Stormwater Commission
Regular MeetingNiles, IL · September 12, 2013
Minutes
STORMWATER COMMISSION
MEETING SUMMARY
Thursday, September 12, 2013
The following persons were present: Chair Joe Lo Verde, Steven Vinezeano, Chuck
Ostman, Richard Wlodarski, Robert Callero, Andrew Vitale, Fred Kudert, Tom Polcyn,
Mousa Nazzal, Scott Jochim and Jeff Wickenkamp and Patrick Lach of Hey and
Associates.
The meeting was called to order at 8:30 a.m.
I. Approve Meeting Summary of August 1, 2013: The summary was approved to
be posted on the Stormwater Commission web page.
II. Old Business:
i. Flood Control Assistance Program Update. Wlodarski provided an
update of the program. He stated 40 applicants have not responded
to contact to move forward. He stated about 50 to be done over next
couple of weeks for initial inspection. He stated that he anticipates
to stay within the budget of 1.25M. There will be about 5 to 10
percent that will not qualify for some reason or another.
ii. Small Projects
a. No update.
iii. Tier 1 Capital Improvements.
a. Cleveland Sewer Project. Jeff stated that MWRD is okay
with solution, but what happens when sleuth gate closes. He
is at 30 percent plans. He said MWRD stated there are no
promises the gates will not be closed, but it will not matter
since the outflow runs directly to the river then. Value
engineering is complete and ready for final engineering. He
stated it is time to once again approach the FPD.
Resident Mike Shields approached the commission about
extending the Cleveland sewer project westward. Jeff stated
that future upsizing would be possible, but the cost of
upsizing must be justified. Should the pipe be designed from
a 60” to a 72”. Mike stated that he does not believe the
message about the program and the upcoming projects is
understood by the public. He stated that there needs to be a
campaign to educate people on the program and progress.
Mike stated that he understands that we are putting all this
money into a new system, but what about the current sewers
that are not being replaced. What is the plan for preventive
maintenance? How long with they last?
b. Main/Lee Project. Jeff stated that the Lee portion of the
project will need to wait until 2015 due to the number of
streets that will be under construction with Cleveland sewer
project. He is investigating ways to ensure that the Lee
project does not negatively impact homes north of Lee
during a 100-year storm event that may not have been
impacted in the past.
c. OLR. The plumber who went to the church was able to
determine the problem that was causing the flooding in the
basement. It was discussed how the Church would not allow
more water to be passed to the church if this simple problem
was not corrected. The new sewer from Greenwood to
Normal will also reduce water in that direction. A meeting is
set to meet with Father Chris.
iv. IGIG Project. Scott Jochim stated that the project was well done
and done under budget. It beautified the area and made it more
functional.
III. New Business:
i. Tier III Project Development. It was discussed that the next meeting
will cover possible Tier III projects. Most likely, Tier II will be
reevaluated completely to ensure the triage is correct moving
forward since there was additional study completed since the study
was completed.
ii. Stormwater Commission Management. It was discussed that the
Village Manager cannot be expected to continue to be the project
manager of the stormwater projects. The projects are now growing
beyond his workload capacity and knowledge of actual stormwater
construction of this size and scope. There is also a need for this
position to play an oversight role of Hey and Associates to ensure
the Village’s interests are protected. There was discussion of how
there is only one engineer, a tech and the superintendent. If the
engineer retires, there will not be anyone to do in-house projects.
Vinezeano made a motion to recommend to the Village Board the
hiring of a new engineer. This motion was not seconded.
IV. Open Discussion: The Chair shared a resident letter and requested Vinezeano
to respond to it on his behalf.
V. Next Scheduled Meetings: TBD