Water Pollution Control Authority
Regular MeetingNorwalk, CT · July 21, 2025
Minutes
CITY OF NORWALK
WATER POLLUTION CONTROL AUTHORITY VIA ZOOM VIRTUAL
VIDEOCONFERENCE AND TELECONFERENCE
REGULAR MEETING
July 21, 2025
Attendance: Darren Oustafine, Chairman; John Igneri, Vice Chairman; Chris Mannella;
John Bove; James Frayer
Staff: Vanessa Valadares, Chief of Operations and Public Works; Christine Pacelli,
Wastewater Systems Manager; Mario Pizighelli, Stormwater Systems Manager
Others: Trever Steeprock, Project Manager, Veolia, Inc. Ross Gambino,
Asst. Project Manager, Veolia, Inc.
I. CALL TO ORDER
Mr. Oustafine called the meeting to order at 5:30 PM.
II. ROLL CALL
Mr. Oustafine called the roll; all those listed in attendance were present.
III. ACCEPTANCE OF MINUTES
A. REGULAR MEETING- JUNE 16, 2025
** MR. BOVE MOVED TO APPROVE THE MINUTES AS SUBMITTED.
** THE MOTION PASSED UNANIMOUSLY.
IV. PUBLIC PARTICIPATION
There were no public comments this evening.
V. OLD BUSINESS
A. Contract Operations Report
1
1. Veolia Monthly Operating Report-June 2025 (copy included)
Mr. Steeprock reported that the Veolia collections system team completed 0.57 miles of TV
inspection in June, which is expected to increase with the new camera and computer setup.
Additionally, the team performed 6.20 miles of sewer cleaning, 140 manhole inspections, 7.7
miles of SL Rat, and responded to six service calls. They also installed new level monitoring
in both the bisulfite storage tanks. The IPP inspection program conducted 32 inspections.
Mr. Steeprock said the facility’s nitrogen performance for June was 566 pounds.
Mr. Steeprock stated that they have repaired primary tank #4 by removing concrete and other
debris from the cross collector. Additionally, the fencing and paving at the Old Trolley Way
pump station are now complete. They are now working on the grass cutting that they are
responsible for this week.
Mr. Steeprock noted that a heavy rain event occurred last week, and the wastewater treatment
plant experienced approximately an inch and a half of rain, but was able to sustain it without
going into stormflow.
Mr. Steeprock stated that all permit requirements were met for June, and all required reports
were submitted to the CT DEEP and the EPA. The quarterly report was sent to Synagro. He
said they are working with the Norwalk team on the permit renewal application for the
discharge permit, which is due in late September.
2. Contract Year 6- Inflation Adjustment (letters included)
Mr. Steeprock stated that, according to the contract, the inflation rate is based on a weighted
average of several metrics, primarily the CPI, and this year resulted in a 3.3% increase.
B. REPORTS:
1. FY 24/25 REVENUES/EXPENDITURES MUNIS REPORTS (COPY INCLUDED)
There was no discussion.
2. CONSENT ORDER-2025 ANNUAL PROGRESS REPORT (COPY INCLUDED)
Ms. Pacelli said on June 26th, the WPCA submitted the 2025 annual progress report to the
DEEP. The report highlighted that the WPCA had made substantial progress towards meeting
the goals outlined in the Collection System Master Plan. The highlights included the ongoing
implementation of the cured-in-place piping in low-lying and coastal areas. By the end of this
September, over 70,000 linear feet of pipe will be lined upon completion of the project.
Continued efforts to reduce the inflow and infiltration, and have disconnected seven catch
basins since last year's report, and launched a design task order with Tighe and Bond to
2
separate five more in the Bettswood Road and Walnut Road area. The WPCA has advanced
the Hubble’s Lane relief sewer project design to 90%. The project aims to mitigate significant
surcharges, prevent manhole overflows, and permanently close the Wall Street outfall. The
Dreamy Hollow infrastructure improvement project has been completed, and the design for
the recently awarded construction of the sanitary sewer replacement project near Beacon
Street has been finalized. This project aims to eliminate potential wet weather SSOs and is
expected to take approximately one year to complete.
Ms. Pacelli provided an update on the Facility Plan, stating that in November 2024, the
WPCA had responded in writing to a July 24th DEEP letter, in which we reiterated our plan
to eliminate Outfall 002 through a comprehensive wet weather flow reduction program, rather
than on-site plant treatment. This offers a long-term benefit for lifespan and improved water
quality. They also propose to extend the timeline of this work from 10 to 20 years and are still
awaiting DEEP’s response. As part of the update, they have also initiated the design with
ARCADIS for the upgrade of the final settling tank project. This project is potentially eligible
for Clean Water Funding, so they have requested and obtained DEEP’s approval of the
engineering agreement in February 2025. The design is progressing, and the construction is
anticipated to be bid as early as June 2026.
C. DISCUSSION ON WPCA ENGINEERING PROJECTS:
1. HUBBELL’S LANE RELIEF SEWER
Ms. Pacelli said the Hubbell’s Lane sewer relief project is progressing to 100% design and is
working on the utility conflicts with the design.
2. FINAL SETTLING TANKS
Ms. Pacelli said the design of the final settling tanks is progressing toward 30%.
3. BETTSWOOD ROAD AND BARBARA DRIVE SEWER SEPARATION AND
DRAINAGE PROJECT
Mr. Pizighelli provided an update on the project, stating that we are continuing with the
design and finalizing the grant paperwork, as well as acquiring easements through Norwalk
Green. The project is currently at 90% design and is expected to reach 100% completion over
the next couple of months.
D. DISCUSSION ON WPCA CONSTRUCTION PROJECTS:
1. PS- OLD TROLLEY WAY SITE IMPROVEMENTS
Ms. Pacelli said the Old Trolley Way pump station site improvements have been completed,
and they are now working on the limits of the grass mowing. Ms. Valadares said the state will
be mowing their area.
3
2. PS- FORT POINT IMPROVEMENTS
Ms. Pacelli said they continue to work with the Walk Bridge team reviewing the submittals
for the pump station work, which is anticipated to start this fall.
3. COLLECTION- BEACON STREET SANITARY SEWER REPLACEMENT
Mr. Pizighelli said a pre-construction meeting is scheduled for next Tuesday, and they are
hopeful of breaking ground at the end of September or the beginning of October, pending
submittal reviews and approval of materials.
4. COLLECTION- SAMMIS AND BELL ISLAND SEWERSHED REHABILITATION
Ms. Pacelli stated that Insituform has been working on manhole rehabilitation, lateral
grouting, and completing the CIPP lining. They are on schedule to complete all the work by
the end of September.
E. SEWER USE APPEALS AND ADJUSTMENT UPDATE
Ms. Pacelli stated that the sewer use bills were sent out on July 1st and, to date, have issued
$2,688 in adjustments.
VI. NEW BUSINESS
There was no new business discussed this evening.
VII. DISCUSSION
There was no discussion this evening.
VIII. ADJOURNMENT
** MR. IGNERI MOVED TO ADJOURN
** THE MOTION PASSED UNANIMOUSLY.
The meeting was adjourned at 5:50 PM.
Respectfully submitted,
Dilene Byrd
4
Agenda
REGULAR MEETING – WATER POLLUTION CONTROL AUTHORITY
AGENDA
JULY 21, 2025, 5:30 PM
BY ZOOM VIRTUAL MEETING
To allow public access, anyone may access a meeting by telephone and/or Zoom, or a recording in the City of
Norwalk YouTube channel. Specific instructions and links can be found at norwalkct.gov/meetings.
Members of the public may call in to participate. Callers will not be able to see the meeting
participants. All participants will be muted upon entering the meeting. To speak, dial *9 on the phone
and you will be called on by the host of the meeting during the public comment section. All speakers
must state their name and address. Comments must be on a topic on the agenda, and are limited to
three minutes. Anyone disrupting the orderly conduct of the meeting, including by using threatening,
hateful, or sexually-explicit language, will be removed. Please find the information using the link
above.
Members of the public who wish to provide "live comments" may also use the Zoom meeting platform.
All participants will be muted upon entering the meeting. To speak, click the “raise your hand
indicator” and you will be called by the host of the meeting during the public comment section. All
speakers must state their name and address. Comments must be on a topic on the agenda, and are
limited to three minutes. Anyone disrupting the orderly conduct of the meeting, including by using
threatening, hateful, or sexually-explicit language, will be removed. Please find the information using
the link above.
Members of the public who wish to provide public comment are encouraged to submit those via email
in advance of the meeting. For these comments to be included into the record, they must be
submitted by 12:00 p.m. the day of the meeting. Please email Dilene Byrd at dbyrd@norwalkct.gov
with the subject line “Public Comment” to provide written public comment prior to the meeting.
I. CALL TO ORDER
II. ROLL CALL
III. ACCEPTANCE OF MINUTES
A. Regular Meeting: June 16, 2025
IV. PUBLIC PARTICIPATION
V. OLD BUSINESS
A. Contract Operations Report:
1. Veolia Monthly Operating Report- June 2025 (copy included)
2. Contract Year 6 – Inflation Adjustment (letters included)
B. Reports:
1. FY 24/25 Revenues/Expenditures MUNIS Reports (copy included)
2. Consent Order - 2025 Annual Progress Report (copy included)
C. Discussion on WPCA Engineering Projects:
1. Hubbell's Lane Relief Sewer
2. Final Settling Tank
3. Bettswood Road and Barbara Drive Sewer Separation and Drainage Project
D. Discussion on WPCA Construction Projects:
1. PS- Old Trolley Way Site Improvements
2. PS - Fort Point Improvements
3. Collection- Beacon Street Sanitary Sewer Replacement
4. Collection – Sammis and Bell Island Sewershed Rehabilitation
E. Sewer Use Appeals/Adjustments Update
VI. NEW BUSINESS
VII. DISCUSSION
UPCOMING MEETINGS- MONDAY, AUGUST 18, 2025, 5:30PM.
VIII. ADJOURNMENT
Packet
REGULAR MEETING – WATER POLLUTION CONTROL AUTHORITY
AGENDA
JULY 21, 2025, 5:30 PM
BY ZOOM VIRTUAL MEETING
To allow public access, anyone may access a meeting by telephone and/or Zoom, or a recording in the City of
Norwalk YouTube channel. Specific instructions and links can be found at norwalkct.gov/meetings.
Members of the public may call in to participate. Callers will not be able to see the meeting
participants. All participants will be muted upon entering the meeting. To speak, dial *9 on the phone
and you will be called on by the host of the meeting during the public comment section. All speakers
must state their name and address. Comments must be on a topic on the agenda, and are limited to
three minutes. Anyone disrupting the orderly conduct of the meeting, including by using threatening,
hateful, or sexually-explicit language, will be removed. Please find the information using the link
above.
Members of the public who wish to provide "live comments" may also use the Zoom meeting platform.
All participants will be muted upon entering the meeting. To speak, click the “raise your hand
indicator” and you will be called by the host of the meeting during the public comment section. All
speakers must state their name and address. Comments must be on a topic on the agenda, and are
limited to three minutes. Anyone disrupting the orderly conduct of the meeting, including by using
threatening, hateful, or sexually-explicit language, will be removed. Please find the information using
the link above.
Members of the public who wish to provide public comment are encouraged to submit those via email
in advance of the meeting. For these comments to be included into the record, they must be
submitted by 12:00 p.m. the day of the meeting. Please email Dilene Byrd at dbyrd@norwalkct.gov
with the subject line “Public Comment” to provide written public comment prior to the meeting.
I. CALL TO ORDER
II. ROLL CALL
III. ACCEPTANCE OF MINUTES
A. Regular Meeting: June 16, 2025
IV. PUBLIC PARTICIPATION
V. OLD BUSINESS
A. Contract Operations Report:
1. Veolia Monthly Operating Report- June 2025 (copy included)
2. Contract Year 6 – Inflation Adjustment (letters included)
B. Reports:
Page 1 of 32
1. FY 24/25 Revenues/Expenditures MUNIS Reports (copy included)
2. Consent Order - 2025 Annual Progress Report (copy included)
C. Discussion on WPCA Engineering Projects:
1. Hubbell's Lane Relief Sewer
2. Final Settling Tank
3. Bettswood Road and Barbara Drive Sewer Separation and Drainage Project
D. Discussion on WPCA Construction Projects:
1. PS- Old Trolley Way Site Improvements
2. PS - Fort Point Improvements
3. Collection- Beacon Street Sanitary Sewer Replacement
4. Collection – Sammis and Bell Island Sewershed Rehabilitation
E. Sewer Use Appeals/Adjustments Update
VI. NEW BUSINESS
VII. DISCUSSION
UPCOMING MEETINGS- MONDAY, AUGUST 18, 2025, 5:30PM.
VIII. ADJOURNMENT
Page 2 of 32
CITY OF NORWALK
WATER POLLUTION CONTROL AUTHORITY VIA ZOOM VIRTUAL
VIDEOCONFERENCE AND TELECONFERENCE
REGULAR MEETING
June 16, 2025
Attendance: Darren Oustafine, Chairman
John Igneri, Vice Chairman
Chris Mannella
John Bove
James Frayer
Staff: Vanessa Valadares, Chief of Operations and Public Works
Ralph Kolb, WPCA Senior Environmental Engineer
Christine Pacelli, Wastewater Systems Manager
Mario Pizighelli, Stormwater Systems Manager
Others: Trever Steeprock, Project Manager, Veolia, Inc.
Ross Gambino, Asst. Project Manager, Veolia, Inc.
I. CALL TO ORDER
Mr. Oustafine called the meeting to order at 5:30 PM.
II. ROLL CALL
Mr. Oustafine called the roll; all those listed in attendance were present.
III. ACCEPTANCE OF MINUTES
A. REGULAR MEETING- MAY 19, 2025
** MR. IGNERI MOVED TO APPROVE THE MINUTES AS AMENDED.
** THE MOTION PASSED UNANIMOUSLY.
V. PUBLIC PARTICIPATION
There were no public comments this evening.
1
Page 3 of 32
IV. NEW BUSINESS
A. ELECTION OF OFFICERS AND SECRETARY FROM JULY 1, 2025, TO JUNE 30,
2026.
** MR. MANNELLA MOVED TO NOMINATE THE CURRENT SLATE OF
OFFICERS AND SECRETARY.
*THE MOTION PASSED UNANIMOUSLY.
B. AUTHORIZE THE CHAIRMAN OR VICE CHAIRMAN OF THE WATER
POLLUTION CONTROL AUTHORITY TO EXECUTE AN AGREEMENT WITH
C.J. FUCCI, INC., IN THE AMOUNT OF $4,362,000.00 FOR THE BEACON
STREET SANITARY SEWER REPLACEMENT PROJECT (WPCA 2025-1),
(LETTER ATTACHED) ACCOUNT# 09254062-5777-C0361
Mr. Pizighelli stated that six bids were received for the project, and F.J. Fucci was the lowest
responsible bidder at $ 4.3 million. He noted that they were significantly lower than the engineers’
estimate. He received feedback from other municipalities regarding recommendations and has not
received any negative feedback. It is the staff’s recommendation to move forward with F.J. Fucci
for this project.
Mr. Frayer asked if the engineer’s estimate is what is included in the budget. Mr. Kolb said, “Yes.”
** MR. IGNERI MOVED THE ITEM.
** THE MOTION PASSED WITH FOUR (4) IN FAVOR AND ONE ABSTENTION (MR.
MANELLA).
C. AUTHORIZE THE CHIEF OF OPERATIONS AND PUBLIC WORKS TO
EXECUTE ORDERS ON CONTRACT WITH C.J. FUCCI, INC. FOR THE
BEACON STREET SANITARY SEWER REPLACEMENT PROJECT (WPCA 2025--
1), FOR AN AMOUNT NOT TO EXCEED $ 436,200.00
ACCOUNT# 09254062-5777-C0361
Mr. Pizighelli said that this item is the typical 10% contingency for any change order monies that may be
required for this project.
** MR. FRAYER MOVED THE ITEM.
** THE MOTION PASSED WITH FOUR (4) IN FAVOR AND ONE ABSTENTION (MR.
MANELLA).
2
Page 4 of 32
VII. OLD BUSINESS
A. Contract Operations Report
1. Veolia Monthly Operating Report- May 2025 (copy included)
Mr. Steeprock reported that the Veolia collections system team completed 0 miles of TV
inspection in May because Veolia has invested in a new CCTV computer for the camera
truck, which is expected to be operational within a week or so. He said 7.5 miles of sewer
cleaning, 72 manhole inspections, 10.15 miles of SL Rat, responding to eight service calls,
and cleaning all four final settling tank launders and chlorine contact tanks were completed.
The IPP inspection program conducted 29 inspections.
Mr. Steeprock said the facility’s nitrogen performance for May was 638 pounds.
Mr. Steeprock said new sprayers were added to aeration tanks two and five in the recycle
pump zone to help keep the foam down, and a system was installed to clean the polymer
pump and piping, which has improved operations on the centrifuge.
Mr. Steeprock said the facility had another month of heavy rain without experiencing a wet
weather event.
Mr. Steeprock stated that all permit requirements were met for May, and all required reports
were submitted to the CT DEEP and the EPA.
2. Nitrogen Performance (copy included)
Mr. Steeprock said there was a slight adjustment from what was reported last month. One of
the facilities in the program had a data entry error caught during auditing that affected the
trading credit price. The WPCA will now receive an award of $33,720.
B. REPORTS:
1. FY 24/25 REVENUES/EXPENDITURES MUNIS REPORTS (COPY INCLUDED)
There was no discussion.
2. SAVE THE SOUND- 2025 LONG ISLAND SOUND BEACH REPORT SOUND
HEALTH EXPLORER (PARTIAL COPY INCLUDED)
LINK TO FULL REPORT: Https://soundhealthexplorer.org/swimmable
3
Page 5 of 32
Ms. Pacelli said Save the Sound published its 2025 Long Island Sound Beach report, which
was a fairly positive report for Norwalk beaches.
C. DISCUSSION ON WPCA ENGINEERING PROJECTS:
1. DISCUSSION OF SANITARY SEWER EXTENSION REQUEST ON BOUTON
STREET (PRESENTATION INCLUDED)
Mr. Kolb said at the May meeting that the WPCA board requested that staff revisit the cost
estimate range and present the revisions. He said the proposal was approximately 850’ of 8”
gravity main and having connections for the parcels to the right of way. He presented the
estimated costs and stated that two components are included: the sanitary sewer extension
project within the city's right of way, and the second component is the private sewer lateral
work, which includes connection and permit fees, among other expenses. The range is
$15,000 to $25,000. The WPCA team followed the CTDOT bid documents for a cost range
and the engineers' estimate, and at a conceptual level, the range was $600,000 to $975,000.
Mr. Frayer noted that the savings seem incredible from running the numbers using different
guidelines. Ms. Valadares said estimating without a concept design is difficult, but they are
considering an allowance for the unknowns.
The WPCA team requested direction from the board. Mr Oustafine said what he had heard
from the folks at the public hearing was that they were not interested in the price that was
previously presented. He asked the board if more money should be allocated to obtain a more
accurate estimate of the rock, which will be a significant factor in determining the cost of any
sewer project. Mr. Kolb clarified that the estimate is per parcel and not the total cost, and the
private sewer later is an additional cost each parcel owner bears to connect. Ms. Valadares
reminded the board that the freeholder’s process is something they can decide to use, or that it
can be implemented as a capital improvement project to the collection system, without
charging the residents. Even if the board chooses to cover the cost of the major line, there will
be some costs associated with each of the properties when the connection is made. Mr. Frayer
said he is concerned about the new, significantly lower project cost and whether the project
will be approved. Once started, if it is discovered that it would be more expensive, his
concern is what the ceiling will be. Ms. Valadares said that before designing the project,
borings will be conducted to evaluate the soil, so a more realistic cost can be determined
before the project is advertised. Mr. Frayer asked if the cost of the borings is included in the
engineering design phase. Ms. Valadares said, “Yes,” more than likely, and sometimes, when
a design is ready, grants may be available that can be applied for. Mr. Igneri asked how many
times there have been projects like this that were declared capital improvement projects,
where the residents have not been charged. Ms. Valadares stated that over the past 15 years,
no projects have been undertaken, and the existing sewer has been rehabilitated; therefore,
there is no charge to the residents. Some developers or individuals have also been interested
in extending the sewer where they are working on the project, but the WPCA takes ownership
if they follow our guidelines.
4
Page 6 of 32
Mr. Oustafine said that if the board were to vote for a benefit appraisal, it would be less than
$60,000. The board would be assured the assessment would not pay for the project because
we can’t charge above whatever that apparent benefit is to the people who live there, but
$60,000 to $100,000 for an apparent benefit to the home is a lot and probably outside the
range of an evident benefit of having a sewer. If the WPCA board is not interested in funding
the sewer extension project out of the reserves, the project should not proceed. Still, if we
believe the benefit of having a sewer is great and the apparent benefit would likely be in that
range, we should probably vote to have a benefit appraisal done to see if it is viable. Mr.
Igneri asked if the project was not feasible, and if an alternative could be offered to the
residents to help with the drainage issues from the school. Mr. Oustafine said that as the
WPCA, he does not think they can decide on storm sewers or drainage, and the only
alternative would be to choose to fund the project from the reserve account, which is not
typically done because rate payers in other areas will subsidize the sewer extension.
Typically, residents in the project area are responsible for paying for the sewer extension.
Mr. Mannella asked if it reaches the point where the sewer is leaking into the road due to the
septic tanks failing, and there is no viable option to replace the septic system, nor is a design
in place, if the house will be condemned. Mr. Kolb said in his discussions with the health
department that some modifications can be made to the septic system, but no improvements
to the house would be allowed.
Mr. Frayer asked, although it was not a WPCA issue, one of the residents pointed to the
drainage from the football field, which was causing flooding in their yards, and wondered if
there was any merit to that. Ms. Valadares said there are numerous issues on Bouton Street
related to drainage, not only affecting the school, but also the road itself. However, there is a
physical restraint due to the watershed that drains under the tracks. A study was conducted a
few years ago, but it has not been followed up on because improving the drainage in that area
would be extremely expensive to the city. To implement that drainage improvement, we need
to secure an easement so that the drainage issue in that area can be easily resolved.
Mr. Mannella suggested that the staff move forward with 30% to 40% of the design to
manage the cost better. Mr. Oustafine asked the staff if they knew the cost. Ms. Valadares said
that the staff would get some proposals and present the cost to the board.
2. HUBBELL’S LANE RELIEF SEWER
Ms. Pacelli said the Hubbell’s Lane sewer relief project is progressing to 100% design. Due
to a utility conflict, some redesign was needed for the intersection on East Avenue and East
Wall Street, so the product will now progress towards the final design.
3. FINAL SETTLING TANKS
Ms. Pacelli said the design of the final settling tanks is progressing toward 30%. We have a
workshop scheduled this week to discuss the development of the basis for the design report.
5
Page 7 of 32
D. DISCUSSION ON WPCA CONSTRUCTION PROJECTS:
1. COLLECTION- SAMMIS AND BELL ISLAND SEWERSHED REHABILITATION
Mr. Kolb said Insituform has been working on manhole rehabilitations and lateral grouting at
the connections. Shortly after July 4th, crews will finish the CIPP lining. They are still on
schedule and anticipate that all the work will be completed by the end of September.
2. PS- OLD TROLLEY WAY SITE IMPROVEMENTS
Ms. Pacelli stated that the Old Trolley Way pump station site improvements were completed
last month, and the only remaining portion of work is the fencing, which is expected to be
finished soon.
3. PS- FORT POINT IMPROVEMENTS
Ms. Pacelli said the WPCA team continues to coordinate with the Walk Bridge team to
discuss the coordination efforts for the improvements at the Fort Point pump station, which
are scheduled to begin in early fall.
VII. DISCUSSION
There was no discussion this evening.
VIII. ADJOURNMENT
** MR. IGNERI MOVED TO ADJOURN
** THE MOTION PASSED UNANIMOUSLY.
The meeting was adjourned at 6:14 PM.
Respectfully submitted,
Dilene Byrd
6
Page 8 of 32
Norwalk Water Pollution Control Authority
Monthly Operating Report
June 2025
1
Page 9 of 32
Norwalk Water Pollution Control Authority Monthly Operating Report –June 2025
EXECUTIVE SUMMARY
June Highlights
● The Veolia collections system team completed 0.57 miles of TV inspection, 6.20 miles of sewer
cleaning was completed, 140 Manhole Inspections, and 7.7 miles of SL Rat.
● Veolia responded to 6 service calls.
● Veolia installed new level monitoring in both Bisulfite storage tanks.
● The IPP inspection program conducted 32 inspections.
● The facility’s Nitrogen Performance for June was 566 lbs.
● Veolia repaired Primary Tank #4 by removing concrete and other debris from the cross collector.
● Old Trolley Way fencing and paving at the pump station is complete.
Regulatory Events
The Water Pollution Control Facility followed all permit requirements for the month of
June.
The netDMR, MOR, NAR, and ATMR reports were submitted to CT-DEEP and EPA in June.
The Quarterly Sludge Report was sent to Synagro.
2
Page 10 of 32
Norwalk Water Pollution Control Authority Monthly Operating Report –June 2025
EXECUTIVE SUMMARY - Key Operational Parameters`
Parameter Units June CYTD Result Contract Limit
Result
Average Daily Flow MGD 11.30 n/a n/a
180 Day Average Daily Flow MGD 11.97 n/a n/a
Effluent BOD mg/l 4.4 n/a 10
Effluent TSS mg/l 4.4 n/a 10
Effluent Fecal Coliform # / 100 ml 5 n/a 10
Effluent Enterococci # / 100 ml 9 n/a 30
Effluent Total Chlorine mg/l 0.02 n/a 0.07
Effluent Total Nitrogen lbs/day 566 n/a 1,000
Biosolids Quality (cake) % solids 30 n/a n/a
Biosolids Disposal (cake) DT/month 246 n/a n/a
Biosolids Disposal (liq) DT/month 12 n/a n/a
Biosolids Disposal (total) DT/month 258 n/a n/a
Grit and Screenings WT/month 6 n/a n/a
Chemicals – Hypochlorite gal/month 6456 n/a n/a
Chemicals – Bisulfite gal/month 5102 n/a n/a
Chemicals – Polymer gal/month 600 n/a n/a
Chemicals – Odor Control gal/month 0 n/a n/a
Sewer Cleaning Miles 6.20 38.18 3 miles (avg)
CCTV Inspection Miles 0.57 14.57 2 miles (avg)
Odor Complaints # 0 n/a 0
SL-RAT Inspection Miles 7.7 70.27 60 months
Manhole Inspections # 140 546 50/m
IPP Inspections # 32 385 Approx. 500/year
3
Page 11 of 32
Norwalk Water Pollution Control Authority Monthly Operating Report –June 2025
EXECUTIVE SUMMARY - Influent Flow
Influent Flow
20.00
18.00
16.00
14.00
12.00
MGD
10.00
8.00
6.00
4.00
2.00
0.00
Jun-21 Aug-21 Oct-21 Dec-21 Feb-22 Apr-22 Jun-22 Aug-22 Oct-22 Dec-22 Feb-23 Apr-23 Jun-23 Aug-23 Oct-23 Dec-23 Feb-24 Apr-24 Jun-24 Aug-24 Oct-24 Dec-24 Feb-25 Apr-25 Jun-25
180 Day MA Flow Design Flow 90% Design Flow Linear (180 Day MA Flow)
4
Page 12 of 32
Page 13 of 32
Page 14 of 32
Page 15 of 32
Page 16 of 32
Page 17 of 32
Norwalk Water
Pollution Control
Authority
www.wpcanorwalk.org
July 10, 2025
Trevor Steeprock
Project Manager
Veolia
60 South Smith Street
Norwalk, CT 06855
Subject: Inflation Adjustment of the Annual Base Service Fee – Year 6
Dear Mr. Steeprock:
The Norwalk WPCA is in receipt of your June 30, 2025 letter received via email for Inflation
Adjustment of the Annual Base Service Fee for Contract Year 6. WPCA has reviewed the backup
calculation sheets and agree with the inflation increase of 3.3 percent reflecting an annual increase
amount of $303,986.64.
Sincerely,
Ralph K. Kolb, P.E.
Sr. Environmental Engineer
cc: WPCA Board Members
Vanessa Valadares, P.E., Chief of Operations and Public Works
Chris Torre, Superintendent of Operations
Christine Pacelli, EIT, Wastewater Systems Manager
Michael Burke, Veolia
15 South Smith Street, Second Floor, Norwalk, CT 06855 Phone: (203) 854-3228 Fax: (203) 854-3224
Page 18 of 32
June 30, 2025
Mr. Ralph Kolb
Senior Environmental Engineer
City of Norwalk
15 South Smith Street
Norwalk, CT 06855
Subject: Inflation Adjustment of the Annual Base Service Fee – Year 6
Dear Mr. Kolb,
Veolia is pleased to present the following Inflation Adjustment of the Annual Base Service Fee
for Year 6 as detailed in Section 10.2 of the Wastewater System Operations, Maintenance &
Management Agreement.
CPI Adjustment (%) 3.20%
ECI-SUM Adjustment (%) 3.33%
Annual Inflation Adjustment 1.033
CY-5 CY-6
Annual O&M Costs $ 8,523,436.29 $ 8,804,709.69
Collections CRSF $ 292,380.37 $ 302,028.92
ETERF Contribution $ 395,899.89 $ 408,964.58
Annual Base Service Fee $ 9,211,716.55 $ 9,515,703.19
Annual Increase Amount $ 303,986.64
In addition, the following components of the agreement have been adjusted for contract year 6
as follows:
Contract Item CY5 AIF CY6
IPP Adjustment $ 1,754.36 1.033 $ 1,812.25
$ 584.79 1.033 $ 604.09
Effluent Guarantee Limits (Sec 7.2A)
$ 11,695.71 1.033 $ 12,081.67
$ 584.79 1.033 $ 604.09
$ 1,169.57 1.033 $ 1,208.17
Odor Non-Compliance (Sec 7.3)
$ 1,754.36 1.033 $ 1,812.25
$ 3,508.72 1.033 $ 3,624.51
$ 584.79 1.033 $ 604.09
$ 1,169.57 1.033 $ 1,208.17
Environmental Guarantee (Sec 7.4B)
$ 1,754.36 1.033 $ 1,812.25
$ 3,508.72 1.033 $ 3,624.51
$ 5,847.86 1.033 $ 6,040.84
Environmental Guarantee (Sec 7.4C and D) $ 11,695.71 1.033 $ 12,081.67
$ 23,391.46 1.033 $ 24,163.38
Admin Sanctions (Sec 7.7B) $ 584.79 1.033 $ 604.09
Performance Incentive (Sec 7.10A) $ 5,847.86 1.033 $ 6,040.84
Maintenance Repair and Replacement (Sec 8.10C) $ 11,695.71 1.033 $ 12,081.67
Page 19 of 32
Collections System Repair Fund (Sec 8.2E) $ 292,380.37 1.033 $ 302,028.92
End of Term Replacement Fund (Sec 8.3A) $ 395,899.88 1.033 $ 408,964.58
Sewer Back-up Liability (Sec 11.3) $ 58,478.57 1.033 $ 60,408.36
Subcontractors (Sec 14.8B) $ 29,239.28 1.033 $ 30,204.18
Attached also for your use are the back-up calculation sheets and BLS statistics used to
determine the adjustment. Should you require additional information, please do not hesitate to
contact me.
Sincerely,
Trevor Steeprock
Project Leader
Cc: Michael Burke Veolia
Veolia North America
60 S. Smith St.
Norwalk, CT 06855
203.395.6248
www.veolianorthamerica.com
Page 20 of 32
City of Norwalk
YEAR-TO-DATE BUDGET REPORT
FOR 2025 99
ACCOUNTS FOR: ORIGINAL TRANFRS/ REVISED AVAILABLE PCT
22 WATER POLLUTION CONTROL APPROP ADJSTMTS BUDGET YTD EXPENDED ENCUMBRANCES BUDGET USED
040 PUBLIC WORKS
224062 WATER POLLUTION CONTROL
224062 4051 INTEREST -65,000 0 -65,000 -99,671.86 .00 34,671.86 153.3%
224062 4121 NITROGEN -30,000 0 -30,000 -49,199.00 .00 19,199.00 164.0%
224062 4451 SEWER PERM -1,500 0 -1,500 -1,600.00 .00 100.00 106.7%
224062 4453 SEPTIC LIC -1,200 0 -1,200 -1,500.00 .00 300.00 125.0%
224062 4513 SEWER CHRG -18,747,000 0 -18,747,000 -19,164,768.82 .00 417,768.82 102.2%
224062 4516 SPT DIS FE -175,000 0 -175,000 -225,815.00 .00 50,815.00 129.0%
224062 4521 WILTON SU -850,000 0 -850,000 -1,705,108.46 .00 855,108.46 200.6%
224062 4522 SEWER USE -45,000 0 -45,000 -93,121.00 .00 48,121.00 206.9%
224062 452C INDUSTRIAL -175,000 0 -175,000 -189,557.48 .00 14,557.48 108.3%
224062 452D SEWER CONN -150,000 0 -150,000 -312,547.15 .00 162,547.15 208.4%
224062 452E IPP INTERE -5,000 0 -5,000 -8,640.65 .00 3,640.65 172.8%
224062 4807 REIMB EXP -1,000 0 -1,000 .00 .00 -1,000.00 .0%
224062 489F REIMB GF -139,806 0 -139,806 -139,806.00 .00 .00 100.0%
224062 4901 INV INCOME -110,000 0 -110,000 -206,453.57 .00 96,453.57 187.7%
TOTAL WATER POLLUTION CONTROL -20,495,506 0 -20,495,506 -22,197,788.99 .00 1,702,282.99 108.3%
TOTAL PUBLIC WORKS -20,495,506 0 -20,495,506 -22,197,788.99 .00 1,702,282.99 108.3%
TOTAL WATER POLLUTION CONTROL -20,495,506 0 -20,495,506 -22,197,788.99 .00 1,702,282.99 108.3%
TOTAL REVENUES -20,495,506 0 -20,495,506 -22,197,788.99 .00 1,702,282.99
Report generated: 07/11/2025 10:30 Page 1
User: 2882dbyrd
Program ID: glytdbud
Page 21 of 32
City of Norwalk
YEAR-TO-DATE BUDGET REPORT
FOR 2025 99
ACCOUNTS FOR: ORIGINAL TRANFRS/ REVISED AVAILABLE PCT
22 WATER POLLUTION CONTROL APPROP ADJSTMTS BUDGET YTD EXPENDED ENCUMBRANCES BUDGET USED
040 PUBLIC WORKS
224062 WATER POLLUTION CONTROL
224062 5110 WAGES & SA 706,026 0 706,026 592,172.68 .00 113,853.32 83.9%
224062 5120 WAGES & SA 100,000 0 100,000 3,708.88 .00 96,291.12 3.7%
224062 5140 WAGES & SA 36,000 0 36,000 .00 .00 36,000.00 .0%
224062 5150 LONGEVITY 1,150 0 1,150 1,225.00 .00 -75.00 106.5%
224062 5235 MEMBERSHIP 10,000 0 10,000 297.50 .00 9,702.50 3.0%
224062 5241 ELECTRIC 1,607,400 0 1,607,400 1,612,270.34 84,576.19 -89,446.53 105.6%
224062 5245 TELEPHONE 2,000 0 2,000 957.52 .00 1,042.48 47.9%
224062 5252 LEGAL SERV 250,000 0 250,000 133,645.00 16,355.00 100,000.00 60.0%
224062 5258 OMI 10,795,100 692,522 11,487,622 11,312,433.95 175,187.97 .00 100.0%
224062 5286 BUSINESS E 32,000 0 32,000 27,302.17 2,310.43 2,387.40 92.5%
224062 5295 SEMINAR&CO 20,000 0 20,000 8,296.24 .00 11,703.76 41.5%
224062 5298 OTHER 250,000 4,500 254,500 82,940.23 16,700.00 154,859.77 39.2%
224062 5418 INSURANCE 88,950 0 88,950 88,950.00 .00 .00 100.0%
224062 5428 BENEFITS 376,312 0 376,312 376,312.00 .00 .00 100.0%
224062 5521 PRINCIPAL 3,248,691 0 3,248,691 3,154,022.21 .00 94,668.79 97.1%
224062 5522 INTEREST 1,887,129 0 1,887,129 1,872,551.67 .00 14,577.33 99.2%
224062 5523 BOND EXP 0 0 0 48,170.00 .00 -48,170.00 100.0%
224062 5651 TO G/F 763,653 0 763,653 763,653.00 .00 .00 100.0%
224062 5741 IT HARDWAR 60,000 0 60,000 31,393.77 .00 28,606.23 52.3%
224062 5789 RESERVE 261,095 0 261,095 .00 .00 261,095.00 .0%
TOTAL WATER POLLUTION CONTROL 20,495,506 697,022 21,192,528 20,110,302.16 295,129.59 787,096.17 96.3%
TOTAL PUBLIC WORKS 20,495,506 697,022 21,192,528 20,110,302.16 295,129.59 787,096.17 96.3%
TOTAL WATER POLLUTION CONTROL 20,495,506 697,022 21,192,528 20,110,302.16 295,129.59 787,096.17 96.3%
TOTAL EXPENSES 20,495,506 697,022 21,192,528 20,110,302.16 295,129.59 787,096.17
Report generated: 07/11/2025 08:45 Page 1
User: 2882dbyrd
Program ID: glytdbud
Page 22 of 32
Norwalk Water
Pollution Control
Authority
www.wpcanorwalk.org
VIA ELECTRONIC MAIL
June 26, 2025
Mr. Syed Bokhari
Environmental Engineer 2
Municipal Wastewater
Water Planning and Management Division
Bureau of Water Protection and Land Reuse
Department of Energy and Environment Protection
79 Elm Street
Hartford, CT 06106-5127
Subject: City of Norwalk, CT, Consent Order (#COWRMU22001)
2025 Annual Progress Report
Dear Mr. Bokhari,
Please find attached for your records a copy of the 2025 Annual Progress Report that is due on or
before June 30th annually in accordance with Section B.6. of the above referenced Consent
Order.
Should you have any questions, please feel free to contact me at 203-854-3242.
Sincerely,
Ralph K. Kolb, P.E.
Sr. Environmental Engineer
Copy: WPCA Board of Directors
Vanessa Valadares, P.E., DPW (via Electronic Mail)
Chris Torre, DPW (via Electronic Mail)
Christine Pacelli, WPCA (via Electronic Mail)
Trevor Steeprock, Veolia (via Electronic Mail)
15 South Smith Street, Second Floor, Norwalk, CT 06855 Phone: (203) 854-3228 Fax: (203) 854-3224
Page 23 of 32
Norwalk Water
Pollution Control
Authority
www.wpcanorwalk.org
June 26, 2025
Mr. Syed Bokhari
Environmental Engineer 2
Municipal Wastewater
Water Planning and Management Division
Bureau of Water Protection and Land Reuse
Department of Energy and Environment Protection
79 Elm Street
Hartford, CT 06106-5127
Subject: City of Norwalk, CT, Consent Order (#COWRMU22001)
2025 Annual Progress Report
Dear Mr. Bokhari,
In accordance with Paragraph B.6 of the above-referenced Consent Order between the State of
Connecticut and City of Norwalk (the “City”) dated May 5, 2022 (the “Consent Order”), this
Progress Report documents the actions taken by the City pursuant to the Consent Order since its
2024 Annual Progress Report filed June 26, 2024.
Progress Report June 2025
In response to the requirements of Paragraph B.1
As specified in Paragraph B.1 of the Consent Order, the City of Norwalk’s Water Pollution
Control Authority (“WPCA”) retained Brown and Caldwell as the primary on-call collection
system consultant and Woodard and Curran as the secondary on-call collection system consultant
to complete the Sanitary Sewer Collection System Master Plan update (the “Master Plan”).
Brown and Caldwell’s current contract was extended in December 2022 and expires in March
2027. In May 2024, the WPCA and Woodard and Curran signed a contract amendment,
extending Woodard and Curran’s services as the secondary on-call collection system consultant
through March 2027.
In response to the requirements of Paragraph B.2
As specified in Paragraph B.2 of the Consent Order, the WPCA retained Arcadis US, Inc. to
complete the Wastewater Treatment Plant Facility Plan update (the “Facility Plan Update”). The
WPCA’s current contract with Arcadis was extended in 2022 and expires in January 2026. The
WPCA expects to extend the current contract with Arcadis in advance of January 2026.
15 South Smith Street, Second Floor, Norwalk, CT 06855 Phone: (203) 854-3228 Fax: (203) 854-3224
Page 24 of 32
In response to the requirements of Paragraph B.3
In accordance with Paragraph B.3, Brown and Caldwell prepared the Master Plan, which the
City submitted to DEEP on September 30, 2022. The Master Plan is currently pending before
DEEP. The Master Plan describes and evaluates a range of viable and cost-effective measures to
(1) remove excess flows (such as infiltration/inflow) from the wastewater collection system, and
(2) eliminate the Ann Street Siphon Emergency Overflow from the wastewater collection
system.
As part of the Master Plan update, Brown and Caldwell developed and calibrated a hydraulic
model of Norwalk’s collection system to analyze existing conditions, characterize system
performance, and to support modeling of potential sewer improvement alternatives and future
conditions. With the help of the collection system model, the Master Plan update evaluates a
range of cost-effective measures to reduce excess flows, such as inflow and infiltration, from
entering the collection system. Reduced excess flows includes both the disconnection of
stormwater catch basins that are directly connected to the wastewater collection system and
targeted reduction of infiltration and inflow.
On September 29, 2023, the WPCA submitted to DEEP an Amended Collection System Master
Plan (“Amended Master Plan”), revising the Master Plan’s flow calculations for Outfall 002-1 as
shown in Tables ES-1, ES-2, 4-4, 5-2, 5-7, 5-8, and 7-1 to 7-4. As the WPCA informed DEEP at
a meeting on June 20, 2023, the prior Master Plan’s flow calculations resulted in an over-
estimation of wastewater volume directed to Outfall 002-1 during storm events. The revised
calculations included in the Amended Master Plan are favorable, showing predicted flows to
Outfall 002-1 that are considerably lower for a range of rainfall events, including a 66-78%
reduction in flow for 24-hour rainfall events.
On February 20, 2024, the City, WPCA and DEEP met to discuss the Amended Master Plan and
the Facility Plan Update, which describes and evaluates a range of viable and cost-effective
measures to (1) provide Outfall 002-1 with primary treatment or its equivalent or (2) eliminate
Outfall 002-1. On July 9, 2024 1, the City received follow-up correspondence from DEEP
providing comments on the topics of the February 20, 2024 meeting and requesting additional
documents. The City provided a response to DEEP on November 1, 2024, as discussed further
on pages 6-8 of this Progress Report.
Since its 2024 Annual Progress Report filed June 26, 2024, the City has continued to make
substantial progress toward meeting its goals as set forth in the Master Plan. Specifically, the
WPCA has engaged in the following to address collection system projects and reduce excess
flow such as infiltration and inflow into the wastewater collection system:
1
The DEEP correspondence was dated June 17, 2024, but was received via electronic mail on July 9, 2024.
2
Page 25 of 32
• The WPCA has issued a base contract with Insituform Technologies, LLC for sewer
rehabilitation in the low lying and coastal areas of Sammis Street and Bell Island pump
station sewer sheds in the southwest part of Norwalk. In addition to other benefits, the
project will prevent infiltration into the wastewater collection system from storm-
impacted and tidal areas, and high groundwater.
o The original scope of the project included cured-in-place pipe (CIPP) lining 2 of
over 38,800 feet of gravity sewer main ranging in diameter from 8- to 24-inches,
manhole cementious lining, and lateral grouting.
o In May 2024, the scope of the project was expanded to include additional CIPP
lining of approximately 12,000 feet of gravity sewer main, manhole cementious
lining, and lateral grouting in the Marvin Beach Pump Station sewer shed area
and some additional locations.
o In June 2024, the scope of the project was expanded further to include additional
CIPP lining of approximately 15,000 feet of gravity sewer main, manhole
cementious lining, and lateral grouting in the Woodward Ave and Shady Beach
Pump Station sewer sheds, easement, and hot spot locations.
o Following these scope expansions and once completed, the project will include
over 70,000 feet of CIPP lining.
• The WPCA and Veolia, the WPCA’s contract operator, continue to contract with Green
Mountain Pipeline Services to implement CIPP lining throughout the City to reduce
inflow and infiltration to the wastewater collection system.
o In May 2024, Veolia engaged Green Mountain Pipeline Services to rehabilitate all
8-inch and 15-inch collection system gravity mains within the Colonial Village
area of the City. Green Mountain Pipeline Services has since completed this
work.
• The WPCA has continued feasibility and design work for its Catch Basin Disconnection
Program.
o In May 2024, WPCA’s consultant, Brown and Caldwell, completed a task order
issued May 2023 and submitted to the WPCA a final Basis of Design Report.
o The Basis of Design Report investigated the feasibility of disconnecting
approximately forty-three (43) priority catch basins over a five-year project
lifespan, which would have the benefit of diverting approximately 203.8 million
gallons per day of peak flow during a 25-year, 24-hour event from the wastewater
2
Before and after images showing the significant beneficial impacts of pipe lining can be found here on the
WPCA’s website: https://www.norwalkwpca.org/system-information/collection-system/
3
Page 26 of 32
collection system. The project will cost approximately $12.9 million over five
years.
o Seven (7) catch basins have been disconnected since filing the 2024 Annual
Report. 3 They are:
Asset ID No. 1001: Sniffen Street
Asset ID No. 10345: Clay Street
Asset ID No. 49214: Spicewood Road
Asset ID No. 4014: 6 Byselle Place
Asset ID No. 4015: 5 Byselle Place
Asset ID No. 14919: 8 Byselle Place
Asset ID No. 10312: 115 Flax Hill Road
o In December 2024, the WPCA entered a task order with Tighe & Bond for an
infiltration and inflow separation project in the vicinity of Bettswood Road and
Walnut Avenue. The project will disconnect four catch basins – Asset ID Nos.
3932, 3933, 3934, and 8538. The WPCA subsequently increased the scope of the
project in January 2025 to disconnect an additional catch basin on the nearby
Barbara Drive, Asset ID No. 14910. The WPCA anticipates completion of this
project by June 2026.
• The Hubbells Lane Relief Sewer project is currently at 90% design. The project will
install about 500 feet of new 36-inch diameter sewer on Hubbells Lane to reroute flows
from East Wall Street and replace approximately 600 linear feet of existing 36-inch
interceptor with 60-inch diameter sewer interceptor on Smith Street, effectively
mitigating significant surcharging, preventing manhole overflows, and permanently
closing the Wall Street overflow.
o Additional field investigation took place in 2024 to identify the most effective
method of disconnecting two (2) catch basins in the area and redirecting
stormwater flow. Field investigation included smoke testing and dye testing to
identify any unknown connections to the wastewater collection system that may
need to be incorporated into the current design.
o Finalization of the project design has been delayed by a significant utility
presence in the intersection of East Avenue, East Wall Street, Hubbell Lane, and
Park Street.
• The City’s Dreamy Hollow project, which includes improvements to both the storm and
wastewater infrastructure, is now complete.
3
Three (3) of these catch basins are among the forty-three (43) included in the Catch Basin Disconnection Program.
They are assets 1001, 10345, and 49214.
4
Page 27 of 32
o WPCA has upgraded the infrastructure in this area by replacing approximately
3,000 feet of existing piping with new PVC pipe, which will reduce infiltration
into the wastewater collection system from storm-impacted areas.
o The WPCA disconnected two (2) catch basins from the wastewater collection
system in this area and extended the storm drains in 2024.
• The City initiated a new sanitary sewer replacement project in the vicinity of Beacon
Street. The project will replace approximately 1,800 feet of 15-inch sanitary sewer with
24-inch pipe. The larger pipe will eliminate potential wet weather Sanitary Sewer
Overflows in the area.
o The WPCA signed a task order with Brown and Caldwell for design and bid
services in September 2024.
o Bids for construction of the project opened on June 11, 2025, and the WPCA
received six (6) separate bids. Once a contract is executed, the project is expected
to take up to one (1) year to complete.
In response to the requirements of Paragraph B.4
In accordance with Paragraph B.4, Arcadis and Brown and Caldwell prepared the Facility Plan
Update, which was submitted to DEEP on September 29, 2023. The Facility Plan Update
describes and evaluates a range of viable and cost-effective measures to (1) provide Outfall 002-
1 with primary treatment or its equivalent or (2) eliminate Outfall 002-1.
To meet this goal, the WPCA and Arcadis held a series of collaborative workshops to evaluate
multiple wet weather treatment technologies, including conducting site visits to Bridgeport West
Side WPCF, and Waterbury WPCF to observe their wet weather pilot programs. To ensure the
Facility Plan Update comprehensively evaluated all viable measures and identified a path
forward that has the greatest environmental benefit to the Norwalk River and Long Island Sound,
on June 22, 2023, following discussion with DEEP, the WPCA requested a filing extension so
that it could evaluate its options for advancing elimination of Outfall 002-1.
The final Facility Plan Update, submitted September 29, 2023, recommends implementation of
the Comprehensive Wet Weather Flow Reduction Program, which includes substantial
investment in the WPCA collection system, inflow and infiltration reduction efforts, and targeted
collection system rehabilitation projects, as a viable and cost-effective means to advance
elimination of Outfall 002-1. Modeling of the Comprehensive Wet Weather Flow Reduction
Program demonstrates significant overall reduction in flow to the Wastewater Pollution Control
Facility (“WPCF”) and a decrease in volume and duration of discharges from Outfall 002-1,
should they occur.
5
Page 28 of 32
• As noted above, on February 20, 2024, the City, WPCA and DEEP met to discuss the
Facility Plan Update, including the results of further analysis quantifying the
environmental benefits of the Comprehensive Wet Weather Flow Reduction Program.
DEEP provided comments on the City’s proposal to eliminate Outfall 002-1 by
implementing a Comprehensive Wet Weather Flow Reduction Program (the “Program”)
and requested additional documentation. The City provided a written response to DEEP
on November 1, 2024, reiterating its conclusion that elimination of Outfall 002-1 through
the Program will result in better outcomes for the environment, water quality, cost, and
project life span as compared to any viable form of primary treatment or its equivalent for
Outfall 002-1. In addition to overall reduced flow to the WPCF, it is anticipated that the
Program will have a greater overall benefit to water quality than available wet weather
treatment technologies. Over a ten-year period, the Comprehensive Wet Weather Flow
Reduction Program is projected to reduce from Outfall 002-1 discharges: TSS by almost
30% more than cloth filters, BOD by 88% compared to 17% if cloth filters are installed,
and total nitrogen by 88% compared to only 4% if cloth filters are employed. These
significant reductions will result in overall enhanced water quality in the Norwalk River
and Long Island Sound. Moreover, the Program is expected to have a projected lifespan
of 50-100 years compared to a 30-year lifespan for cloth filters.
In response to DEEP’s correspondence dated June 17, 2024, the City proposed the
following plan/modifications to fully eliminate Outfall 002-1, including extending the
timeline in Paragraph B(5) of the Consent Order for completion of measures identified in
the Facility Plan Update from 10 years to 20 years. 4 According to this modification, the
City proposed the following:
1. Years 0-10: Implementation of Comprehensive Wet Weather Flow Reduction
Program
During years 0-10, the City will implement the Comprehensive Wet Weather Flow
Reduction Program as set forth in the Facility Plan Update submitted to DEEP on
September 29, 2023. As described in that submission, the Program will
comprehensively rehabilitate public sewer assets to reduce flow to the WPCF
enabling elimination of Outfall 002-1. Program activities include the following: 5
o Public sewer mains: all public sewer mains within the identified watershed will
be rehabilitated by cured-in-place pipe lining or similar type of continuous lining.
4
Modifying the Consent Order to extend the period for eliminating Outfall 002-1 from 10 years to 20 years is
consistent with other municipalities across Connecticut which have modified their consent orders in similar
circumstances.
5
The City has already made important strides in reducing inflow and infiltration into the collection system by
requiring its contract operator, Veolia, to contract with a cured-in-place lining company to frequently perform small
lining projects, and to deploy new and innovative technology such as smart covers and smarts balls to enhance
awareness of, and real-time inform about, the collection system.
6
Page 29 of 32
This provides an integral barrier to prevent infiltration through defects in the
sewer pipe or the joints between pipe segments.
o Sewer manholes: all sewer manholes within the identified sewershed area will be
rehabilitated by epoxy, cementitious, or other equivalent lining. Like the sewer
main rehabilitation, this provides an integral barrier to prevent infiltration through
defects in the manhole riser or the joints between manhole riser sections.
o Pipe to manhole connections: all pipe to manhole penetrations will be grouted.
Grouting the pipe penetrations creates a seal at the joint that is resistant to
infiltration.
o Lateral to sewer main connections: all lateral to sewer main penetrations will be
grouted. Grouting the lateral to sewer main penetration creates a seal that is
resistant to infiltration.
As described in Tables 4-1 and 4-2 and Figure 4-3 of Appendix E of the Facility Plan
Update, sewersheds will be grouped together and rehabilitated over the course of a
10-year period.
2. Year 5 Assessment
As set forth in the Facility Plan Update, the City anticipates that the Program will
result in, among other impacts, an 80% reduction in volume for a 1-year, 24-hour
storm event and an overall reduction in absolute volume discharged from Outfall 002-
1 for all rain events. The City’s estimates for expected flow reduction associated with
the Program are based on published case studies, flow reductions achieved in other
communities, and a case study in Norwalk. The analysis recognizes that actual
reductions resulting from implementation of the Program may differ from expected
projections. As a result, the City intends to perform Year 5 Assessment to evaluate
and quantify the flow reductions achieved within the Norwalk collection system.
The Year 5 Assessment will include analysis of the following:
o Pre-rehabilitation flow monitoring;
o Post-rehabilitation flow monitoring;
o Hydraulic model update and simulations; and
o Flow reduction analysis.
If, at the 5-year mark, the flow reduction analysis shows that the Program is
reasonably meeting projections for reductions in excess flow, the City will continue
to administer and implement the Program as planned. If the flow reduction analysis
shows that the comprehensive rehabilitation of sewer assets are not reasonably
meeting the projections for reductions in excess flow, the City will prepare a
performance evaluation plan describing the appropriate methods for investigating and
identifying corrective measures necessary to achieve the projected removal of excess
7
Page 30 of 32
flow from the collection system and to assess the best path forward for complete
elimination of Outfall 002-1.
While further discussion with DEEP is warranted, the City is open to memorializing
the Year 5 Assessment as part of the Consent Order.
3. Year 10 Assessment
In addition to the Year 5 Assessment, at year 10, the City will conduct a second
program assessment. This will include a second round of pre-rehabilitation flow
monitoring, post-rehabilitation flow monitoring, hydraulic model update and
simulations, and a final flow reduction analysis. The purpose of this final analysis
will be to quantify and determine the results of the corrective measures implemented
to remove excess flow from the collection system.
As noted above, the City is similarly open to memorializing the Year 10 Assessment
as part of the Consent Order.
4. Years 11-20: Elimination of Outfall 002-1
Based on the results of the Year 10 Assessment, the City will develop a final Outfall
002-1 elimination plan to be implemented from years 11 to 20. The City anticipates
implementing the following:
o Year 11: Conduct an alternatives analysis to determine the best path forward for
eliminating Outfall 002-1 based on the results of the Year 10 Assessment. 6
o Years 12-13: Based on the results of the alternatives analysis, the City will enter a
two-year design phase to implement the study outcome.
o Years 14-20: The City will enter a construction phase for final elimination of
Outfall 002-1 and construction of any additional modifications that may need to
be completed to facilitate elimination.
As with the Years 5 and 10 Assessments, the City is open to memorialize
implementation of a final Outfall 002-1 elimination plan as part of the Consent Order.
• In accordance with the Facility Plan Update, the WPCA also signed a task order with
Arcadis for design and bid services for the WPCF Final Settling Tanks Upgrade Project.
The WPCA requested that DEEP consider this project eligible for the Clean Water Fund
program and DEEP issued an Engineering Agreement Approval on February 5, 2025.
6
At this time, the final method used to eliminate Outfall 002-1 is unknown, as it will depend on the results of the
Year 10 Assessment, but could include, for example, increasing storage capacity at the Facility, increasing flow
through secondary treatment, or additional collection system rehabilitation measures.
8
Page 31 of 32
The approval is included here as Attachment A. It is anticipated that bids for the project
will be received by June 30, 2026.
In response to the requirements of Paragraph B.6
In accordance with Paragraph B.6, this Progress Report summarizes all actions required by this
Consent Order and is submitted on or before the last day of June 2025.
Certification of Documents
The following certification statement is included pursuant to Paragraph B.11 of the Consent
Order:
I have personally examined and am familiar with the information submitted in this
document and all attachments thereto, and I certify, based on reasonable investigation,
including my inquiry of those individuals responsible for obtaining the information, that
the submitted information is true, accurate and complete to the best of the knowledge and
belief. I understand that any false statement made in the submitted information may be
punishable as a criminal offense under § 53a-157b of the Connecticut General Statutes
and any other applicable law.
6/26/2025
Signature Date
Ralph K. Kolb, P.E.
Name
Sr. Environmental Engineer
Title
9
Page 32 of 32