Advisory Taskforce on Ryan Park
Regular MeetingNorwalk, CT · August 19, 2015
Minutes
Meeting Notes
Project Kickoff Meeting
Ryan Park / 192310567
Date/Time: August 19, 2015
Place: Norwalk City Hall
Next Meeting: September 10, 2015
Attendees: See Attached
Public Outreach Meeting #1 SWOT
Thursday September 10, 2015 at Norwalk Community Center.
6:15pm site walk and 6:30pm meeting start.
Stantec to draft text for meeting notification and provide to Susan.
Notification should be in English, Spanish and Creole. City to provide creole translation.
Notification by one or all of the following:
o flyer
o posting
o mailing
o TV notification
The overall schedule was revised (see attached). The meeting scheduled for September 3,
2015 with City staff was rescheduled for September 2, 2015.
Roadway & Infrastructure
Roadway and infrastructure will be completed independent of Ryan Park and the housing
development.
Tighe & Bond is the consultant responsible for Raymond & Day improvements.
Tighe & Bond is the completing a FONSI for the roadway component.
Dry Egress
Is dry egress required in the park?
2nd tax district has provided a suggestion for the dry egress and has submitted to Tighe & Bond
and is awaiting a response.
Dry access to be reviewed as the design process moves forward
oj u:\192310567\record\20150831_meeting_minutes\20150819_meeting minutes.docx
August 19, 2015
Project Kickoff Meeting
Page 2 of 2
Park Design and Regulatory
Once the design is established an environmental assessment review record will need to be
submitted for public notice and then submitted to HUD.
Agency and department review will be required for HUD submission including but not limited
to:
o Fish & Wildlife
o SHPO,
o Local Indian Tribes,
o Flood Plain Review
A FONSI will be required for HUD submission. This is outsides Stantec’s scope of work.
Phase I Environmental Site assessment of Ryan Park will be completed by the City of Norwalk.
Communication and Correspondence
All correspondence should run through Susan Sweitzer
Neighborhood communication will be done through:
o Neighborhood Outreach
o HUD’s Choice Neighborhood Website
o www.RebuildblockD.org
The next Advisory Committee meeting is scheduled for September 27, 2015 @ 11am.
The foregoing is considered to be a true and accurate record of all items discussed. If any
discrepancies or inconsistencies are noted, please contact the writer immediately.
Jeff Olszewski, RLA
Project Manager
Phone: 203-495-1645
Jeff.olszewski@stantec.com
Attachment: Sign-in Sheet
Updated Project Schedule
c. Cc List
oj u:\192310567\record\20150831_meeting_minutes\20150819_meeting minutes.docx
Development of Design and Engineering for Ryan Park
City of Norwalk, CT
Project Work Plan – Meetings Dates
Prepared by Stantec
August 2015
8/19 – Project Kick-Off / Review of Work Plan
September 2015
9/2 – Open House: City Staff / Department Interviews
9/10 – Public Outreach #1: SWOT Assessment
9/22 – Advisory Committee Meeting / Updates @ 11am
October 2015
10/8 – Public Outreach #2: Preliminary Program Recommendations
10/14 – Recreation & Parks/Advisory Committee: Draft Program Plan Review
November 2015
11/5 – Public Outreach #3: Draft Preliminary Design Review
11/11 – Recreation & Parks/Advisory Committee: Draft Preliminary Design Review
December 2015
12/9 – Recreation & Parks Committee of the Common Council: Preferred Draft Preliminary Design Review
***Holiday Break***
January 2016
1/19 – Public Meeting: Adoption of Proposed Preliminary Design
1/26 – Norwalk Common Council: Adoption of Proposed Preliminary Design
February 2016
None
March 2016
3/1 – Milestone Meeting with City: 50% Construction Document Completion
April 2016
4/19 – Submission of 100% Construction Documents