Norwalk Facilities Construction Commission July 7, 2010 Agenda (Final)
NORWALK FACILITIES CONSTRUCTION COMMISSION
WEDNESDAY, JULY 7, 2010
5:30 P.M. – CITY HALL Room #231
I. ROLL CALL
II. MINUTES OF PREVIOUS MEETING(S)
May 5, 2010
III. OLD BUSINESS
A. Roosevelt Center HVAC and window replacement project
1. Review and refer the following to the Common Council for action:
“Authorize the NFCC to issue Change Orders on Contract with Merritt
Contractors, Inc. for the Roosevelt Center HVAC and window replacement project
for an additional amount not to exceed$100,000.00. These funds will be set aside for
construction contingencies and balance to be used for energy conservation measures
including the replacement of existing single pane windows and the elimination of
window air conditioning units. Funds to be available from Special Capital
appropriation.”
IV. NEW BUSINESS
A. Proposed New Norwalk Fire Headquarters
1. Project update
2. Review recommendation to retain architectural firm for the proposed Norwalk Fire
Headquarters and refer the following to the Common Council for action:
“Authorize the Mayor, Richard A. Moccia, to execute an Agreement with (name of
consulting firm) to provide architectural design services for the proposed Norwalk
Fire Headquarters for a total not to exceed (amount to be determined). Acct. #
09113110-5777-C0466”
V. MISCELLANEOUS ITEM(S)
Prepared by Alan Lo
Dated: July 1, 2010
1