Stormwater Commission
Regular MeetingNiles, IL · March 19, 2012
Minutes
STORMWATER COMMISSION
MEETING SUMMARY
Monday, March 19, 2012
The following persons were present: Steven Vinezeano, Andrew Vitale, Richard
Wlodarski, Fred Kudert, Tom Polcyn, Chuck Ostman, Mousa Nazzal, Robert Callero,
George Van Geem Scott Jochim and Pat Lach and Jeff Wickenkamp of Hey and
Associates. Also in attendance was Eric Duray of ComEd. Absent: Chair Joe Lo Verde
The meeting was called to order at Noon.
1. Approve Meeting Summary of Thursday, March 8, 2012: The summary was
approved to be posted on the Stormwater Commission web page.
2. Old Business:
a. Trustee Przybylo Request. In preparation for the meeting, Andrew Vitale
created a map showing reported flooding from September 2008 and July
2011.
Eric Duray presented information on ComEd outages in the last two rain
storms (September 2008 and July 2011). Was there a correlation between
power outages and flooding reported? He reviewed the 2008 event first.
The area with 164 to 2,413 minutes of outage was at one circuit with about
100 customers. The circuit was C7226. It was discussed that a ComEd
transformer at 8314 Lincoln Avenue was submerged under water in 2008.
The resident stated that just before the power went out, the transformer
popped. The Commission confirmed that the only long-term outage in 2008
rain was in the Niles area bordering Greenwood, Stolting, Nor Terrace and
Western.
At the time shortly after the storm, ComEd stated that the Village would
have to pay to lift the transformer because of the property built up around it.
The other option would be to have all that was built up around the
transformer removed. The Commission asked Eric to have ComEd review
this situation again in an effort to prevent outages in this area in the future
due to the transformer being submerged. Vinezeano stated that, unlike in
2008, the Village can now show with engineering data that the area is a low
point. He stated he would look into the possibility.
Fred was interested in ComEd’s ability to give frequency data of outages
lasting two hours or more. If we know there is an area that is impacted
more often by outages and assessable to flooding, ComEd will work to
focus on it. In 2009, the average was one outage per customer for 120
minutes and the goal of ComEd is to reduce this by 20%. Most outages in
Niles are not weather related.
The Mayor asked if ComEd could provide data for areas on outages and
Eric stated that with the current system it is feeder based and since working
with the NWMC on some annual report changes, starting in 2012 the report
will provide a better form of the data. Currently he can only key on one
circuit. The Mayor asked Eric if ComEd can give the Village the areas with
the most outages in the past three years. Eric stated he can if he has
addresses. Maybe give him those addresses with flooding concerns and he
can tie it back to the outages. Jeff commented that if we had a map with
flood occurrences (which we have for 2008 and 2011 storms) and ComEd
had addresses by event and then we superimpose them and out of 700
complaints, there may be 30 that lost power. That would show that power
loss is not the key reason homes are flooding in Niles. Parameters for
information are homes with over 2 hours per occurrence and three
occurrences per year.
Van Geem asked how past performance has any bearing on future power
events. You can’t determine what will happen in the next five years. With
mechanical improvements, you can get about a 20% increase in reliability,
but you can’t stop weather or accidents that cause outages. How many
generators would need to be purchased to solve the floods caused? Eric
asked if it is because the power is out or flooding inundation. Eric stated
that generators are the least desirable situation. You want to work with the
utility to fix the problem of outages if they happen that often. A generator,
from the utilities perspective, could be helpful in a bad storm with a long
duration such as the one in July of 2011.
Vinezeano opened discussion on the ComEd transformer in the corner of
8314 Lincoln. The transformer failed in 2008 taking out the power in the
area for an extended time. Vinezeano put up a picture of the transformer in
question.
Jeff made a comment regarding a statement made by Eric regarding the
mission of ComEd and the importance of reliable power. If this transformer
is underwater due to weather related events, it should be ComEd’s
responsibility to fix it. Eric stated that there are times when homeowners
may be running a business from their home and they need uninterrupted
service and so they choose to protect their livelihood. What is an
expectable period they can be without power? How many times will there
be outages like the one in 2011? A generator should be a last resort. Work
with the utility where there are a large number of power outages. Is there a
correlation with equipment that is failing often?
Maybe some people flood because they lose power, but overlaying the
outages with the flooding data you will see most persons flood due to the
inadequate sewers and not power outages. Maybe some flood for that
reason, but the large majority does not. Is it an ad on contributor or the
main contributor?
b. Review of Open House Layout. Vinezeano discussed the layout with the
group to ensure everyone was aware of their responsibilities during the
open house.
3. New Business:
a. Project Prioritization. Jeff and Pat from Hey and Associates began
discussion about the recommended prioritization of projects based on the
$15M. There are two tiers. An implementation schedule was distributed
showing the tier one and tier two projects.
Tier One – 1 to 5 years by priority.
i. Cleveland Relief Sewer $6.9M;
ii. Milwaukee and Main to Lee, Storage and Sewer Improvements
$5M; and
iii. Storage and Conveyance Improvements West of Maryhill Cemetery
$3.1M.
Tier Two – (TBD and not prioritized)
i. Maynard and Glendale Sewer Improvements with ComEd Storage
$4.5M;
ii. Maryland/Milwaukee Improvements $5.5M;
iii. Milwaukee/Courtland Improvements $3.5M;
iv. Milwaukee and Touhy Structure Reconstruction $200K;
v. Oakton and Seward $1.7M; and
vi. Dobson Outfall $1.3M.
Jeff stated that there was a 25% contingency in the numbers shown on the
schedule. The cost share program and other ancillary projects will need to
come out of the proposed $15M.
The Mayor asked if any of the north or south projects made it into the Tier
One projects. The Callero Drive backflow preventer did make it, but it will
be pulled out as a small project.
Jeff stated the reason the Maynard and Glendale project was at the top of
Tier Two and not in Tier One was due to the $4.5M price tag. However,
when it is done could depend on if Glenview participates or there is grant
funding for an inter-jurisdictional project such as this. Glenview’s flooding
due to this area is much worse than that of Niles and they may move ahead
with it. This project could potentially be pushed into Tier One.
Jeff stated the Milwaukee and Touhy Structure Reconstruction project
could also be a shared situation due to a benefit to Chicago. Chicago has
already researched the project.
Jochim stated that in the beginning of the study, flooding in streets was not
set as a priority, so why would the Glendale area be prioritized to Tier One?
The Commission agreed that the complaints in the area were mostly due to
flooded streets, but that when it gets deep enough and flooding moves to the
yards, the sump pumps cannot keep up and that can cause flooding through
the pits. Wouldn’t it be cheaper for those residents to increase the capacity
of their sump pumps?
Jochim asked about the Maryhill Cemetery project and whether or not it
should be pushed further up on the Tier One list. It was explained by Jeff
that the Village could try to tackle all the projects at once, but that it is a lot
of balls in the air to be joggling. Someone on Village staff is going to need
to be on the ball managing the projects and be working very diligently to
move the projects forward. The Maryland and Milwaukee project was
discussed briefly.
Jeff wanted to leave the meeting with a good idea of the projects and
priorities before the open house. He mentioned that when a resident from
the Cortland area comes to the open house and sees that they are in the Tier
Two project area, they will be told there is a project, but right now it is not
programmed because it is not a high priority project. There are more
important projects and there is only $15M.
George asked if we can break out the number of homes helped per project.
He continued that it is important to show we are helping more homes with
the priority projects. Jeff stated they have that. There was discussion that it
could be addressed in a percentage of homes in stead of a cost per home.
The Chair has established early on that this is a community issue and we
didn’t need to discuss per home cost. Jeff stated that Hey and Associates
mostly planned on informing participants at the open house that the
recommendations were made based on places with the most frequent and
adverse flooding with the highest number of homes.
Jochim asked about the Cleveland Relief Sewer project. Will it help lake
Monroe? Yes. They will be shown the current flooding vs. flooding levels
after the project is in place. This will help with flooding, but it will not
make streets “bone” dry in most cases. It will cut down on flooding. They
will see that in 50- to 100-year rains, there will still be some flooding, just
not as much and not as damaging as in the past.
Jeff asked what the company line will be about the Tier One/Tier Two
projects. Why? The cost and frequency of flooding and the issues are
severe enough that we developed a project, just that there are other areas in
the Village that are worse and we need to focus on them with the initial
funds first. We developed all the projects and then came up with a subset of
all the ones that address most frequent and the highest numbers of floods.
The most frequent and sever flooding with the highest number of homes
helped by the projects. Future boards will most likely need to make a
decision on when Tier Two projects can be funded.
The Mayor stated the importance of providing information at the event
regarding the time it will take for Tier One and Tier Two projects to be
completed. Jeff stated that these projects will take years to design and
permit and years of multiple phases to construct because they are long and
big. Most will take several years from start to finish. Jochim recommended
increasing the amount of years for implementation.
There was discussion on how to show the projects on a map. It was decided
that it could be done with a large map of the Village with the Tier One and
Tier Two projects in blue and green. The amount of the Tiers would be
included. Tier One is $15M and Tier Two is $17M. Cost share is included
in these numbers.
The Mayor reiterated the top goals of the Commission. First it is to get the
sewer water (sewage) out of the basements. Next it is to keep the overland
out of the doors and windows. Reducing stormwater in the streets cannot
be a goal at this time. Jeff stated that it is probably more important to
prevent the water from coming in doors and windows overland. There are
concerns about street flooding and emergency vehicles. Vinezeano
reminded the group about the Emergency Vehicle Flood Map to be shared
with the Fire Department. This will allow the department to develop a
contingency plan for areas that are flooded past the wheel base of
emergency vehicles. Based on his discussions with the Fire Chief, this is a
good strategy. The Fire Chief stated that he is not concerned about his
department’s ability to get into flooded areas and treat patients.
Terrace Square Condos was brought up regarding flooding in the parking
lot. This will need to be investigated further, but was not initially placed in
the phase two study because of the lack of flood calls reported from the
area. The area just West of Golf Mill was discussed briefly. The
Commission did mention the one property owner on Western who floods
and how he would be covered under the flood control program if it is
implemented. He is on a private sewer that belongs to a group of
unincorporated homes.
There was discussion about the Cleveland relief sewer project. Ostman
asked whether or not it will prevent sewer backup. Jeff stated that it will
have a tremendous impact on the backups in the area, but you can never
prevent sewer backup without some form of flood control. Cleveland is a
new storm sewer that will be added next to the combined sewer. All of the
street catch basins will be tied to the storm sewer and removed from the
combined sewer. Hey put the project on the screen for discussion and
clarification. Ostman wanted to make sure everyone was clear that even
with the Cleveland sewer that will greatly reduce backups, protection with
overhead sewers or backflow preventers is still necessary to eliminate
backups entirely.
The Commission reviewed the remainder of the projects being proposed for
Tier One and Tier Two. The Commission agreed that the projects in Tier
One were chosen by the engineers correctly. The Callero Dr. Backflow
Prevention was removed, however, as a smaller project. The Tier Two
projects remained unchanged.
There was a brief discussion about how this open house was promoted.
Vinezeano stated that the same method was used as in the past, which was
articles in the local papers, an article in the Village newsletter, and a
message on the Police sign. This year Niles TV was also used to promote
the event. In the past, over 200 showed, but it was mentioned that there was
flooding just days before the event.
4. Open Discussion:
a. Trustee Preston request for additional information. Vinezeano shared the
information collected from the other municipalities recently for Trustee
Preston. She wanted to know the first program year, how long it was to be
budgeted, and how it was funded. Morton Grove was added to the list for
their Overhead Sewer and Flood Control Device Assistance Program. They
use a loan program for 50% of the cost of the project up to a maximum of
$2.5k.
Mt. Prospect also uses a “loan” program. The funds for Mt. Prospect come
from their over 50 population CDBG HUD funds. They have a loan up to
$25k and began in the 1980s. Morton Grove was added to the list for their
2011 loan program with a max of $2.5k and an annual budget of $50k. This
program is for low to moderate income.
Jochim stated that this is not the first time the Village had a stormwater
related program. In the 1970s, we paid for homeowners to disconnect
downspouts and take sump pumps out of sewers.
Vinezeano shared the possibility of having the “cost share” program
changed to “flood assistance” since it could be in the form of a grant or loan
at some point.
b. Illinois “IKE” Disaster Recovery Grant. Vinezeano shared an update on the
IKE Housing Rehabilitation and Reconstruction grant. The Village
identified nine owner-occupied homes that qualified for up to $45k per
home in improvements. Ostman asked if these funds helped to stop the
flooding or just brought the homes back to pre flood conditions. Vinezeano
stated that the funds do not provide for overhead sewer or flood control,
which he believes it should.
c. IAFSM Annual Conference. Jeff mentioned the recent presentation on
stormwater given by Hey and Associates and Assistant Village Manager
Vinezeano. The presentation was on 2D modeling. Vinezeano provided a
history of Niles and the Stormwater Commission and Hey presented how
the 2D modeling will help to solve problems.
5. Next Scheduled Meetings: TBD
Agenda
“Where People Count”
1000 Civic Center Drive, Niles, Illinois 60714
Telephone (847) 588-8000 ● Fax (847) 588-8051 ● TDD (847) 588-8059
Mayor
Robert M. Callero
Trustees
Chris Hanusiak
James T. Hynes
Joe LoVerde
PUBLIC NOTICE
Rosemary Palicki
Louella B. Preston Stormwater Commission
Andrew Przybylo
Village Manager Trustee Joe LoVerde, Chairman of the Stormwater Commission,
George R. Van Geem
has called a meeting on:
Village Clerk
Marlene J. Victorine Monday, March 19, 2012 at Noon
2nd Floor Conference Room
Niles Village Hall
1000 Civic Center Drive
Niles, Illinois
www.vniles.com