Milwaukee Avenue Corridor Committee
Regular MeetingNiles, IL · July 11, 2017
Minutes
MILWAUKEE AVENUE CORRIDOR COMMITTEE
JULY 11, 2017 MEETING SUMMARY
CALL TO ORDER
The meeting was called to order by Co-Chair McCreery at 1:38 p.m.
ATTENDANCE
The following Committee members were in attendance:
Denise McCreery, Village Trustee
Ross Klicker, Economic Development Coordinator
Bob Pilat, Admin. Asst. to Director of Public Services
Tom Powers, Village Engineer
Bruce Sylvester, Senior Planner
Others in attendance were:
Mary Anderson, Director of Public Services
Tim O’Brien, Civil Engineer II
STREETSCAPE PROJECT UPDATE - ITEP IV
An update of the ITEP IV project, which is the streetscape project on Milwaukee Avenue
from Oakton Street to Monroe Street, was provided. Bob Pilat stated the construction
has been substantially completed for some time, however we are still waiting on IDOT
to process the pay requests from Martam Construction and invoice the Village for our
share of the construction costs.
In regards to the landscaping, the trees and shrubs for the project had a one-year
warranty and the one tree that died over the winter was replaced this spring.
Unfortunately, under the IDOT standard specifications, perennials only have a 30-day
warranty period. While the perennials thrived after being planted in late fall 2015 or
May/June 2016, many died off during the winter of 2016/17. Therefore we could not
require the landscaper to replace the perennials.
The original plantings specified were salt tolerant species, however we believe exposure
to the high levels of in this area salt may have caused them to die. Therefore the
Village’s landscape contractor was hired to replace the dead plantings, and they planted
more tried and true salt tolerant species. Additionally varied and smaller plant groups
were used to lessen the impact should there be another die off. It should be noted
Public Works will be wrapping the planter box areas this fall to minimize the amount of
salt overspray as well.
Page 1 of 3
STREETSCAPE PROJECT UPDATE – ITEP V, ITEP VI AND ITEP VII
An update of various streetscape projects was presented:
a. ITEP V – Milwaukee from Monroe to Greenwood
b. ITEP VI – Milwaukee from Howard to Jonquil
c. ITEP VII – Milwaukee/Waukegan & Waukegan/Oakton
As background, an application for funding under the State of Illinois ITEP program was
submitted for projects ITEP V and ITEP VI. In October, 2016, ITEP VI received funding
under the ITEP program in the amount of $698,620. ITEP V was not approved for
funding.
Subsequent to the award for ITEP VI there was discussion to expand the project limits
and include median improvements at the intersection of Milwaukee and Waukegan.
While the Milwaukee Avenue Corridor Committee was in favor of this, the State of
Illinois stated we would not be allowed to expand the scope of the project. IDOT
instead suggested we apply for funding in the next ITEP grant submission period of
October 2, 2017 to December 1, 2017. Just prior to this, the Village provided funding in
the FY18 budget to begin engineering work for a streetscape improvement at the
intersection of Waukegan and Oakton. As there was still a desire to pursue both
projects, it was decided to combine these two projects into one project.
Based upon this plan of action, three separate RFPs for Phase I engineering services
were issued for the projects in May. This was mainly due to grant requirements for ITEP
VI, however each is also a stand-alone project. Seven different firms submitted
proposals. Based upon the review of the proposals, it was recommended by staff to
award the contracts as follows:
a. ITEP V – ESI Consultants, LTD
b. ITEP VI – Baxter & Woodman (with Hitchcock Design Group)
c. ITEP VII - Baxter & Woodman (with Hitchcock Design Group)
Criteria used to judge the proposals include completeness of proposal, understanding of
project requirements, meeting RFP requirements, staff experience, similar project
experience, sub-consultants, schedule adherence and potential conflicts.
After discussion regarding the proposals a motion was made by Trustee McCreery,
seconded by Tom Powers, to have the Milwaukee Avenue Corridor Committee
recommend the aforementioned consultants for approval to the Village Board. On roll
call the vote was unanimous.
Page 2 of 3
UNFINISHED BUSINESS
Bob Pilat stated there was one other topic to bring up regarding ITEP IV. On east side of
Milwaukee just north of Oakton, there is a small landscaping “bump-out” just north of
the Walgreens exit. This area has been driven over several times by cars and trucks
damaging the sod. We have replaced the sod only to have it driven over the next day.
Reflective stakes were also installed to highlight the bump-out to drivers. This did not
stop vehicles either. At this time we are looking for alternative solutions to stop or
minimize the damage caused when motorists drive on this bump-out.
Various possibilities were discussed including removal and replacement of the sod with
concrete or brick pavers, removal of the entire bump-out or installation of heavy duty
driveable grass brick paver, such as Unilock’s Turfstone. The various options will be
explored further.
NEW BUSINESS
There was no new business.
ADJOURNMENT
There being no further business, a motion was made by Bob Pilat, seconded by Ross
Klicker to adjourn the meeting. The vote was unanimous and the meeting adjourned at
2:47 p.m.
Page 3 of 3
Agenda
PUBLIC MEETING NOTICE
MILWAUKEE AVENUE CORRIDOR COMMITTEE
Trustees Denise McCreery and Danette O’Donovan Matyas, Co-Chairs
Tuesday, July 11, 2017 – 1:30 p.m.
Administration Building
1000 Civic Center Drive
Niles, Illinois 60714
AGENDA
I. CALL TO ORDER
II. STREETSCAPE PROJECT UPDATE
a. ITEP IV – Milwaukee from Oakton to Monroe
III. STREETSCAPE PROJECT UPDATES & ENGINEERING SERVICES DISCUSSION
a. ITEP V – Milwaukee from Monroe to Greenwood
b. ITEP VI – Milwaukee from Howard to Jonquil
c. ITEP VII – Milwaukee/Waukegan & Waukegan/Oakton Project
V. OLD BUSINESS
V. NEW BUSINESS
VI. ADJOURNMENT