Water Pollution Control Authority
Regular MeetingNorwalk, CT · June 16, 2025
Minutes
CITY OF NORWALK
WATER POLLUTION CONTROL AUTHORITY VIA ZOOM VIRTUAL
VIDEOCONFERENCE AND TELECONFERENCE
REGULAR MEETING
June 16, 2025
Attendance: Darren Oustafine, Chairman
John Igneri, Vice Chairman
Chris Mannella
John Bove
James Frayer
Staff: Vanessa Valadares, Chief of Operations and Public Works
Ralph Kolb, WPCA Senior Environmental Engineer
Christine Pacelli, Wastewater Systems Manager
Mario Pizighelli, Stormwater Systems Manager
Others: Trever Steeprock, Project Manager, Veolia, Inc.
Ross Gambino, Asst. Project Manager, Veolia, Inc.
I. CALL TO ORDER
Mr. Oustafine called the meeting to order at 5:30 PM.
II. ROLL CALL
Mr. Oustafine called the roll; all those listed in attendance were present.
III. ACCEPTANCE OF MINUTES
A. REGULAR MEETING- MAY 19, 2025
** MR. IGNERI MOVED TO APPROVE THE MINUTES AS AMENDED.
** THE MOTION PASSED UNANIMOUSLY.
V. PUBLIC PARTICIPATION
There were no public comments this evening.
1
IV. NEW BUSINESS
A. ELECTION OF OFFICERS AND SECRETARY FROM JULY 1, 2025, TO JUNE 30,
2026.
** MR. MANNELLA MOVED TO NOMINATE THE CURRENT SLATE OF
OFFICERS AND SECRETARY.
*THE MOTION PASSED UNANIMOUSLY.
B. AUTHORIZE THE CHAIRMAN OR VICE CHAIRMAN OF THE WATER
POLLUTION CONTROL AUTHORITY TO EXECUTE AN AGREEMENT WITH
C.J. FUCCI, INC., IN THE AMOUNT OF $4,362,000.00 FOR THE BEACON
STREET SANITARY SEWER REPLACEMENT PROJECT (WPCA 2025-1),
(LETTER ATTACHED) ACCOUNT# 09254062-5777-C0361
Mr. Pizighelli said six bids were received for the project, and F.J. Fucci was the lowest responsible
bidder at 4.3 million dollars. He noted that they were significantly lower than the engineers’
estimate. He received feedback from other municipalities regarding recommendations and has not
received any negative feedback. It is the staff’s recommendation to move forward with F.J. Fucci
for this project.
Mr. Frayer asked if the engineer’s estimate is what is included in the budget. Mr. Kolb said, “Yes.”
** MR. IGNERI MOVED THE ITEM.
** THE MOTION PASSED WITH FOUR (4) IN FAVOR AND ONE ABSTENTION (MR.
MANELLA).
C. AUTHORIZE THE CHIEF OF OPERATIONS AND PUBLIC WORKS TO
EXECUTE ORDERS ON CONTRACT WITH C.J. FUCCI, INC. FOR THE
BEACON STREET SANITARY SEWER REPLACEMENT PROJECT (WPCA 2025--
1), FOR AN AMOUNT NOT TO EXCEED $ 436,200.00
ACCOUNT# 09254062-5777-C0361
Mr. Pizighelli said that this item is the typical 10% contingency for any change order monies that may be
required for this project.
** MR. FRAYER MOVED THE ITEM.
** THE MOTION PASSED WITH FOUR (4) IN FAVOR AND ONE ABSTENTION (MR.
MANELLA).
2
VII. OLD BUSINESS
A. Contract Operations Report
1. Veolia Monthly Operating Report- May 2025 (copy included)
Mr. Steeprock reported that the Veolia collections system team completed 0 miles of TV
inspection in May because Veolia has invested in a new CCTV computer for the camera
truck, which should be operational in about a week or so. He said 7.5 miles of sewer cleaning,
72 manhole inspections, 10.15 miles of SL Rat, responding to eight service calls, and
cleaning all four final settling tank launders and chlorine contact tanks were completed. The
IPP inspection program conducted 29 inspections.
Mr. Steeprock said the facility’s nitrogen performance for May was 638 pounds.
Mr. Steeprock said new sprayers were added to aeration tanks two and five in the recycle
pump zone to help keep the foam down, and a system was installed to clean the polymer
pump and piping, which has improved operations on the centrifuge.
Mr. Steeprock said the facility had another month of heavy rain without experiencing a wet
weather event.
Mr. Steeprock said all permit requirements were followed for May, and all required reports
were submitted to the CTDEEP and the EPA.
2. Nitrogen Performance (copy included)
Mr. Steeprock said there was a slight adjustment from what was reported last month. One of
the facilities in the program had a data entry error caught during auditing that affected the
trading credit price. The WPCA will now be awarded $33,720.
B. REPORTS:
1. FY 24/25 REVENUES/EXPENDITURES MUNIS REPORTS (COPY INCLUDED)
There was no discussion.
2. SAVE THE SOUND- 2025 LONG ISLAND SOUND BEACH REPORT SOUND
HEALTH EXPLORER (PARTIAL COPY INCLUDED)
LINK TO FULL REPORT: Https://soundhealthexplorer.org/swimmable
3
Ms. Pacelli said Save the Sound published their 2025 Long Island Sound Beach report and
said and was a fairly positive report for Norwalk beaches.
C. DISCUSSION ON WPCA ENGINEERING PROJECTS:
1. DISCUSSION OF SANITARY SEWER EXTENSION REQUEST ON BOUTON
STREET (PRESENTATION INCLUDED)
Mr. Kolb said at the May meeting that the WPCA board requested that staff revisit the cost
estimate range and present the revisions. He said the proposal was approximately 850’ of 8”
gravity main and having connections for the parcels to the right of way. He presented the
estimated costs and said two components include the sanitary sewer extension project within
the city right of way, and the second component is the private sewer lateral work that includes
the connection and permit fees, etc. The range is $15,000 to $25,000. The WPCA team
followed the CTDOT bid documents for a cost range and the engineers' estimate, and at a
conceptual level, the range was $600,000 to $975,000.
Mr. Frayer noted that the savings seem incredible from running the numbers using different
guidelines. Ms. Valadares said estimating without a concept design is difficult, but they are
considering an allowance for the unknowns.
The WPCA team asked the board for direction. Mr Oustafine said what he had heard from the
folks at the public hearing was that they were not interested with the price that was previously
presented and asked the board if more money should be spent to get a more accurate estimate
of the rock, which will be a major driver in the cost of any sewer project. Mr. Kolb clarified
that the estimate is per parcel and not the total cost, and the private sewer later is an
additional cost each parcel owner bears to connect. Ms. Valadares reminded the board that the
freeholder’s process is something they can decide to use, or that it can be done as a capital
improvement project to the collection system, and not charge the residents. Even if the board
decides to cover the cost of the major line, there will be some costs associated with each of
the properties when the connection is made. Mr. Frayer said he is concerned with the new,
much lower project cost and whether the project is approved. Once started, if it is discovered
that it would be more expensive, his concern is what the ceiling will be. Ms. Valadares said
that before designing the project, borings will be done to evaluate the soil, so there will be a
more realistic cost before the project is advertised. Mr. Frayer asked if the cost of the borings
is included in the engineering design phase. Ms. Valadares said, “Yes,” more than likely, and
sometimes, when a design is ready, grants may be available that can be applied for. Mr. Igneri
asked how many times there have been projects like this that were declared capital
improvement projects, where the residents have not been charged. Ms. Valadares said that in
the past 15 years, no projects have been done, and the existing sewer has been rehabilitated,
so there is no charge to the residents. Some developers or people have also been interested in
extending the sewer where they do the project, but the WPCA takes ownership if they follow
our guidelines.
Mr. Oustafine said if the board were to vote for a benefit appraisal, and if it were to be less
than $60,000. The board would be assured the assessment would not pay for the project
4
because we can’t charge above whatever that apparent benefit is to the people who live there,
but $60,000 to $100,000 for an apparent benefit to home is a lot and probable outside the
range on an evident benefit of having a sewer. If the WPCA board is not interested in funding
the sewer extension project out of the reserves, the project should not proceed. Still, if we
believe the benefit of having a sewer is great and the apparent benefit would likely be in that
range, we should probably vote to have a benefit appraisal done to see if it is viable. Mr.
Igneri asked if it is not a feasible project, and if an alternative can be offered to the residents
to help with the drainage issues from the school. Mr. Oustafine said that as the WPCA, he
does not think they can decide on storm sewers or drainage, and the only alternative would be
to choose to fund the project from the reserve account, which is not typically done because
rate payers in other areas will subsidize the sewer extension. Usually, the people in the project
area pay for a sewer extension.
Mr. Mannella asked if it gets to the point where the sewer is leaking into the road due to the
septic tanks failing, and there is no viable option to replace the septic, and no design in place,
if the house will be condemned. Mr. Kolb said in his discussions with the health department
that some modifications can be made to the septic system, but no improvements to the house
would be allowed.
Mr. Frayer asked, although not a WPCA issue, one of the residents pointed to the drainage
from the football field, causing the flooding in their yards, and wondered if there was any
credence to that. Ms. Valadares said there are a lot of issues on Bouton Street related to
drainage, not only related to the school, but to the road itself, but there is a physical restraint
because all of the watershed that drains under the tracks. A study was conducted a few years
ago, but has not been followed up on because improving the drainage in that area would be
extremely expensive to the city. To implement that drainage improvement, we need to secure
an easement so that the drainage issue in that area is not easy to resolve.
Mr. Mannella suggested that the staff move forward with getting 30% to 40% of the design
done to better handle the cost. Mr. Oustafine asked the staff if they knew how much it would
cost. Ms. Valadares said that the staff would get some proposals and present the cost to the
board.
2. HUBBELL’S LANE RELIEF SEWER
Ms. Pacelli said the Hubbell’s Lane sewer relief project is progressing to 100% design. Due
to a utility conflict, some redesign was needed for the intersection on East Avenue and East
Wall Street, so the product will now progress towards the final design.
3. FINAL SETTLING TANKS
Ms. Pacelli said the design of the final settling tanks is progressing toward 30%. We have a
workshop scheduled this week to discuss the development of the basis for the design report.
5
D. DISCUSSION ON WPCA CONSTRUCTION PROJECTS:
1. COLLECTION- SAMMIS AND BELL ISLAND SEWERSHED REHABILITATION
Mr. Kolb said Insituform has been working on manhole rehabilitations and lateral grouting at
the connections. Shortly after July 4th, crews will finish the CIPP lining. They are still on
schedule and anticipate all of the work to be completed by the end of September.
2. PS- OLD TROLLEY WAY SITE IMPROVEMENTS
Ms. Pacelli said the Old Trolley Way pump station site improvements were performed last
month, and the only portion of work that remains is the fencing, which should be completed
soon.
3. PS- FORT POINT IMPROVEMENTS
Ms. Pacelli said the WPCA team continues coordinating with the Walk Bridge team to discuss
the coordination efforts to begin the improvements at the Fort Point pump station, which is
scheduled to start in early fall.
VII. DISCUSSION
There was no discussion this evening.
VIII. ADJOURNMENT
** MR. IGNERI MOVED TO ADJOURN
** THE MOTION PASSED UNANIMOUSLY.
The meeting was adjourned at 6:14 PM.
Respectfully submitted,
Dilene Byrd
6
Agenda
REGULAR MEETING – WATER POLLUTION CONTROL AUTHORITY
AGENDA
JUNE 16, 2025, 5:30 PM
BY ZOOM VIRTUAL MEETING
To allow public access, anyone may access a meeting by telephone and/or Zoom, or a recording in the City of
Norwalk YouTube channel. Specific instructions and links can be found at norwalkct.gov/meetings.
Members of the public may call in to participate. Callers will not be able to see the meeting
participants. All participants will be muted upon entering the meeting. To speak, dial *9 on the phone
and you will be called on by the host of the meeting during the public comment section. All speakers
must state their name and address. Comments must be on a topic on the agenda, and are limited to
three minutes. Anyone disrupting the orderly conduct of the meeting, including by using threatening,
hateful, or sexually-explicit language, will be removed. Please find the information using the link
above.
Members of the public who wish to provide "live comments" may also use the Zoom meeting platform.
All participants will be muted upon entering the meeting. To speak, click the “raise your hand
indicator” and you will be called by the host of the meeting during the public comment section. All
speakers must state their name and address. Comments must be on a topic on the agenda, and are
limited to three minutes. Anyone disrupting the orderly conduct of the meeting, including by using
threatening, hateful, or sexually-explicit language, will be removed. Please find the information using
the link above.
Members of the public who wish to provide public comment are encouraged to submit those via email
in advance of the meeting. For these comments to be included into the record, they must be
submitted by 12:00 p.m. the day of the meeting. Please email Dilene Byrd at dbyrd@norwalkct.gov
with the subject line “Public Comment” to provide written public comment prior to the meeting.
I. CALL TO ORDER
II. ROLL CALL
III. ACCEPTANCE OF MINUTES
A. Regular Meeting: May 19, 2025
IV. PUBLIC PARTICIPATION
V. NEW BUSINESS
A. Election of Officers and Secretary the period between July 1, 2025, to June 30, 2026.
B. Authorize the Chairman or the Vice Chairman of the Water Pollution Control Authority
to execute an agreement with C.J. Fucci, Inc. in the amount of $4,362,000.00 for the
Beacon Street sanitary sewer replacement project (WPCA 2025-1), (letter attached)
Account# 09254062-5777-C0361
C. Authorize the Chief of Operations and Public Works to execute orders on contract
with C.J. Fucci, Inc. for the Beacon Street sanitary sewer replacement project (WPCA
2025-1) for an amount not to exceed $436,200.00
Account No. 09254062-5777-C0361
VI. OLD BUSINESS
A. Contract Operations Report:
1. Veolia Monthly Operating Report-May 2025 (copy included)
2. Nitrogen Performance 2024 (copy included)
B. Reports:
1. FY 24/25 Revenues/Expenditures MUNIS Reports (copy included)
2. Save the Sound – 2025 Long Island Sound Beach Report Sound Health Explorer
(partial copy included)
Link to full report: https://soundhealthexplorer.org/swimmable/
C. Discussion on WPCA Engineering Projects:
1. Discussion of sanitary sewer extension request on Bouton Street (presentation
included)
2. Hubbell's Lane Relief Sewer
3. Final Settling Tank
D. Discussion on WPCA Construction Projects:
1. Collection- Sammis and Bell Island Sewershed Rehabilitation
2. PS- Old Trolley Way Site Improvements
3. PS- Fort Point Improvements
VII. DISCUSSION
UPCOMING MEETINGS
VIII. ADJOURNMENT
Packet
REGULAR MEETING – WATER POLLUTION CONTROL AUTHORITY
AGENDA
JUNE 16, 2025, 5:30 PM
BY ZOOM VIRTUAL MEETING
To allow public access, anyone may access a meeting by telephone and/or Zoom, or a recording in the City of
Norwalk YouTube channel. Specific instructions and links can be found at norwalkct.gov/meetings.
Members of the public may call in to participate. Callers will not be able to see the meeting
participants. All participants will be muted upon entering the meeting. To speak, dial *9 on the phone
and you will be called on by the host of the meeting during the public comment section. All speakers
must state their name and address. Comments must be on a topic on the agenda, and are limited to
three minutes. Anyone disrupting the orderly conduct of the meeting, including by using threatening,
hateful, or sexually-explicit language, will be removed. Please find the information using the link
above.
Members of the public who wish to provide "live comments" may also use the Zoom meeting platform.
All participants will be muted upon entering the meeting. To speak, click the “raise your hand
indicator” and you will be called by the host of the meeting during the public comment section. All
speakers must state their name and address. Comments must be on a topic on the agenda, and are
limited to three minutes. Anyone disrupting the orderly conduct of the meeting, including by using
threatening, hateful, or sexually-explicit language, will be removed. Please find the information using
the link above.
Members of the public who wish to provide public comment are encouraged to submit those via email
in advance of the meeting. For these comments to be included into the record, they must be
submitted by 12:00 p.m. the day of the meeting. Please email Dilene Byrd at dbyrd@norwalkct.gov
with the subject line “Public Comment” to provide written public comment prior to the meeting.
I. CALL TO ORDER
II. ROLL CALL
III. ACCEPTANCE OF MINUTES
A. Regular Meeting: May 19, 2025
IV. PUBLIC PARTICIPATION
V. NEW BUSINESS
A. Election of Officers and Secretary the period between July 1, 2025, to June 30, 2026.
B. Authorize the Chairman or the Vice Chairman of the Water Pollution Control Authority
to execute an agreement with C.J. Fucci, Inc. in the amount of $4,362,000.00 for the
Beacon Street sanitary sewer replacement project (WPCA 2025-1), (letter attached)
Account# 09254062-5777-C0361
Page 1 of 34
C. Authorize the Chief of Operations and Public Works to execute orders on contract
with C.J. Fucci, Inc. for the Beacon Street sanitary sewer replacement project (WPCA
2025-1) for an amount not to exceed $436,200.00
Account No. 09254062-5777-C0361
VI. OLD BUSINESS
A. Contract Operations Report:
1. Veolia Monthly Operating Report-May 2025 (copy included)
2. Nitrogen Performance 2024 (copy included)
B. Reports:
1. FY 24/25 Revenues/Expenditures MUNIS Reports (copy included)
2. Save the Sound – 2025 Long Island Sound Beach Report Sound Health Explorer
(partial copy included)
Link to full report: https://soundhealthexplorer.org/swimmable/
C. Discussion on WPCA Engineering Projects:
1. Discussion of sanitary sewer extension request on Bouton Street (presentation
included)
2. Hubbell's Lane Relief Sewer
3. Final Settling Tank
D. Discussion on WPCA Construction Projects:
1. Collection- Sammis and Bell Island Sewershed Rehabilitation
2. PS- Old Trolley Way Site Improvements
3. PS- Fort Point Improvements
VII. DISCUSSION
UPCOMING MEETINGS
VIII. ADJOURNMENT
Page 2 of 34
CITY OF NORWALK
WATER POLLUTION CONTROL AUTHORITY VIA ZOOM VIRTUAL
VIDEOCONFERENCE AND TELECONFERENCE
REGULAR MEETING
May 19, 2025
Attendance: Darren Oustafine, Chairman
John Igneri, Vice Chairman
Chris Mannella
John Bove
Barbara Smyth
Heather Dunn
Staff: Ralph Kolb, WPCA Senior Environmental Engineer
Chris Torre, Superintendent, DPW
Christine Pacelli, Wastewater Systems Manager
Mario Pizighelli, Stormwater Systems Manager
Wilber Giron, DPW Permit Engineer
Others: Trever Steeprock, Project Manager, Veolia, Inc.
Ross Gambino, Asst. Project Manager, Veolia, Inc.
Regina Flaherty, Verrill Law
I. CALL TO ORDER
Mr. Oustafine called the meeting to order at 5:30 PM.
II. ROLL CALL
Mr. Oustafine called the roll; all those listed in attendance were present.
III. PUBLIC HEARING
A. PROPOSED SANITARY SEWER EXTENSION- 2 MULLER AVENUE, NORWALK, CT.
(DRAWING AND NOTICE INCLUDED)
Mr. Oustafine opened the public hearing at 5:31 PM.
Nick Wendle
Mr. Wendle said he is speaking on behalf of Shawn’s Lawns regarding the application to
tie into the sewer from their property located on 2 Muller Avenue. This is per the
conditions for their special use permit; they have begun some of the work inside the
1
Page 3 of 34
property line and are now at the point where they will need to tie into the sewer,
including adding two manholes and connecting to the sewer on Pulaski Street.
B. SANITARY SEWER EXTENSION REQUEST ON BOUTON ST., NORWALK, CT.
(NOTICE INCLUDED)
Santos Martinez- 184 Bouton Street
Mr. Martinez said the stretch of road at the end of Bouton Street had been left on septic,
and it is here to petition to extend the sewer to the end of the street. The septic systems
are old, and there is an issue with the water table being high in the area. The water
comes from Brien McMahon High School, and he does not think the storm drainage is
working correctly. He said they had hired an engineer to assess the issue and
recommended the sewer extension, which would benefit the homeowner and the city
because they could add or modify the houses on the properties. He said the last house on
the street is struggling because it is located next to a swamp, which has seen more water
flow recently, and water is a big issue for all of them. He read the following from the
licensed engineer who performed the study:
As a licensed engineer, it is his responsibility to help the public. This office highly
recommends helping the residents on Bouton Street, as this is a health-related issue.
Therefore, he believes the sewer extension would help the residents and the city.
Sean Rosa- 178 Bouton Street
Mr. Rosa said he has lived at 178 Bouton Street for a couple of decades and said it
wasn’t that bad 20 years ago, but when the field was redone at Brien McMahon High
School, it has consistently been getting worse over the past 12 years. He said it is bad
for his neighbor at 122 Bouton Street, and she has a river. Not having a sewer system is
hurting the area.
Silvia Perez- 188 Bouton Street
Ms. Perez said she lives in the last house on the street and has a big problem because of
a swamp. It is very bad in the winter because of ice, and it is also bad in the summer.
Because of the septic tanks, there are a lot of mosquitoes, and they would like to sit
outside, but the odor is very bad.
Mr. Oustafine closed the public hearing at 5:42 PM.
2
Page 4 of 34
IV. ACCEPTANCE OF MINUTES
A. REGULAR MEETING- APRIL 21, 2025
** MR. IGNERI MOVED TO APPROVE THE MINUTES AS SUBMITTED.
** THE MOTION PASSED UNANIMOUSLY.
V. PUBLIC PARTICIPATION
There were no public comments this evening.
V. NEW BUSINESS
A. APPROVE THE PROPOSED SANITARY SEWER EXTENSION AT 2 MULLER
AVENUE. THROUGH TECHNICAL ANALYSIS, IT WAS CONFIRMED THAT
THE CITY’S SANITARY SEWER COLLECTION SYSTEM AND
WASTEWATER TREATMENT PLANT CAN ACCOMMODATE THE
ADDITIONAL SANITARY SEWER FLOW GENERATED FROM THE
PROPOSED CONNECTIONS. THE PROPOSED SANITARY SEWER
EXTENSION SHALL BE CONSTRUCTED IN ACCORDANCE WITH DPW AND
WPCA SANITARY SEWER PERMIT PROCESS AND SANITARY SEWER MAIN
EXTENSION POLICY (ADOPTED JULY 7, 2021) AND BE REFERRED BACK
TO THE WPCA BOARD FOR FINAL ACCEPTANCE (DRAWING ATTACHED)
Mr. Giron said this item related to the first public hearing we heard this evening. Staff have
nothing new to add but are happy to entertain any questions the board may have.
Ms. Smyth thanked Ms. Dunn for her memory and pointed out that Shawn’s Lawn was removed
from the bid process for the South Norwalk School last February due to the unsolved zoning and
conservation commission violations. She has concerns about this and would like to be assured
that the zoning and conservation violations have been rectified, or if the applicant has
information that this would not be an issue for this project.
Mr. Wendle said this is part of that problem, and as part of the special use permit, they have to tie
into the sewer, because all of the issues put forth on the plan at the time were not satisfied, so
they were rejected. He provided background and said this parcel was approved for a construction
yard through eminent domain; however, they could not get a mortgage due to prior
contamination. They bought the property, and these conditions existed. They have been trying to
3
Page 5 of 34
get through the process, and he has been working with Mr. Giron and Ms. Cherichetti, and they
have been very helpful.
Ms. Smyth said that if this is approved this evening, it will go to the Planning and Zoning
Commission, which has been following along with their problems and moving through this to
rectify them. Mr. Wendle said that he believes they are aware of it, as they require the property to
be tied into the sewer. Mr. Giron noted that the Planning and Zoning had notified DPW of this
outstanding violation, and to comply, they must connect to the sanitary sewer.
Mr. Oustafine asked whether the applicant would be responsible for installing their own laterals.
Mr. Giron said it is correct, and through the WPCA permit process, the applicant would install
the sanitary sewer on their property. Through the DPW permit process, they would extend the
main and make the connection at the main. Mr. Oustafine asked if Shawn’s Lawn would be
responsible for paying for the entire sewer extension. Mr. Giron said, “Yes,” that is correct, and
the intent is for Shawn’s Lawn to donate the sewer main infrastructure to the city to be accepted
once it has been installed, inspected, and confirmed that it meets our requirements. Mr. Oustafine
asked if there was a written agreement. Mr. Giron said that information is spelled out in the
sewer extension policy, and that is what has been followed through this process. Mr. Oustafine
asked if a bond would be required. Mr. Giron said, “Yes.” Should the Common Council approve
this, the work will be performed under the permit process, where a bond is equivalent to the
construction cost, so the city is secured.
Mr. Oustafine said to review that there is capacity in the line and the sewer system, which will
not cost the WPCA or the rate payers of Norwalk. The developer-contractor and/or property
owner will bear all costs, and the road will be returned to DPW standards. Mr. Giron said, “Yes,”
that is correct, and as a requirement of the permit process, they are required to backfill with a
temporary trench, and DPW bills the restoration and performs the final restoration through the
road restoration contract. Mr. Oustafine asked who would be inspecting the work. Mr. Giron said
the DPW permit staff will have an inspector on site to confirm the sewer extension is installed
correctly, and the applicant will test the main, but DPW staff will be present when testing.
** MR. FRAYER MOVED TO APPROVE ITEM.
*THE MOTION PASSED UNANIMOUSLY.
B. REFERRAL OF ITEM A. TO PLANNING COMMISSION FOR REPORT AND
RECOMMEND ACTION PURSUANT TO CONN. GEN. STAT. 8-24
** MR. FRAYER MOVED TO APPROVE ITEM.
*THE MOTION PASSED UNANIMOUSLY.
C. REFERRAL OF ITEM A. TO PUBLIC WORKS COMMITTEE OF THE
COMMON COUNCIL FOR APPROVAL FOR THE PROPOSED SANITARY
SEWER EXTENSION.
4
Page 6 of 34
** MR. FRAYER MOVED TO APPROVE ITEM.
*THE MOTION PASSED UNANIMOUSLY.
D. AUTHORIZE THE CHIEF OF OPERATIONS AND PUBLIC WORKS TO
EXECUTE ORDER ON CONTRACT WITH INSITUFORM TECHNOLOGIES,
LLC. FOR THE SANITARY SEWER REHABILITATION PROJECT (PROJECT:
WPCA: 2023-01) FOR AN AMOUNT NOT TO EXCEED $300,000
ACCOUNT NO. 09244062-5777-C0361
Mr. Kolb reviewed the breakdown of what the $300,000 will cover and said the project's
total cost is approximately six million dollars. He anticipates the project closing out at the
end of September.
** MR. FRAYER MOVED TO APPROVE ITEM.
** THE MOTION PASSED UNANIMOUSLY.
VII. OLD BUSINESS
A. Contract Operations Report
1. Veolia Monthly Operating Report- April 2025 (copy included)
Mr. Steeprock reported that in April, the Veolia collections system team completed 2.40 miles
of TV inspection, 4.50 miles of sewer cleaning, 43 manhole inspections, 2.95 miles of SL
Rat, responded to 20 service calls, and cleaned all four final settling tank launders and both
chlorine contact tanks. The IPP inspection program conducted 28 inspections.
Mr. Steeprock said new pipes and sprayers were installed in the anoxic zone of aerating tank
#3 to minimize scum build-up.
Mr. Steeprock noted that Norwalk experienced moderate-heavy rain of over 2” without the
storm outfall activating. The wastewater treatment plant and the collections system performed
very well, with a good recovery time in the collections system, which they could monitor
through the smart covers. All the lining that has been done seems to be making an impact.
Mr. Steeprock said the nitrogen performance for April was 587 pounds per day.
Mr. Steeprock said all permit requirements were followed for April, and all required reports
were submitted to the CTDEEP and the EPA.
2. Draft 2024 Nitrogen Credit Exchange Buyers and Sellers (copy included)
5
Page 7 of 34
Mr. Steeprock said that Norwalk came in at an average of 680 pounds per day/month, putting
Norwalk 15th in the state. This is worse than in previous years due to the transition of staff
and management over the past year and the wet weather. However, it is still a good result, and
the commission will receive an estimated $33,685 when it buys the credits. This year, they
are trending significantly lower than the beginning of last year.
3. Major Repair or Replacement/ Out of Scope Items:
a. Pump Station Electric Wiring- SCADA (copy included)
Mr. Steeprock said the additional wiring is a project they are doing with the WPCA. The
intent is to install current monitoring and wiring for eight pump stations, which will give
additional information back to SCADA and can be used for troubleshooting and energy
consumption monitoring. The project has been approved and should begin next week.
B. REPORTS:
FY 24/25 REVENUES/EXPENDITURES MUNIS REPORTS (COPY INCLUDED)
There was no discussion.
C. DISCUSSION ON WPCA ENGINEERING PROJECTS:
1. DISCUSSION OF SANITARY SEWER EXTENSION REQUEST ON BOUTON
STREET (PRESENTATION INCLUDED)
Mr. Kolb said that, as discussed in the public hearing earlier this evening, various property
owners on Bouton Street approached the WPCA to request a sanitary sewer extension. He
presented an overview of the request and the residents' concerns. The original extension
scope in 2021 was approximately 330’, and the new request would be approximately 850’ of
8” gravity main sewer along with four manholes and 10 sewer laterals.
Mr. Kolb presented the location map and proposed sanitary sewer extension request. The
WPCA team estimated the project to be between 1.6 million and 2.4 million dollars,
depending on the unknowns based on site conditions, current bids for comparable estimates,
and total construction.
Ms. Flaherty discussed the process required to assess the benefits of new sewer lines.
Mr. Kolb shared the WPCA future capital projects that were submitted to the CT DEEP as
part of the Consent Order, the Collection System Master Plan, and Facility Plan, which will
need to be committed to once the CT DEEP comes back to the WPCA and plans for which
the 5-year and 10-year clock begins. Staff are looking for direction from the board on how to
proceed.
6
Page 8 of 34
Ms. Dunn said there were current issues regarding blight in the area and asked which
property. Mr. Martinez said that it is in every vacant lot. Ms. Dunn suggested some city
insights into the area may be helpful. Mr. Frayer asked if this had been reported to the blight
officer. Mr. Martinez said he has contacted the city’s customer service many times over the
years, and DPW has cleaned the area numerous times.
Mr. Oustafine asked who would be responsible for paying for the sewer extension as it is
difficult for him to imagine how one of the properties would be benefited by $240,000 so he
does not see how the WPCA could support this except if the residents are willing to absorb
that cost, which is a lot of money. Mr. Martinez said they did not imagine it would cost that
much, which does not include the cost to connect each of the properties. Mr. Oustafine said
he knows the benefit of a sewer and the issues related to older septic systems and inundation
with drainage, and suggested that the money may be better spent solving the drainage
problem, if there is one, but he doesn’t see a road forward due to the cost. Mr. Oustafine
asked if city staff determined the cost estimate. Mr. Kolb said “Yes” and devised the cost
estimate using recent bids for DPW/WPCA projects.
Mr. Mannella asked if there is city water in the area. Mr. Martinez said, “Yes.”
Mr. Frayer said if this is the only approach and this is the cost, he would have to say “No”
because the city can’t afford to start installing these types of installations.
Mr. Oustafine suggested that the board's direction to staff is to try to reduce the project's cost,
with some of the alternatives that have been discussed.
2. BEACON STREET SANITARY SEWER
Mr. Pizighelli said the Beacon Street sanitary sewer project was recently put out to bid, and
there will be a bid opening on June 11, 2025. The timetable for construction will be
approximately 365 working days.
3. HUBBELL’S LANE RELIEF SEWER
Ms. Pacelli said the Hubbell’s Lane sewer relief project is progressing to 90% design and will
meet this week to discuss the East Wall Street and East Avenue intersection, which needs to
be redesigned due to some utility issues.
4. FINAL SETTLING TANKS
Ms. Pacelli said the design of the final settling tanks is progressing toward a 10% to 30%
design.
D. DISCUSSION ON WPCA CONSTRUCTION PROJECTS:
1. COLLECTION- SAMMIS AND BELL ISLAND SEWERSHED REHABILITATION
7
Page 9 of 34
Mr. Kolb said much progress has been made with the Sammis and Bell Island sewershed
rehabilitation project. The total project is just over 70,000 linear feet of pipe at various sizes,
ranging from 8” to 24”, and almost 65,000 linear feet have been completed, so we are at 92%
complete. Insituform is currently doing manhole rehabilitation and later grounding, which is
approximately 44% of those items, and as mentioned earlier, the project should be completed
by September 30, 2025.
2. PS- OLD TROLLEY WAY SITE IMPROVEMENTS
Ms. Pacelli said the Old Trolley Way pump station site improvement has begun, and all
permits have been submitted and approved.
3. PS- FORT POINT IMPROVEMENTS
Ms. Pacelli said the WPCA team has been coordinating with the Walk Bridge team to discuss
the coordination efforts to begin the improvements at the Fort Point pump station.
4. SEWER USE APPEALS/ADJUSTMENTS UPDATE
Ms. Pacelli said the sewer use appeals/adjustments to date are $82,724.
VIII. DISCUSSION
There was no discussion this evening.
IX. ADJOURNMENT
** MR. BOVE MOVED TO ADJOURN
** THE MOTION PASSED UNANIMOUSLY.
The meeting was adjourned at 6:53 PM.
Respectfully submitted,
Dilene Byrd
8
Page 10 of 34
Norwalk Water Pollution Control Authority
Monthly Operating Report
May 2025
1
Page 11 of 34
Norwalk Water Pollution Control Authority Monthly Operating Report –May 2025
EXECUTIVE SUMMARY
May Highlights
● The Veolia collections system team completed 0.0 miles of TV inspection, 7.15 miles of sewer
cleaning was completed, 72 Manhole Inspections, and 10.15 miles of SL Rat.
● Veolia responded to 8 service calls.
● Veolia cleaned all four Final tank launders and both Chlorine contact tanks.
● The IPP inspection program conducted 29 inspections.
● The facility’s Nitrogen Performance for May was 638 lbs.
● There were new sprayers added to Aeration tanks 2 & 5 in the recycle pump zone.
● Installed a system to clean the polymer pump and piping.
● The facility had another month of heavy rain without experiencing a wet weather event.
Regulatory Events
The Water Pollution Control Facility followed all permit requirements for the month of
May.
The netDMR, MOR, NAR, and Bi-Monthly sludge reports were submitted to CT-DEEP and EPA in
May.
2
Page 12 of 34
Norwalk Water Pollution Control Authority Monthly Operating Report –May 2025
EXECUTIVE SUMMARY - Key Operational Parameters`
Parameter Units May CYTD Result Contract Limit
Result
Average Daily Flow MGD 12.8 n/a n/a
180 Day Average Daily Flow MGD 12.02 n/a n/a
Effluent BOD mg/l 4.3 n/a 10
Effluent TSS mg/l 5.8 n/a 10
Effluent Fecal Coliform # / 100 ml 4 n/a 10
Effluent Enterococci # / 100 ml 11 n/a 30
Effluent Total Chlorine mg/l 0.01 n/a 0.07
Effluent Total Nitrogen lbs/day 638 n/a 1,000
Biosolids Quality (cake) % solids 30 n/a n/a
Biosolids Disposal (cake) DT/month 281 n/a n/a
Biosolids Disposal (liq) DT/month 23 n/a n/a
Biosolids Disposal (total) DT/month 304 n/a n/a
Grit and Screenings WT/month 6 n/a n/a
Chemicals – Hypochlorite gal/month 6634 n/a n/a
Chemicals – Bisulfite gal/month 6283 n/a n/a
Chemicals – Polymer gal/month 575 n/a n/a
Chemicals – Odor Control gal/month 0 n/a n/a
Sewer Cleaning Miles 7.15 31.98 3 miles (avg)
CCTV Inspection Miles 0 14.0 2 miles (avg)
Odor Complaints # 0 n/a 0
SL-RAT Inspection Miles 10.15 62.57 60 months
Manhole Inspections # 72 406 50/m
IPP Inspections # 29 353 Approx. 500/year
3
Page 13 of 34
Norwalk Water Pollution Control Authority Monthly Operating Report –May 2025
EXECUTIVE SUMMARY - Influent Flow
Influent Flow
20.00
18.00
16.00
14.00
12.00
MGD
10.00
8.00
6.00
4.00
2.00
0.00
May-21
Jul-21 Sep-21 Nov-21 Jan-22 Mar-22 May-22
Jul-22 Sep-22 Nov-22 Jan-23 Mar-23 May-23
Jul-23 Sep-23 Nov-23 Jan-24 Mar-24 May-24
Jul-24 Sep-24 Nov-24 Jan-25 Mar-25 May-25
180 Day MA Flow Design Flow 90% Design Flow Linear (180 Day MA Flow)
4
Page 14 of 34
Page 15 of 34
Page 16 of 34
Page 17 of 34
Page 18 of 34
Page 19 of 34
Nitrogen Credit Exchange Program
FINAL Credit Exchange Invoice for CY 2024
NORWALK WPCF NPDES Permit # CT0101249
End-of-Pipe TN Credit Exchange Calculation
Discharged (lbs/day)
January 998 Permit Limit lbs./day 718
February 801 Annual Avg lbs./day 680
March 939 E-Factor 1
April 758 Credits eq.lbs./day -38
May 719 Cost/Credits $2.4245289
June 587 Annual Invoice -$33,720
July 583
August 612
September 593
October 485
November 455
December 624
Annual Avg 680
If the Water Pollution Control Facility
discharged more nitrogen than required by
its Nitrogen General permit, the Exchange
Program will require payment.
Please send payment to:
Electronic deposit in financial institution The Commissioner will purchase
ACH instructions:
($33,720)
Bank of America
Routing Number: 011900254
Account Name: State of CT Regular Account
Or if by check:
Please Make Checks Payable to:
Office of the State Treasurer
165 Capitol Ave - 2nd Floor
Hartford, CT 06106
Attn: Renae Earlington
Page 20 of 34
Page 21 of 34
Table 3
FINAL 2024 Nitrogen Credit Exchange Buyers and Sellers
Selling Credits Buying Credits
Plant Name Equalized Cost Eq.Lbs Plant Name Equalized Cost Eq.lbs
Credits Credit at Credits Credit at $5.3
$2.4245289
STAMFORD WPCF 608.00 $539,526 BRIDGEPORT WEST WPCF 212.50 $412,208
MERIDEN WPCF 143.57 $127,401 WALLINGFORD WPCF 159.60 $309,592
WATERBURY WPCF 135.00 $119,796 NORWICH WPCF 87.84 $170,392
TORRINGTON WCPF 109.20 $96,902 SHELTON WPCF 75.04 $145,563
BRIDGEPORT EAST WPCF 97.75 $86,741 HARTFORD 71.40 $138,502
STRATFORD WPCF 83.08 $73,723 WINDSOR POQUONOCK WPCF 68.02 $131,945
MILFORD HOUSATONIC WPCF 69.01 $61,238 BRISTOL WPCF 33.30 $64,595
BRANFORD WPCF 56.40 $50,048 EAST HARTFORD WPCF 26.60 $51,599
SOUTHINGTON WPCF 49.49 $43,916 EAST HAMPTON WPCF 19.00 $36,856
ANSONIA WPCF 46.90 $41,618 BEACON FALLS WPCF 18.76 $36,391
DANBURY WPCF 45.54 $40,411 PLYMOUTH WPCF 17.10 $33,171
NEW HAVEN WPCF 44.40 $39,400 FAIRFIELD WPCF 17.00 $32,977
NEW CANAAN WPCF 42.00 $37,270 RIDGEFIELD SOUTH WPCF 8.00 $15,518
WESTPORT WPCF 38.25 $33,942 NAUGATUCK WPCF 7.20 $13,967
NORWALK WPCF 38.00 $33,720 CANTON WPCF 5.94 $11,522
NORTH HAVEN WPCF 34.20 $30,348 SALISBURY WPCF 5.60 $10,863
MANCHESTER WPCF 25.65 $22,761 NORTH CANAAN WPCF 5.60 $10,863
MATTABASSETT WPCF 23.60 $20,942 THOMPSON WPCF 4.90 $9,505
ENFIELD WPCF 22.42 $19,895 JEWETT CITY WPCF 3.57 $6,925
GREENWICH WPCF 22.00 $19,522 WINSTED WPCF 2.70 $5,237
WEST HAVEN WPCF 21.00 $18,635 PLAINFIELD NORTH 2.52 $4,888
MILFORD BEAVER BROOK WPCF 15.41 $13,674 SEYMOUR WPCF 2.01 $3,899
NEWTOWN WPCF 14.26 $12,654 PORTLAND WPCF 1.80 $3,492
SIMSBURY WPCF 11.52 $10,223 SPRAGUE WPCF 1.60 $3,104
NEW LONDON WPCF 9.72 $8,625 DERBY WPCF 1.34 $2,599
ROCKY HILL WPCF 9.60 $8,519 SOUTH WINDSOR WPCF 1.33 $2,580
WINDHAM WPCF 8.10 $7,188 KILLINGLY WPCF 0.98 $1,901
FARMINGTON WPCF 7.92 $7,028 STONINGTON BOROUGH 0.18 $349
VERNON WPCF 7.22 $6,407 STAFFORD SPRINGS WPCF 0.00 $0
GROTON TOWN WPCF 5.40 $4,792 NEW MILFORD WPCF 0.00 $0
SUFFIELD WPCF 4.94 $4,384 Total 861.43 $1,671,003
THOMASTON WPCF 4.80 $4,259
EAST WINDSOR WPCF 3.80 $3,372
GLASTONBURY WPCF 3.60 $3,195
The Self-Sufficient Program was approved
PUTNAM WPCF 3.22 $2,857
under Public Act 15-38 in 2016. The
PLAINVILLE WPCF 3.06 $2,715 program consists of the buyers purchasing
LICHFIELD WPCF 2.45 $2,174 the credits
(861.43 equalized at $5.3) they need to meet
MONTVILLE 2.34 $2,076
their General Permit with those payments
UCONN WPCF 2.10 $1,863
($1,671,003) being shared amongst the
CHESHIRE WPCF 1.96 $1,739
sellers (1,883.08 equalized at $(1,671,002)
WINDSOR LOCKS WPCF 1.52 $1,349 proportionally. There will be no State
PLAINFIELD VILLAGE WPCF 1.12 $994 purchase of excess credits. The 2024 year
NORFOLK 1.05 $932 data is traded in 2025.
GROTON CITY WPCF 0.90 $799
STONINGTON MYSTIC WPCF 0.90 $799 If the Water PollutionControl Facility
LEDYARD WPCF 0.54 $479 dischared more nitrogen than required by its
STONINGTON PAWCATUCK 0.17 $151 Nitrogen General Permit, the Nitrogen
WPCF Exchange Program will require payment by
1883.08 $1,671,002
July 31, 2025.
Bold = Project Facilities (is defined The Comissioner will purchase credits by
as any facility with a fully August 15, 2025.
operational nitrogen removal
system of any scale as of January 1st
of the trading year).
Page 22 of 34
2 025
LONG ISLAND SOUND
B E ACH
R E P OR T
BASED ON DATA FROM 2022-2024
Glen Island Park
New Rochelle, New York
Page 23 of 34
CHA LLE N G E :
S TO R M W AT ER R U N O FF
Densely populated areas. Leaky old wastewater systems. Impervious
surfaces. Weather that’s getting increasingly wetter. For water quality around
Long Island Sound, those factors add up to a perfect storm of challenges.
Throughout this Beach Report, we frame how concerning a problem fecal
indicator bacteria pollution can be in our region. Focusing on how contaminants
get into the water at our swimming beaches is critically important—in part
because it’s one of the areas where the most progress can be made.
Picture what happens in your neighborhood when it rains. Some of it gets
absorbed into the ground, but that’s only if it finds a permeable surface. The
more developed the area, the more likely precipitation will come down on roofs
and sidewalks, parking lots and roadways, hardened surfaces that rain cannot
penetrate. Instead, it runs off these impervious surfaces in torrents toward
storm drains that discharge into nearby waterways or it flows straight into the
Sound. Whatever it picks up along the way gets carried off to the coastline to
make water quality worse.
Volunteers installing a rain garden — New Haven, Connecticut
There’s the usual toxic mix of fertilizers and pesticides, fuel and oil that’s
spilled on the road, plastic trash, and other pollutants. But stormwater runoff
can also pick up pet waste that hasn’t been disposed of properly or waste from
wildlife (sometimes on the ground, sometimes in catch basins and stormwater
pipes themselves where raccoons and rodents can make their homes). Too often,
it gets into sewer pipes and aging septic systems, mixing with wastewater and
flooding the system. Or the increased volume of stormwater and wastewater
becomes too much for a combined sewer system to handle, and it discharges
raw sewage combined with stormwater into waterways—like the Sound and its
tributaries—before it can get decontaminated at a treatment plant.
14 ©2025 SAVE THE SOUND — LONG ISLAND SOUND BEACH REPORT
Page 24 of 34
The more it rains, the more this parade of pollutants threatens the water
at our beaches. And it’s raining more. We’re coming off the wettest two-year
stretch (40 total inches) and the wettest five-year span (91 inches) around Long
Island Sound dating back at least to 2003.
Mitigating impacts of stormwater is central to our work, whether we’re
lobbying in Albany for stronger stormwater management policies or partnering
with the Town of Groton and Groton Municipal TV on “Clean Water Ways,” a
video series creating awareness of non-point source pollution—a mix of pollution
types typically delivered via stormwater runoff.
We also have continued to emphasize the use of green infrastructure
wherever possible to filter stormwater before it reaches our waterways. There
was the restoration project at Sunken Meadow State Park in 2019 where we
retrofitted a 16.6-acre parking lot with bioswales and constructed wetlands,
creating a system that filters four million gallons of stormwater a year on its
way from a parking lot to Sunken Meadow Creek and, eventually, the Sound and
one of Long Island’s most popular beaches. More recently, we helped create
a 40,000-square foot rain garden at Town Center Park in Hamden, installing
more than 400 plants to help absorb 96 million gallons of stormwater every
year before it reaches the Mill River (and, again, ultimately the Sound). In 2024,
145 volunteers helped us install 17 rain gardens in Hamden and New Haven. And
in 2025, we’ll be working with students from the Port Chester Youth Bureau to
build one at William James Memorial Gateway Park, filtering runoff bound for
the Byram River.
Communities around the Sound are seeing how investing in green
infrastructure benefits hyperlocal water quality. As part of a recent renovation
at Calf Pasture Beach, the City of Norwalk installed 3,000 square feet of
permeable pavement, several bioretention areas, and native plants to absorb,
hold, and filter stormwater. The early returns are promising. Calf Pasture Beach
received an A+ grade in 2024 and was one of five Connecticut beaches west of
Guilford to get an A+.
B ET T E R I N F O R MATION
B E TTER D ECI S I O NS
Perhaps the most important tool in our mission to protect water quality around the Long
Island Sound region is information. It is the critical piece to our data-to-understanding-
to-action approach for addressing the challenges to clean water we face and finding
appropriate solutions.
The 2025 Long Island Sound Beach Report is one source for the kind of data that
leads to such understanding. But there’s always more to know. For example, you could
visit www.SoundHealthExplorer.org/swimmable/ to take a deeper dive into years’ worth
of data behind the Beach Grades.
In February, we introduced another important information source: QuickDrops, the
first online database tool of its kind designed to collect, manage, and broadly share
water quality data specific to the Long Island Sound watershed. QuickDrops not only
benefits community science groups, health departments, and beach and water resource
managers; it provides access to user-friendly data visualization tools that will help
researchers, educators, news media, and municipal leaders sort and share information in
more effective ways.
Visit www.QuickDrops.org to explore all it offers. If your organization is interested in
becoming a contributor, please email us at support@quickdrops.org.
©2025 SAVE THE SOUND — LONG ISLAND SOUND BEACH REPORT 15
Page 25 of 34
Ne
Connecticut
Wes
Gree
walk
wY
tpor
nwic Stam t
Port o rk
No r
h ford D a ri
Che en 60
ster
55
57 56
61 58
72 59
68 66 62
69 67 65
63
70
64
73 71
20 ©2025 SAVE THE SOUND — LONG ISLAND SOUND BEACH REPORT
Page 26 of 34
Wes
rt
Brid t Ha
rd
Connecticut
gep ven
Milfo
o
Fair ord
field
39
42
49 Stra 43 41 40
tf
54 50 44
53 48
51
52
45
47
46
©2025 SAVE THE SOUND — LONG ISLAND SOUND BEACH REPORT 21
Page 27 of 34
Page 28 of 34
Page 29 of 34
WPCA Meeting
June 16, 2025
Bouton Street Sanitary Sewer Extension Request
Page 30 of 34
Location Map
Project Area
Page 31 of 34
Sanitary Sewer Extension
Legend
Approved Proposed
Existing
Private Main (not
Sanitary
constructed)
Sewer
176 - 174
Approved Proposed
Private Manhole
(not constructed)
Requested New
Gravity Main
Requested New
Sewer Lateral
Requested New
Manhole
Page 32 of 34
Estimated Costs:
Sanitary Sewer Extension Project (within City ROW):
Description Cost Range
Engineering Design/Bidding Services $75,000 - $100,000
Construction $525,000 - $875,000
Total Sanitary Sewer Extension Cost Estimate: $600,000 - $975,000
Private Sewer Lateral:
Description Cost Range
Private Sewer Lateral / Connection Cost Estimate: $15,000 - $25,000
Page 33 of 34
Next Steps
• WPCA Board Direction
Page 34 of 34