles.com 847-588-8002
Bill Shaw MIS Director wfs@vniles.com 847-588-8015
Andrew Vitale MIS – Sr. GIS Coordinator ajv@vniles.com 847-588-8022
Steve Cusick MIS src@vniles.com 847-588-8018
Moses Nazzal Engineering Superintendent mhn@vniles.com 847-588-7924
Scott Jochim Public Services Director snj@vniles.com 847-588-7901
Bob Pilat Public Services rmp@vniles.com 847-588-7926
Rich Wlordarski Community Development rjw@vniles.com 847-588-8085
4
Agenda
“Where People Count”
MANAGEMENT INFORMATION SYSTEMS
1000 Civic Center Drive, Niles, Illinois 60714 Telephone (847) 588-8000 Fax (847) 588-8050
AGENDA
GIS Steering Committee Meeting
January 12, 2012
8:00 am
1. Approval of Minutes
2. Old Business – Project Updates
GPS Equipment
o Training scheduled – January 13
MMS Update
o Administrators Training – January 9
o Users Training – January 25
Stormwater Commission
o Non-CIP related mapping
3. New Business
Sewer Infrastructure gathering
Cook County Data Sharing
Cook County Zoning Layer
4. Schedule Next Meeting (Recommended Date: February 9, 2011)