Prequalification Review Board
Regular MeetingOklahoma City, OK · September 10, 2025
Agenda
The City of
OKLAHOMA CITY
FORMAL AGENDA
PREQUALIFICATION REVIEW BOARD
8:30 AM September 10, 2025
PREQUALIFICATION REVIEW BOARD MEMBERS:
Deborah K. Miller, City Engineer/Chair
Chris Browning, Utilities Director/Vice Chair
Amy Simpson, City Clerk/Secretary
Brent Bryant, Assistant City Manager/City Manager Designee
Amy Parker, Finance Director Designee
EMBARK
431 West Main Street, Ste. B
Large Conference Room
INFORMATION ABOUT THE OKLAHOMA CITY
PREQUALIFICATION REVIEW BOARD MEETINGS
The Oklahoma City Prequalification Review Board meets the second Wednesday of the month at
8:30 a.m., at EMBARK, 431 W. Main Street, Suite B in the Large Conference Room, unless prior
notice of a change is posted. Parking is available at the Sheridan-Walker Parking Garage (501 West
Sheridan).
It is the policy of the City to ensure that communications with participants and members of the
public with disabilities are as effective as communications with others. Anyone with a disability
who requires an accommodation, a modification of policies or procedures, or an auxiliary aid or
service in order to participate in this meeting should contact the Prequalification Manager at 297-
2581 as soon as possible but not later than 24 hours (not including weekends or holidays) before
the scheduled meeting. The department will give primary consideration to the choice of auxiliary
aid or service requested by the individual with disability. If you need an alternate format of the
agenda or any information provided at said meeting, please contact the ADA department
coordinator listed above 48 hours prior to the scheduled meeting.
Citizens may address the Prequalification Review Board during public hearings on any matter,
listed on the agenda. Citizens may also address the Prequalification Review Board on individual
concerns at the end of the agenda when the Chairman announces "Comments from Board
Members, Staff and Citizens."
Citizens who wish to be listed on the agenda for comments to the Prequalification Review Board
may call the Prequalification Manager at 297-2581 before 4 p.m. on the Wednesday prior to the
next Prequalification Review Board meeting.
Official action can be taken only on items which appear on the agenda. Staff recommendations do
not limit or define the potential actions of the Prequalification Review Board. The Prequalification
Review Board may grant approval with or without conditions, remove conditions, deny, defer,
strike, amend, refer to staff, include limitations, suspend, revoke, or reinstate prequalification
applications.
When more information is needed to act on an item, the Prequalification Review Board may defer
the matter to a future meeting. Under certain circumstances, items may be deferred to a specific
later meeting date or be stricken from the agenda entirely.
Consent Docket
Items listed under "Consent Docket" are usually approved as a group with the proper motion from
a member of the Prequalification Review Board. Members of the Prequalification Review Board
may request discussion or separate action on any item on the Consent Docket. Citizens may request
to address the Prequalification Review Board on any item on the Consent Docket.
PREQUALIFICATION REVIEW BOARD
FORMAL AGENDA
SEPTEMBER 10, 2025
I. CALL TO ORDER
II. APPROVE MINUTES
A. Approve minutes from the August 13, 2024, meeting.
III. CONSENT DOCKET
A. Items for Consent
1. A#1 Trenching, Inc.
16625 SE 59th
Choctaw, OK 73020
Bonding Limit: $ 250,000 single/$500,000 aggregate
Previous Action: June 11, 2025, conditionally granted approval as Class C:
Paving; Provisional Class C: Water Pipeline; and Class D: Bore Contractor.
Recommendation: REMOVE condition regarding financial statements and
bond assurance letter.
2. Best 4 OKC Enterprises, LLC
2408 N. Meridian Ave.
Oklahoma City, OK 73107
Bonding Limit: $ 750,000 single/$750,000 aggregate
Requested: Class A: Roofing; and Class C: Building Contractor.
Recommendation: 90-day CONDITIONAL approval as:
Class B: Roofing Contractor, pending receipt and endorsement of financial
statements and an updated bond assurance letter with corresponding date.
3. Bishop Construction, LLC
PO Box 851293
Yukon, OK 73085
Bonding Limit: $ 6,000,000 single/$20,000,000 aggregate
Previous Action: August 13, 2025, approved as Class A: Paving; Class B:
Stormwater Contractor.
Recommendation: REMOVE condition regarding financial statements and
bond assurance letter.
4. Built Right Construction, LLC
PO Box 366
Savanna, OK 74565
Bonding Limit: $ 60,000,000 single/$120,000,000 aggregate
Recommendation: GRANT approval as:
Class A: Bridge; and Paving Contractor.
5. C2 Construction, LLC
9317 NW 80th St.
Yukon, OK 73099
Bonding Limit: $ 1,500,000 single/$3,000,000 aggregate
Recommendation: GRANT approval as:
Class C: Building Contractor.
6. C3 Construction, Inc.
1012 N. Mississippi Ave., Ste A
Ada, OK 74820
Bonding Limit: $ 7,500,000 single/$40,000,000 aggregate
Recommendation: GRANT approval as:
Class A: Bridge; and Paving Contractor.
7. Coontz Roofing, Inc.
14708 Santa Fe Crossing Dr.
Edmond, OK 73013
Bonding Limit: $ 10,000,000 single/$25,000,000 aggregate
Recommendation: GRANT approval as:
Class A: Roofing Contractor.
8. Dobson Technologies
14101 Wireless Way, Ste 300
Oklahoma City, OK 73134
Bonding Limit: $ 2,500,000 single/$5,000,000 aggregate
Previous Action: August 13, 2025, approved as Class A: Bore Contractor.
Recommendation: REMOVE condition regarding financial statements and
bond assurance letter.
9. DT Specialized Services, Inc.
703 S. Cherokee St.
Catoosa, OK 74015
Bonding Limit: $ 20,000,000 single/$30,000,000 aggregate
Recommendation: GRANT approval as:
Class A: Demolition Contractor.
10. Globe Construction Company
PO Box 17420
Oklahoma City, OK 73136
Bonding Limit: $ 20,000,000 single/$40,000,000 aggregate
Recommendation: GRANT approval as:
Class A: Building Contractor.
11. H & H Plumbing and Utilities, Inc.
381 W. Adkins Hill Rd.
Norman, OK 73072
Bonding Limit: $ 10,000,000 single/$30,000,000 aggregate
Recommendation: GRANT approval as:
Class A: Bore;
Class B: Stormwater; Water Pipeline; Wastewater Facilities;
Provisional Class B: Wastewater Pipeline;
Class C: Paving; and Wastewater Pipeline Contractor.
12. Iseler Demolition
300 Stoddard Rd.
Kinde, MI 48445
Bonding Limit: $ 750,000 single/$1,500,000 aggregate
Recommendation: GRANT approval as:
Class A: Demolition Contractor.
13. JJ Gonzales Construction, LLC
324 SW 11th St.
Oklahoma City, OK 73109
Bonding Limit: $ 250,000 single/$250,000 aggregate
Recommendation: GRANT approval as Class C: Paving Contractor.
14. Lingo Construction Services, Inc.
1135 N. Robinson Ave.
Oklahoma City, OK 73103
Bonding Limit: $ 125,000,000 single/$250,000,000 aggregate
Requested: Class A: Building; and Paving Contractor.
Recommendation: GRANT approval as:
Class A: Building; and
Class C: Paving Contractor.
15. Monark Construction, LLC
3030 NW Expressway, Ste 300
Oklahoma City, OK 73112
Bonding Limit: $ 500,000 single/$1,000,000 aggregate
Recommendation: GRANT approval as:
Class C: Building Contractor.
16. Pillar Contracting, Inc.
7408 NW 85th St.
Oklahoma City, OK 73132
Bonding Limit: $ 8,500,000 single/$13,000,000 aggregate
Recommendation: GRANT approval as:
Provisional Class A: Building; and
Class B: Building Contractor.
17. Redlands Contracting, LLC
5601 NW 72nd St., Ste 308
Warr Acres, OK 73132
Bonding Limit: $ 20,000,000 single/$40,000,000 aggregate
Recommendation: GRANT approval as:
Class A: Bridge; Paving; and Stormwater Contractor.
18. Rudy Construction Company
PO Box 14575
Oklahoma City, OK 73113
Bonding Limit: $ 50,000,000 single/$100,000,000 aggregate
Previous Action: July 09, 2025, approved as Class A: Paving; Stormwater;
and Streetcar Embedded Rail; Provisional Class B: Building; and Class C:
Building Contractor.
Recommendation: REMOVE condition regarding financial statements and
bond assurance letter.
19. Stryker Asphalt and Seal Coating LLC
15921 Aparados Way
Edmond, OK 73013
Bonding Limit: $ 750,000 single/$750,000 aggregate
Previous Action: July 09, 2025, approved as Provisional Class C: Paving
Contractor.
Recommendation: REMOVE condition regarding financial statements and
bond assurance letter.
20. TMC Construction Company, Inc.
15130 NW Expressway
Piedmont, OK 73078
Bonding Limit: $ 2,500,000 single/$10,000,000 aggregate
Recommendation: 90-day CONDITIONAL approval as:
Class B: Paving; and Stormwater Contractor, pending receipt and
endorsement of financial statements and an updated bond assurance letter
with corresponding date.
21. Triple T Construction and Paving, LLC
6705 N. I-35 Frontage Rd.
Edmond, OK 73034
Bonding Limit: $ 500,000 single/$1,000,000 aggregate
Recommendation: GRANT approval as:
Class C: Paving; and Stormwater Contractor.
22. Turning Point Industries, Inc.
P.O. Box 1805
Blanchard, OK 73010
Bonding Limit: $ 3,000,000 single/$10,000,000 aggregate
Previous Action: June 11, 2025, approved as Class B: Paving; and
Stormwater Contractor.
Recommendation: REMOVE condition regarding financial statements and
bond assurance letter.
23. Urban Contractors, LLC
7113 N. Bryant Ave.
Oklahoma City, OK 73121
Bonding Limit: $ 15,000,000 single/$30,000,000 aggregate
Recommendation: GRANT approval as:
Class A: Bore; Waterwater Pipeline;
Provisional Class B: Stormwater; Water Pipeline; Wastewater Facilities;
Class C: Paving; Stormwater; and Water Pipeline Contractor.
B. And/or Enter into executive session on advice of the Assistant Municipal
Counselor to receive confidential communications from its attorney
concerning a pending investigation, claim, or action, as authorized by 25
O.S. (2024 Supp.) Section 307 (B)(4), because disclosure would seriously
impair the ability of the public body to process the claim or conduct a
pending investigation, litigation, or proceeding in the public interest.
IV. APPLICATIONS REQUIRING SEPARATE VOTE
A. Applications
1. Arrow Contracting & Utilities, LLC
8890 S. Sunnylane Rd.
Norman, OK 73069
Bonding Limit: $ 5,000,000 single/$10,000,000 aggregate
Previous Action: April 9, 2025, conditionally granted approval as Class B:
Stormwater; Provisional Class B: Water Pipeline; Wastewater Pipeline; Class
C: Paving; Water Pipeline; Wastewater Pipeline; and Class D: Bore
Contractor, pending receipt and endorsement of financial statements and an
updated bond assurance letter with corresponding date.
Recommendation: 30-day CONDITIONAL approval as:
Class B: Stormwater; Provisional Class B: Water Pipeline; Wastewater
Pipeline; Class C: Paving; Water Pipeline; Wastewater Pipeline; and Class D:
Bore Contractor, pending receipt and endorsement of financial statements
and an updated bond assurance letter with corresponding date.
2. W.L. McNatt and Company
2000 E. Britton Rd.
Oklahoma City, OK 73131
Bonding Limit: $ 50,000,000 single/$75,000,000 aggregate
Previous Action: April 10, 2024, approved as Provisional Class A: Building;
and Class B: Building, limited Contractor, pending receipt and endorsement
of financial statements and an updated bond assurance letter with
corresponding date. Additionally, per the restrictions set by the
Prequalification Review Board at the January 10, 2024, Show Cause
Hearing, Contractor is restricted from bidding as a prime contractor or
participating as a subcontractor until all outstanding work provided by City
contracts is approved for final acceptance. Thereafter, the Contractor will be
eligible to be granted approval as a Provisional Class A: Building Contractor
for a minimum of one year or until the successful completion of a project
awarded within that year. Contractor is required to appear monthly and
provide updates at the Prequalification Review Board meeting until further
notice.
Recommendation: 30-day CONDITIONAL approval as:
Provisional Class A: Building; and Class B: Building, limited Contractor,
pending receipt and endorsement of financial statements and an updated
bond assurance letter with corresponding date.
The Contractor is restricted from bidding as a prime contractor or
participating as a subcontractor until all outstanding work provided by City
Contracts is approved for final acceptance.
B. And/or Enter into executive session on advice of the Assistant Municipal
Counselor to receive confidential communications from its attorney
concerning a pending investigation, claim, or action, as authorized by 25
O.S. (2024 Supp.) Section 307 (B)(4), because disclosure would seriously
impair the ability of the public body to process the claim or conduct a
pending investigation, litigation, or proceeding in the public interest.
V. INFORMATIONAL ITEMS
A. Expired Prequalification
1. All Hands On Deck, LLC dba Bouldin Construction
6500 NW 110th St.
Oklahoma City, OK 73162
Bonding Limit: $ 500,000 single/$1,000,000 aggregate
Previous Action: September 11, 2024, approved as Class C: Building
Contractor.
2. Metro Water and Sewer, LLC
212 Tulip Trl.
Edmond, OK 73025
Bonding Limit: $ 1,000,000 single/$1,000,000 aggregate
Previous Action: September 11, 2024, approved as Class C: Paving;
Stormwater; Water Pipeline; and Wastewater Pipeline Contractor.
B. Expiration of Conditional Approvals
C. Class D: Bore Administrative Approvals
D. Class D: Paving Administrative Approvals
1. Alpha Structures, Inc. – Renewal
2. Duartes Brothers Concrete, LLC – Renewal
3. Fuab Construction, LLC – Renewal
4. HDZ Concrete Design – New
5. Laras Construction, LLC – Renewal
6. OKC Discount Concrete – New
7. Pinnacle Concrete & Construction, LLC – Renewal
8. Rios Concrete - Renewal
9. Sheppard Concrete – Renewal
10. SS Concrete Construction – Renewal
11. Two G’s Construction – Renewal
12. VM Concrete, Inc. – Renewal
VI. SHOW CAUSE HEARING
VII. COMMENTS FROM BOARD MEMBERS, STAFF AND CITIZENS
VIII ITEMS REQUIRING SEPARATE VOTE
ADJOURN PREQUALIFICATION REVIEW BOARD MEETING