Norwalk Facilities Construction Commission
Regular MeetingNorwalk, CT · January 6, 2010
Minutes
Norwalk Facilities Construction Commission Jan 6, 2010 Minutes (Final)
CITY OF NORWALK
NORWALK FACILITIES CONSTRUCTION COMMISSION
REGULAR MEETING
JANUARY 6, 2010
ATTENDANCE: Mayor Richard A. Moccia; David Jaeger, Richard
Tavella, Dr. Dan Cook, Fred Bondi (5:36 p.m.);
Joseph Beggan (5:37 p.m.)
STAFF: Amar Shamas, Gilbane; Alan Lo, Land Use and
Building Management
ROLL CALL
The Mayor called the meeting to order at 5:35 p.m.
NORWALK SCHOOL PROJECTS
A. Norwalk High School
1. Review only, changes approved by staff:
PCO#00455 ($ 37,323.41) Decrease GMP Credit associated with deleting glycol work
For the heating system from Richard’s
Conditioning Contract (Mechanical
Contractor)
PCO#00456 $ 37,323.41 Increase GMP Retain Modern Mechanical to provide
Glycol work for the heating system at NHS.
Mr. Shamas gave a brief overview of why the change order was necessary. The
original contractor was not able to complete the task. A second contractor was
brought in and the job has been completed. The original contractor has filed for
Chapter 11. Discussion then followed about payment and warranty issues. Mr. Lo
said that the staff was working on closing out the project with the State.
B. Update on various school construction projects
1
City of Norwalk
Norwalk Facility Construction Commission
Regular Meeting
January 6, 2010
Page 1
Mr. Lo said that the Culinary Arts kitchen at Norwalk High School is up and
running. It cost about $500,000, rather than the initial proposed cost of $750,000.
The State audits for Tracey and Columbus have been completed and closed. Funds
were left over in the account. Roton Middle School was just completed. While
the project came in under budget, there was about $100,000 worth of work that
was not covered by the State reimbursement, so the City will have to pay those
costs with funds from the $70 million account.
Ponus, Nathan Hale and Norwalk High School need to be reconciled. Ponus and
Nathan Hale are looking good. Norwalk High School was a major project and will
require some time for reconciliation. The discussion then moved to Brien
McMahon and the reimbursements involved with that project.
Mr. Bondi asked about the elementary school facility study. Dr. Cook reviewed
the process with everyone and said that the BOE Finance Committee would be
reviewing two architectural firms in their upcoming meeting. A discussion
regarding the projected enrollment for the elementary schools then followed.
Mr. Shamas left the meeting at 5:55 p.m.
MINUTES OF PREVIOUS MEETING(S)
November 16, 2009
** MAYOR MOCCIA MOVED THE MINUTES OF NOVEMBER 16, 2009
MEETING.
** THE MOTION TO APPROVE THE NOVEMBER 16, 2009 MINUTES
AS SUBMITTED PASSED UNANIMOUSLY.
MUNICIPAL BUILDING IMPROVEMENT PROJECTS
A. Roosevelt Center
2
City of Norwalk
Norwalk Facility Construction Commission
Regular Meeting
January 6, 2010
Page 2
1. Review recommendation for engineering design consultant for the Roosevelt
Center Heating System Replacement Project and refer the following to the
Common Council for action:
“Authorize the Mayor, Richard A. Moccia, to execute an Agreement
with Peterson Engineering Group, LLC to provide mechanical
engineering design services for the Roosevelt Center Heating System
Improvement Project for a total not to exceed $25,575.00 plus $3,000 for
reimbursable expenses and additional services. Funds are available
from DOE Energy Efficiency and Conservation Block Grant (EECBG)
and City Capital Budget #09107100 5777 C0147”
** MR. BONDI MOVED THE ITEM.
Mr. Lo explained that Capital projects over the amount of $250,000 are brought to
the NFCC for approval. He then gave a brief history as to why the NFCC was
created and its purpose.
Mr. Lo explained that the Roosevelt Center is located on Allen Road and the
facility has three primary users, Tumblebugs, the Senior Center and Recreation and
Parks. He then gave an overview of the heating system and informed the
Commission that the project has been approved for stimulus funding.
Mayor Moccia asked if the City would be required to provide matching funds. Mr.
Lo said no. Mr. Lo then said that 13 firms had submitted bids and that the lowest
four bidders had been shortlisted and interviewed. The Interview Committee
recommends Peterson Engineering Group as the lowest responsible bidder.
** THE MOTION TO AUTHORIZE THE MAYOR, RICHARD A.
MOCCIA, TO EXECUTE AN AGREEMENT WITH PETERSON
ENGINEERING GROUP, LLC TO PROVIDE MECHANICAL
ENGINEERING DESIGN SERVICES FOR THE ROOSEVELT CENTER
HEATING SYSTEM IMPROVEMENT PROJECT FOR A TOTAL NOT TO
EXCEED $25,575.00 PLUS $3,000 FOR REIMBURSABLE EXPENSES AND
ADDITIONAL SERVICES. FUNDS ARE AVAILABLE FROM DOE
ENERGY EFFICIENCY AND CONSERVATION BLOCK GRANT
3
City of Norwalk
Norwalk Facility Construction Commission
Regular Meeting
January 6, 2010
Page 3
(EECBG) AND CITY CAPITAL BUDGET #09107100 5777 C0147 PASSED
UNANIMOUSLY.
B. Old Police Station
1. Review request to increase additional contingency funds for the Old Police
Station – Interior Hazardous Material Remediation Project and refer the
following to the Common Council for action:
“Authorize the Office of Building Management to issue Change Orders
to Environmental Consulting and Contracting, LLC’s contract for the
Old Police Station - Interior Hazardous Material Remediation Project
by increasing the Contingency Allowance for an additional $25,000.
Acct. #09107100-5777-C0368”
** MR. BONDI MOVED THE ITEM.
Mayor Moccia said that he had two personal goals while in office; one to take a
sledge hammer to the Webster Street Parking Lot Collection Booth and the second
to operate the bulldozer that takes the first run at the old Police Station.
Mr. Lo reviewed the details of the abatement issues at the Police Station and
commented that no one is allowed inside the building without wearing a full
HazMat suit. It has been discovered that some hangers holding the pipes in the
basement ceiling had been coated with asbestos along with elbow joints on the
pipes. It takes two men about forty minutes to remove each of these hangers. The
initial change order discussion was in the neighborhood of $25,000. Based on
recent on site “marked demo”, the projected change order will be between $12,000
to $15,000.
Discussion followed about the paint removal and demolition issues.
** THE MOTION TO AUTHORIZE THE OFFICE OF BUILDING
MANAGEMENT TO ISSUE CHANGE ORDERS TO ENVIRONMENTAL
CONSULTING AND CONTRACTING, LLC’S CONTRACT FOR THE
OLD POLICE STATION - INTERIOR HAZARDOUS MATERIAL
REMEDIATION PROJECT BY INCREASING THE CONTINGENCY
4
City of Norwalk
Norwalk Facility Construction Commission
Regular Meeting
January 6, 2010
Page 4
ALLOWANCE FOR AN ADDITIONAL $25,000. ACCT. #09107100-5777-
C0368 PASSED UNANIMOUSLY.
VI. MISCELLANEOUS ITEM(S)
There were no additional items to discuss at this point.
ADJOURNMENT
** MAYOR MOCCIA MOVED TO ADJOURN.
** THE MOTION PASSED UNANIMOUSLY.
The meeting adjourned at 6:15 p.m.
Respectfully submitted,
Sharon L. Soltes
Telesco Secretarial Services
5
City of Norwalk
Norwalk Facility Construction Commission
Regular Meeting
January 6, 2010
Page 5
Agenda
Norwalk Facilities Construction Commission Jan 6, 2010 Agenda (Final)
NORWALK FACILITIES CONSTRUCTION COMMISSION
WEDNESDAY, JANUARY 6, 2010
5:30 P.M. – DPW Conference Room 225, CITY HALL
I. ROLL CALL
II. MINUTES OF PREVIOUS MEETING(S)
November 16, 2009
III. NORWALK SCHOOL PROJECTS
A. Norwalk High School
1. Review only, changes approved by staff:
PCO#00455 ($ 37,323.41) Decrease GMP Credit associated with deleting glycol work
For the heating system from Richard’s
Conditioning Contract (Mechanical
Contractor)
PCO#00456 $ 37,323.41 Increase GMP Retain Modern Mechanical to provide
Glycol work for the heating system at NHS.
B. Update on various school construction projects
IV. MUNICIPAL BUILDING IMPROVEMENT PROJECTS
A. Roosevelt Center
1. Review recommendation for engineering design consultant for the Roosevelt
Center Heating System Replacement Project and refer the following to the
Common Council for action:
“Authorize the Mayor, Richard A. Moccia, to execute an Agreement
with Peterson Engineering Group, LLC to provide mechanical
engineering design services for the Roosevelt Center Heating System
Improvement Project for a total not to exceed $25,575.00 plus $3,000 for
1
reimbursable expenses and additional services. Funds are available
from DOE Energy Efficiency and Conservation Block Grant (EECBG)
and City Capital Budget #09107100 5777 C0147”
B. Old Police Station
1. Review request to increase additional contingency funds for the Old Police
Station – Interior Hazardous Material Remediation Project and refer the
following to the Common Council for action:
“Authorize the Office of Building Management to issue Change Orders
to Environmental Consulting and Contracting, LLC’s contract for the
Old Police Station - Interior Hazardous Material Remediation Project
by increasing the Contingency Allowance for an additional $25,000.
Acct. #09107100-5777-C0368”
VI. MISCELLANEOUS ITEM(S)
Prepared by Alan Lo
Dated: December 30, 2009
2